Bezan v. Chrysler Motors Corp.

636 N.E.2d 1079, 263 Ill. App. 3d 858, 201 Ill. Dec. 647, 1994 Ill. App. LEXIS 971
CourtAppellate Court of Illinois
DecidedJune 23, 1994
Docket2—93—0248, 2—93—1165 cons.
StatusPublished
Cited by18 cases

This text of 636 N.E.2d 1079 (Bezan v. Chrysler Motors Corp.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bezan v. Chrysler Motors Corp., 636 N.E.2d 1079, 263 Ill. App. 3d 858, 201 Ill. Dec. 647, 1994 Ill. App. LEXIS 971 (Ill. Ct. App. 1994).

Opinions

PRESIDING JUSTICE INGLIS

delivered the opinion of the court:

In this consolidated appeal, plaintiff, Frank Bezan, contests two separate decisions of the circuit court of Boone County to grant summary judgment to each defendant, J.S. Alberici Construction Company, and J.S. Alberici Management Company (Alberici), and Chrysler Motors Corporation (Chrysler). Plaintiff brought this action to recover damages for personal injuries he sustained while working at Chrysler’s plant. The two issues presented on appeal are whether the trial court properly found that (1) plaintiff was not entitled to the protection of the Structural Work Act (Ill. Rev. Stat. 1987, ch. 48, par. 60 (now 740 ILCS 150/1 (West 1992)), and (2) defendants were not liable for common-law negligence. We dismiss the appeal as to Alberici (No. 2 — 93—0248) and affirm the appeal as to Chrysler (No. 2 — 93—1165).

Plaintiff, a millwright, was hired by Jervis B. Webb (Webb) to install new conveyor lines at the Chrysler assembly plant. The assembly plant was changing the production equipment and assembly tools, or "retooling,” to manufacture new automobile models. Chrysler solicited Webb to install an inverted power and free conveyor throughout the plant. Chrysler employed Alberici to oversee the changeover operation, which included the installation of body shop equipment and robotics.

The conveyor rail, which plaintiff was attempting to install at the time of his accident, is a steel beam that is approximately 4 to 5 inches high, 2 inches wide, 18 feet long, and weighs approximately 300 pounds. Such rails are hung from headers which extend from the ceiling, approximately 10 to 11 feet from the floor. Previously, the rails were installed by three millwrights, one on each end of the rail, and one in the middle. The millwrights would carry the rail up ladders or scaffolding, clamp it to the headers, and weld it once it was properly aligned.

Webb altered the method of installation just prior to the accident in order to accelerate the process. Rather than lifting individual rails, Webb instructed plaintiff to weld two or three rails together and then elevate them with a fork lift. The rails were placed on top of a tool trunk which was then placed on the forks of the forklift in order to raise the beams to the proper height. As the fork was lifted, the rails apparently shifted and pinned plaintiff against a column in the plant, causing his injuries.

Plaintiff sued Alberici and Chrysler for violation of the Structural Work Act (Ill. Rev. Stat. 1987, ch. 48, par. 60 (now 740 ILCS 150/1 (West 1992))) (count I) and for negligence (count II). Numerous claims were filed. Chrysler sued Webb as a third-party defendant, and Webb intervened. Subsequently Webb was dismissed as the third-party defendant. Alberici also counterclaimed against Chrysler. Alberici filed a motion for summary judgment, and on January 26, 1993, the trial court sent a memorandum to each party explaining its decision to grant summary judgment on both counts to Alberici. Counsel was advised to prepare a written order based on this decision. Plaintiff filed his appeal on February 25, 1993. The written order was filed on March 10, 1993. Chrysler filed its motion for summary judgment in September 1993. Plaintiff timely appealed from the order granting Chrysler summary judgment on both counts. Pursuant to plaintiff’s motion, this court ordered the two appeals consolidated. For the following reasons, we must dismiss the appeal as to Alberici.

An appellate court may only hear appeals from final judgments, unless an exception specified by the supreme court rules applies. (Hicks v. Weaver (1994), 255 Ill. App. 3d 650, 652; Official Reports Advance Sheet No. 26 (December 22, 1993), R. 301, eff. February 1, 1994.) Until a written judgment is filed, the proceedings are not finalized. (In re Marriage of Black (1987), 155 Ill. App. 3d 52, 54.) A bare announcement of a final judgment cannot be attacked by motion, cannot be appealed, and cannot be enforced. Black, 155 Ill. App. 3d at 54.

Supreme Court Rule 271 requires that when a court rules on a motion outside the course of a trial, the attorney for the prevailing party must prepare and present to the court an order or judgment to be entered, unless the court directs otherwise. (134 Ill. 2d R. 271.) Supreme Court Rule 272 states that the clerk will make a notation in the record when a written order is presented and that a signed order is final when filed. (134 Ill. 2d R. 272.) Supreme Court Rule 303(a)(1) requires that an appeal must be filed within 30 days after the judgment has become final. (Official Reports Advance Sheet No. 26 (December 22, 1993), R. 303(a)(1), eff. February 1, 1994.) The record indicates that an order was prepared and entered as directed. Plaintiff, however, filed the notice of appeal prior to the entry of the order. Plaintiff failed to file the notice of appeal after the circuit court’s order became final. An order cannot be appealed before it is entered. Therefore, we must dismiss the appeal as to Alberici.

The threshold question in the appeal regarding Chrysler is whether plaintiff is entitled to the protection of the Structural Work Act (Ill. Rev. Stat. 1987, ch. 48, par. 60 (now 740 ILCS 150/1 (West 1992))). Such protection would result if two elements necessary for liability under the Act can be attributed to Chrysler. The pertinent sections of the Act provide:

"1. All scaffolds, hoists, cranes, stays, ladders, supports, or other mechanical contrivances, erected or constructed by any person, firm or corporation in this State for the use in the erection, repairing, alteration, removal or painting of any house, building, bridge, viaduct, or other structure, shall be erected and constructed, in a safe, suitable and proper manner ***.
Sji }|i
9. For any injury to person or property, occasioned by any wilful violations of this Act, or wilful failure to comply with any of its provisions, a right of action shall accrue to the party injured *** by reason of such wilful violation or wilful failure as aforesaid ***.” (Ill. Rev. Stat. 1987, ch. 48, pars. 60, 69 (now 740 ILCS 150/1, 9 (West 1992).)

Plaintiff first argues that the work he performed at Chrysler’s plant constituted an "alteration” of a "structure” within the meaning of the Act. Plaintiff bases this assertion upon the fact that the plant’s interior was essentially gutted, miles of conveyor were installed, permanent fixtures were removed, and the rails, which plaintiff was installing at the time of his accident, were welded to headers, which are permanent parts of the structure. Chrysler contends that the Act does not contemplate the equipment installation of a conveyor system into a structure already built. Chrysler focuses its argument on whether the conveyor system is a structure.

We agree with plaintiff that Chrysler’s argument that the conveyor system was not a structure is unresponsive to plaintiff’s contention that the plant was altered by plaintiff’s construction activity. Whether a structure is "altered” is a matter of statutory construction and, therefore, a question of law. (Compare Innis v. Elmhurst Dodge, Inc. (1985), 107 Ill.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Snow v. Power Construction Co.
2017 IL App (1st) 151226 (Appellate Court of Illinois, 2017)
Snow v. Power Construction Co., LLC
2017 IL App (1st) 151226 (Appellate Court of Illinois, 2017)
SABA Software, Inc. v. Deere and Company
2014 IL App (1st) 132381 (Appellate Court of Illinois, 2014)
SABA Software, Inc. v. Deere & Company
2014 IL App (1st) 132381 (Appellate Court of Illinois, 2014)
SABA Software, Inc. v. Deere & Co.
2014 IL App (1st) 132381 (Appellate Court of Illinois, 2014)
Pestka v. Town of Fort Sheridan Company, LLC
862 N.E.2d 1044 (Appellate Court of Illinois, 2007)
Pestka v. Town of Fort Sheridan Company
Appellate Court of Illinois, 2007
Cochran v. George Sollitt Construction Co.
Appellate Court of Illinois, 2005
Rangel v. Brookhaven Constructors, Inc.
Appellate Court of Illinois, 1999
Ferguson v. Bill Berger Associates, Inc.
704 N.E.2d 830 (Appellate Court of Illinois, 1998)
Apostal v. Oliveri Construction Co.
678 N.E.2d 756 (Appellate Court of Illinois, 1997)
Fancher v. Central Illinois Public Service Co.
664 N.E.2d 692 (Appellate Court of Illinois, 1996)
Bezan v. Chrysler Motors Corp.
636 N.E.2d 1079 (Appellate Court of Illinois, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
636 N.E.2d 1079, 263 Ill. App. 3d 858, 201 Ill. Dec. 647, 1994 Ill. App. LEXIS 971, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bezan-v-chrysler-motors-corp-illappct-1994.