Bayou Des Familles Development Corp. v. United States Corp.

541 F. Supp. 1025, 13 Envtl. L. Rep. (Envtl. Law Inst.) 20055, 18 ERC (BNA) 1696, 1982 U.S. Dist. LEXIS 18257
CourtDistrict Court, E.D. Louisiana
DecidedApril 20, 1982
DocketCiv. A. 79-4324
StatusPublished
Cited by19 cases

This text of 541 F. Supp. 1025 (Bayou Des Familles Development Corp. v. United States Corp.) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bayou Des Familles Development Corp. v. United States Corp., 541 F. Supp. 1025, 13 Envtl. L. Rep. (Envtl. Law Inst.) 20055, 18 ERC (BNA) 1696, 1982 U.S. Dist. LEXIS 18257 (E.D. La. 1982).

Opinion

CASSIBRY, District Judge:

Plaintiff seeks declaratory and injunctive relief from actions by the federal government which have prevented plaintiff from developing its property. Trial in this matter was held before the court without a jury in October 1981. After considering the pleadings, the voluminous administrative record, the testimony of the witnesses, the documents in evidence, and the law applicable to this case, the court finds in favor of the federal defendants on all claims.

FACTS

Plaintiff Bayou des Families Development Corporation (“BDF”) was formed in August 1972 as a real estate investment venture by several persons who planned to develop and sell approximately 2,000 acres of land located on the West Bank of the Mississippi River in Jefferson Parish, about halfway between New Orleans and Barataría, Louisiana. Much of the property is cypress-tupelo gum swamp and marsh. BDF’s development plan called for the excavation of a canal and construction of a levee and pumping station to drain the area. Portions of the property were to be filled for streets and construction of residences and other structures. The plan called for the blocking of Kenta Canal, a man-made waterway which extends into the subject property and connects at its southerly end with Bayou Barataría, a segment of the Gulf Intracoastal Waterway. The development plan also called for the blocking of Bayou Boeuf, a natural waterway that connects through the Bayou Segnette Waterway to the Gulf Intracoastal Waterway. Both Kenta Canal and Bayou Boeuf have direct hydraulic connections to the Gulf of Mexico and are subject to tidal influence.

The U. S. Army Corps of Engineers (“the Corps”) has been involved in discussions concerning the possible construction of a hurricane protection levee in the vicinity of plaintiff’s property since 1969. BDF designed its levee to follow the contour of- one of the several alternative levee lines proposed by the Corps in 1972 for the West Bank flood control and hurricane protection project.

The federal laws authorizing construction of flood control projects require local assurances of cooperation, hold harmless agreements, and often require some local funding. 33 U.S.C. §§ 701c, 701f. While consultation with appropriate local authorities is important, the sole authority and responsibility for preparing a report recommending a specific project to Congress for approval and funding rests with the Corps. 33 U.S.C. § 701a-l.

BDF obtained the necessary permits from Jefferson Parish for construction of its levee and pumping station. In July 1973, BDF entered into a contract for the construction of a pumping station and sewage treatment plant. On August 16, 1973, BDF entered into a contract for the construction of a levee. The plans for the levee included the digging of a canal to the west of the levee line for fill and transportation of materials and equipment. Construction of the levee and canal system began in August 1973.

*1030 On August 21, 1973, Raymond Condon, Director of the Department of Drainage and Sewerage for Jefferson Parish, wrote a letter to Roy Farmer, an employee of the Corps of Engineers Planning Division, which referred to the BDF levee. The letter forwarded information about the specifications of the BDF levee pursuant to a request from the Federal Insurance Administration, Department of Housing and Urban Development. Mr. Farmer advised him that such a levee would meet certain Corps hurricane protection requirements.

The Planning Division of the Corps’ New Orleans District (“NOD”) has no authority over permitting or regulatory functions. That authority rests with the Permit and Statistics Branch, Operations Division, NOD, which first became aware of BDF’s unauthorized dredge and fill work when review was requested of a report dated October 9, 1973. That report was being forwarded to the office of the Chief Engineer by the Planning Division and concerned reevaluation of base flood elevations for the Harvey Drainage Area in Jefferson Parish.

On October 10, 1973, the District Engineer wrote to Mr. Condon that the levee planned for the Bayou des Families area might be constructed, in part, in wetlands that were navigable waters of the United States, and requested Mr. Condon to furnish the name of the developer or contractor who was constructing the levee. On October 18, 1973, Mr. Condon advised the Corps to contact Wilson Abraham. A certified letter was sent the same day to Mr. Abraham, one of the BDF investors and developers, advising that work on the levee should cease immediately pending a determination as to whether a permit was required.

On October 20, 1973, a letter from the District Engineer was forwarded to BDF advising that its levee construction might require a permit based on the definition of navigable waterways published in the Federal Register on September 9, 1972, and that BDF should supply necessary information for use in determining whether a permit was in fact needed. Moise Steeg replied by letter dated November 8, 1973, requesting that all future correspondence be directed to him as legal counsel for BDF. Also on November 8, Mr. Abraham wrote to the engineering firm of Harris and Varisco, consulting engineer for the levee project, to comment on progress of the levee. He noted that the levee had sunk in many spots, and that the work was not proceeding as expeditiously as the contractor had committed to the previous month.

In January 1974 the Corps issued a cease and desist order to BDF, having heard nothing further from Mr. Steeg. The Corps informed BDF that it had determined that federal permits were required for construction of the levee and canal, including the closures of Bayou Boeuf and Kenta Canal, based on an on-site inspection of the property by the Corps. The levee was approximately 90% complete at that time.

On March 8, 1974, the District Engineer wrote to BDF to direct it to submit a permit application for dredging and filling already done and for work necessary to complete the project. BDF was advised that an Environmental Impact Statement (“EIS”) would have to be prepared before final action could be taken on the permit, due to the potential environmental impact of the proposed project. 42 U.S.C. § 4332(2)(C). On April 4, 1974, BDF suggested to the Corps that by modifying its plans in such a way as not to block Bayou Boeuf, it could avoid Corps jurisdiction entirely. BDF also requested a temporary permit to complete the work already begun. The Corps advised Mr. Steeg that it had no authority to issue a temporary permit. Information before the Corps indicated that Bayou Boeuf had already been blocked.

In February 1975 the United States filed an enforcement action against BDF for violations of Section 10 of the Rivers and Harbors Appropriations Act of 1899 (“RHA”), 33 U.S.C. § 403. United States of America v. Bayou des Families Development Corporation, No. 75-536 (E.D.La.). The proceeding was resolved through entry of a final judgment that required BDF to *1031

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Sweeney
E.D. California, 2020
Permapost Products, Inc. v. McHugh
55 F. Supp. 3d 14 (District of Columbia, 2014)
Barasich v. Columbia Gulf Transmission Co.
467 F. Supp. 2d 676 (E.D. Louisiana, 2006)
United States v. Land
213 F.3d 830 (Fifth Circuit, 2000)
Cristina Investment Corp. v. United States
40 Fed. Cl. 571 (Federal Claims, 1998)
Bayou Des Familles Development Corp. v. United States
130 F.3d 1034 (Federal Circuit, 1997)
West Jefferson Levee D. v. Coast Quality
640 So. 2d 1258 (Supreme Court of Louisiana, 1994)
West Jefferson Levee Dist. v. Coast Quality Const. Corp.
620 So. 2d 319 (Louisiana Court of Appeal, 1993)
DuBois v. Environmental Protection Agency
646 F. Supp. 741 (W.D. Missouri, 1986)
Dubois v. EPA
646 F. Supp. 741 (W.D. Missouri, 1986)
National Wildlife Federation v. Hanson
623 F. Supp. 1539 (E.D. North Carolina, 1985)
United States v. Ciampitti
615 F. Supp. 116 (D. New Jersey, 1984)
United States v. City of Fort Pierre, SD
580 F. Supp. 1036 (D. South Dakota, 1983)
Riverside Irrigation District v. Andrews
568 F. Supp. 583 (D. Colorado, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
541 F. Supp. 1025, 13 Envtl. L. Rep. (Envtl. Law Inst.) 20055, 18 ERC (BNA) 1696, 1982 U.S. Dist. LEXIS 18257, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bayou-des-familles-development-corp-v-united-states-corp-laed-1982.