Riverside Irrigation District v. Andrews

568 F. Supp. 583, 13 Envtl. L. Rep. (Envtl. Law Inst.) 21091, 19 ERC (BNA) 1550, 1983 U.S. Dist. LEXIS 15023
CourtDistrict Court, D. Colorado
DecidedJuly 31, 1983
DocketCiv. A. 80-K-624
StatusPublished
Cited by6 cases

This text of 568 F. Supp. 583 (Riverside Irrigation District v. Andrews) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Riverside Irrigation District v. Andrews, 568 F. Supp. 583, 13 Envtl. L. Rep. (Envtl. Law Inst.) 21091, 19 ERC (BNA) 1550, 1983 U.S. Dist. LEXIS 15023 (D. Colo. 1983).

Opinion

MEMORANDUM OPINION AND ORDER

KANE, District Judge.

This case involves the plaintiffs’ construction of an earth-fill dam on Wildcat Creek in Colorado. Wildcat Creek is a tributary of the South Platte River, which is a tributary of the Missouri River, a navigable water of the United States. Because the construction of the dam involves the placement of fill material into a tributary of navigable waters of the United States, § 404 of the Clean Water Act, 33 U.S.C. § 1344, applies.

*585 An interlocutory appeal was taken from my decision denying the government’s motion to dismiss for lack of jurisdiction. These proceedings challenge the decision of the Army Corps’ Engineer that the dam developers are not entitled to a nationwide temporary permit to discharge sand and gravel during the course of dam construction on a tributary of the South Platte River in Morgan County, Colorado. The Court of Appeals held that the decision of the Army Corps of Engineers that the dam developers were not entitled to the nationwide permit to discharge sand and gravel during the course of construction under nationwide permit regulations was reviewable. A nationwide permit is one covering a category of activities occurring throughout the country which involve discharges of dredged or fill material which will cause only minimal adverse effects on the environment when performed separately and which will have only minimal cumulative effects. Such a permit is automatic in that if one qualifies, no application is needed nor must notice be given before beginning the discharge activity.

As the Court of Appeals stated:

The basic consideration is Section 404 of the Clean Water Act (33 U.S.C. § 1344) and the regulations issued under its authority. The regulations concerned, 33 C.F.R. § 323.4-2, relate to work on the site during the course of construction of the dam, and more particularly to the placement of fill material (discharge of fill material) during construction. As indicated above, the regulations provide for automatic authority to place fill material if certain conditions are met. The regulations do not expressly provide that the Engineer is the one to decide whether the conditions are met and that automatic (nationwide) authority thereby exists. In any event, the Engineer did make such a determination. He decided and advised the plaintiffs that they did not qualify for an automatic permit. He reached a decision and officially advised the plaintiffs. His letter to the parties was as follows:
“Dear Mr. Douglas:
“Reference is made to our previous meetings and discussions regarding the Nationwide Section 404 permit for the Wildcat Creek Dam project.
“Since operation of the proposed reservoir could have an adverse impact on an endangered species (whooping crane), by letter dated 15 September 1978 my predecessor, Colonel James W. Ray, entered into consultation with the US Fish and Wildlife Service.
“Inclosed is a copy of the biological opinion for the project which indicates that the operation of the reservoir is likely to jeopardize continued existence of the whooping crane and adversely modify a 53-mile reach of the Platte River which is critical habitat for the crane. Accordingly, construction of the proposed dam does not qualify for ‘Nationwide’ authorization within the meaning of 33 C.F.R. 323.4-2(a)(1) unless you exercise one of the two alternatives outlined in the biological opinion.
“Should you elect to proceed with construction of the dam, an individual permit processed through the full public interest review will be required.” Riverside Irrigation District v. Stipo, 658 F.2d 762 at 765-66.

It is thus clear that the Engineer did not base his decision on the issue of whether the placement of fill material during the construction of the dam would have an adverse effect on the environment but rather on whether the operation of the dam and the altered water flow would have an adverse impact on an endangered species whose critical habitat exists some 250 to 300 miles downstream. Both the Court of Appeals and the parties before me have assumed without contest that no problems would arise during construction. Virtually no one asserts that the construction work itself will in any way effect the crane habitat. Thus, the issue is whether the Engineer has exceeded his statutory authority. The Court of Appeals remanded the ease to me “.. . for a determination whether the Engineer acted within his authority and to resolve whatever issues may remain.”

*586 A new twist has been added to this case since the opinion of the Court of Appeals. The Corps of Engineers, through Colonel Andrews who is Colonel Stipo’s successor in office and in this litigation, has now attempted to require plaintiffs to apply for an individual permit pursuant to 33 C.F.R. § 323.4-4. A new and more detailed biological opinion was received in April 1982. Relying on that opinion and this other regulation, Colonel Andrews sent a letter in June 1982 ordering the plaintiffs to file for the individual permit. Moreover, Andrews contends that this act cannot be reviewed by the courts because 5 U.S.C. § 701(a)(2) precludes review when “agency action is committed to agency discretion by law.”

Andrews acknowledges that this is a very narrow exception, but argues that in this instance he acted affirmatively to carry out his obligation under a clear mandate of the Endangered Species Act. ' He asserts that the only limit on his authority under 33 C.F.R. § 323.4-4 is that exercise of authority must be based on the concerns of the aquatic environment. Therefore, he urges, there is no legal standard for the court to apply. He further asserts that the case is now moot.

The plaintiffs argue that the issue was, and still is, whether defendant has exceeded his authority under § 404 of the Clean Water Act by considering the downstream effects of the reduced flow on the whooping crane habitat in Nebraska. The case still boils down, they say, to a question of whether the defendant can consider quantity or just quality of the water and, consequently, whether the investigation can include the effects of continuing operation within the ambit of the statutory mandate to consider the construction itself. Plaintiffs «contend, and I agree, that when congress enacted the Clean Water Act, it did not intend to cut off judicial review.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
568 F. Supp. 583, 13 Envtl. L. Rep. (Envtl. Law Inst.) 21091, 19 ERC (BNA) 1550, 1983 U.S. Dist. LEXIS 15023, Counsel Stack Legal Research, https://law.counselstack.com/opinion/riverside-irrigation-district-v-andrews-cod-1983.