Berwick Solar, LLC v. Public Utilities Commission

Supreme Judicial Court of Maine·Decided September 17, 2026·No. PUC-25-51·Published·LAWRENCE, J.

Opinion

MAINE SUPREME JUDICIAL COURT Reporter of Decisions Decision: 2026 ME 98 Docket: PUC-25-51 Argued: January 7, 2026 Decided: September 17, 2026

Panel: STANFILL, C.J., and MEAD, LAWRENCE, and DOUGLAS, JJ., and HORTON, A.R.J.

BERWICK SOLAR, LLC

v.

PUBLIC UTILITIES COMMISSION et al.

LAWRENCE, J.

[¶1] Berwick Solar, LLC, appeals from an order of the Public Utilities Commission dismissing its complaint against Central Maine Power Company (CMP) alleging that CMP issued final reconciliation statements outside the time periods established in both 65-407 C.M.R. ch. 324, § 15(J) (effective Nov. 20, 2023)1 and the standard-form Interconnection Agreement (IA) that Berwick Solar and CMP entered into under Chapter 324. See 65-407 C.M.R. ch. 324, § 4(A). We affirm.

1 As noted by the Commission in its briefing, none of the parties argue that anything besides the current version of Chapter 324 (effective Nov. 2023) should apply despite Berwick Solar and CMP entering the IA on March 6, 2020. The Commission applied the current version in the order on appeal here. Although the version of Chapter 324 provided by Berwick Solar in the appendix in this case was effective January 9, 2022, we cite the current version of Chapter 324.

I. BACKGROUND

[¶2] The following facts and procedural background are drawn from the administrative record and the Commission’s order dated January 15, 2025. See, e.g., Off. of the Pub. Advoc. v. Pub. Utils. Comm’n, 2023 ME 77, ¶ 2, 306 A.3d 633.

[¶3] On March 6, 2020, Berwick Solar and CMP entered into the IA pursuant to 65-407 C.M.R. ch. 324, § 4(A), which provides the method by which small electric power generators may interconnect with electrical transmission and distribution systems. See 65-407 C.M.R. ch. 324, §§ 1-18. The IA was for Berwick Solar’s photovoltaic generation facility. It estimated total interconnection costs of $65,522 plus SCADA2 costs. Those amounts were based on a feasibility/impact final report dated January 29, 2020. Berwick Solar chose not to obtain a facilities study, which would have provided more detail of the cost of system modifications necessary to connect Berwick Solar’s project to CMP’s electric distribution system. Berwick Solar paid to CMP the estimated cost in the IA in advance of CMP completing the connection to CMP’s

2 Although not defined in the record for this matter, we understand that in the utilities field “SCADA” is an acronym that stands for Supervisory Control and Data Acquisition. See Portland Cellular P’ship v. Town of Cape Elizabeth, 139 F. Supp. 3d. 479, 482 (D. Me. 2015).

electric distribution system. The project was operational in May 2021, and CMP sent Berwick Solar a certification of completion on May 5, 2021.

[¶4] On February 24, 2022, CMP sent Berwick Solar a reconciliation statement pursuant to 65-407 C.M.R. ch. 324, § 15(J) and article 5.1.2 of the IA, seeking $45,502.73 in additional interconnection costs. Upon receiving the statement, Berwick Solar asserted that the statement was time-barred under article 5.1.2 of the IA because CMP failed to issue the statement within ninety days of completing the construction and installation of the interconnection facilities and upgrades.3 In response, CMP pointed Berwick Solar to the default provision found in article 6.6 of the IA4 and stated that Berwick Solar had the

3 Chapter 324 § 15(J) provides for a sixty-day period for a transmission and distribution utility to

issue a final reconciliation statement of actual costs, but article 5.1.2 of the IA contains a ninety-day period. There is no dispute between the parties that CMP did not issue the final reconciliation statement within either of the time periods and, as discussed infra ¶¶ 13-16, we reach the same conclusion under both Chapter 324 and the IA.

4 Article 6.6 of the IA, “Default” provides,

6.61 No Default shall exist where such failure to discharge an obligation (other than the payment of money) is the result of a Force Majeure Event as defined in this Agreement, or the result of an act or omission of the other Party. Upon a Default, the non-defaulting Party shall give written notice of such Default to the defaulting Party.

Except as provided in Article 6.6.2, the defaulting Party shall have sixty calendar days from receipt of the Default notice within which to cure such Default; provided however, if such Default is not capable of cure within sixty calendar days, the defaulting Party shall commence such cure within twenty calendar days after notice and continuously and diligently complete such cure within six months from receipt of the Default notice; and, if cured within such time, the Default specified in such notice shall cease to exist.

6.6.2 If a Default is not cured as provided for in this Article, or if a Default is not capable of being cured within the period provided for herein, the non-defaulting Party

right to notify CMP of a default, including a failure to timely provide the final cost reconciliation statements. CMP also asserted that because CMP had already provided the reconciliation statement, there was no longer any default to cure, and Berwick Solar was required to pay the costs within thirty calendar days of receiving the statement.

[¶5] On January 16, 2023, CMP issued a second cost reconciliation statement, this time seeking $27,655.83—a reduction from the February 2022 reconciliation statement. Finally, on May 19, 2023, CMP issued a third, lower cost reconciliation statement, this time seeking $23,655.83. Berwick Solar maintained its position that the statements were time-barred. It also asserted that the reconciliation statements lacked the necessary written explanation of the significant variation between the statements. Berwick Solar made specific requests in May 2023 for supporting information to explain the costs. CMP responded in June 2023 that it was working on putting together responses to the requests for information, but at the time of the hearing CMP had not responded.

shall have the right to terminate this Agreement by written notice at any time until cure occurs, and be relieved of any further obligation hereunder and, whether or not that Party terminates this Agreement, to recover from the defaulting Party all amounts due hereunder, plus all other damages and remedies to which it is entitled at law or in equity. The provisions of this Article will survive termination of this Agreement.

[¶6] CMP and Berwick Solar had no further contact until April 2024 when CMP sent Berwick Solar a notice of default for nonpayment of $27,655.93. CMP stated that it would regard the claim of default as “on pause” until the impending dispute-resolution process concluded. Berwick Solar and CMP followed the informal dispute-resolution procedure in July 2024, see 65-407 C.M.R. ch. 324, § 17(A)-(B), but could not resolve the dispute. Berwick Solar requested that the dispute proceed to the formal adjudication process established by 65-407 C.M.R. ch. 324, § 17(C).5

[¶7] Following the submission of pre-filed testimony from Berwick Solar and briefs from Berwick Solar and CMP, the Commission held a contested hearing in August 2024. On November 8, 2024, the hearing examiners issued a report recommending that the Commission dismiss Berwick Solar’s complaint. On November 22, 2024, CMP filed comments in support of the hearing examiners’ report, and Berwick Solar filed exceptions to the report.

[¶8] The Commission dismissed Berwick Solar’s complaint in an order dated January 15, 2025. In its order, the Commission concluded that nothing in Chapter 324 or the IA allows it to release Berwick Solar from its obligation to

5 Section 17(C) provides that if the parties cannot resolve a dispute under the informal process,

“then either Party may send written notice to Commission Staff requesting an adjudicatory proceeding.” Article 8 of the IA incorporates the dispute-resolution process contained in Chapter 324.

Free access — add to your briefcase to read the full text and ask questions with AI

Berwick Solar, LLC v. Public Utilities Commission, (Me. 2026).

Berwick Solar, LLC v. Public Utilities Commission (Berwick Solar, LLC v. Public Utilities Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Wescott v. Allstate Insurance
397 A.2d 156 (Supreme Judicial Court of Maine, 1979)
American Protection Insurance v. Acadia Insurance Co.
2003 ME 6 (Supreme Judicial Court of Maine, 2003)
Central Maine Power Company v. Public Utilities Commission
2014 ME 56 (Supreme Judicial Court of Maine, 2014)
Oklahoma Gas and Electric Company v. FERC
11 F.4th 821 (D.C. Circuit, 2021)
Cassidy Holdings, LLC v. Aroostook County Commissioners et al.
2023 ME 69 (Supreme Judicial Court of Maine, 2023)
Office of the Public Advocate v. Public Utilities Commission et al.
2023 ME 77 (Supreme Judicial Court of Maine, 2023)
Office of the Public Advocate v. Public Utilities Commission
2024 ME 11 (Supreme Judicial Court of Maine, 2024)
Snakeroot Solar, LLC v. Public Utilities Commission
2025 ME 64 (Supreme Judicial Court of Maine, 2025)