Bayou Des Familles Development Corp. v. United States

130 F.3d 1034, 1997 WL 751742
CourtCourt of Appeals for the Federal Circuit
DecidedDecember 8, 1997
DocketNo. 96-5086
StatusPublished
Cited by3 cases

This text of 130 F.3d 1034 (Bayou Des Familles Development Corp. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bayou Des Familles Development Corp. v. United States, 130 F.3d 1034, 1997 WL 751742 (Fed. Cir. 1997).

Opinion

PLAGER, Circuit Judge.

This is a takings case in which Bayou des Families Development Corp. (“BDF”) alleges that the denial by the United States (“the Government”) of a permit to build a levee effected a taking of its property without just compensation, thereby violating the Fifth Amendment of the U.S. Constitution.1 BDF filed suit in the Court of Federal Claims in 1991. That court dismissed the case as time-[1036]*1036barred. Because BDF failed to file suit within the statute of limitations period, we affirm.

BACKGROUND

This takings case has been twenty-five years in the making. BDF is a real estate investment venture by a group of landowners who planned to develop some two thousand acres of land located on the west bank of the Mississippi River in Jefferson Parish. They acquired the property in 1972. Much of it is eypress-tupelo gum swamp and marsh. Their development plan called for extensive canalization, construction of a major levee, and involved blocking of certain existing waterways running through the property. The property is situated in an area where, as early as 1969, the U.S. Army Corps of Engineers (“the Corps”) had been involved in discussions concerning the possible construction of a hurricane protection levee.

Within a year after acquiring the property, BDF, having obtained the necessary permissions from Jefferson Parish, began construction of the levee and canal system. Meanwhile, in October 1972, the Federal Water Pollution Control Act Amendments (“the Act”) were enacted. See 33 U.S.C. § 1251 et seq. (1994) (renamed the Clean Water Act in 1977). In 1974, the Corps, having learned of the levee construction by BDF, issued a cease and desist order to BDF, and informed BDF that federal permits as provided by § 404 of the Act were required for construction of the levee and canal. The levee at that time was approximately 90% complete.

When BDF did not respond as the Government wished, the United States brought an enforcement action against BDF. See United States v. Bayou Des Families Dev. Corp., No. 75-536 (E.D.La.1975). Thereafter, in 1975 BDF applied for an after-the-fact permit. The Corps waited almost four years before issuing a denial of BDF’s application for the permit on September 17, 1979. Several factors contributed to the Corps’ indecision during the intervening years. One was the continuing uncertainty about the placement of the west bank flood control and hurricane protection levee. For example, in 1978 the Corps had presented a number of proposals for the hurricane levee placement to the Jefferson Parish Council. One of these proposals followed the alignment of the BDF levee.

Another consideration was the potential creation of the Jean Lafitte National Historical Park (“the park”) in the vicinity of BDF’s property. In 1972, Congress appropriated funds to study the creation of the park and subsequently established the park by congressional enactment in 1978. See 16 U.S.C. § 230 (1994). The park consists of a “core area,” essentially land which the Government would acquire, and a “park protection zone” of land which would remain in private hands but the uses of which would be regulated by local authorities pursuant to the federal plan. Over 1000 of BDF’s 2000 acres he in the park protection zone.

Following the 1979 denial of its after-the-fact permit, BDF brought suit against the Corps in the federal district court for the Eastern District of Louisiana. In its suit, BDF challenged the authority of the Corps to exercise jurisdiction over its property. It sought to enjoin the Corps’ denial of its permit, and to enjoin the Corps’ recommendation of a levee alignment that differed from its own levee. BDF raised both constitutional and statutory challenges to the Government’s actions. In 1982, the district court upheld the permit denial, rejecting all of BDF’s arguments. With regard to plaintiff BDF’s allegations of a Fifth Amendment taking, the district court concluded its extensive analysis of the issues by saying, “Plaintiffs exclusive remedy for claims of uncompensated takings, through delay or otherwise, if any are present in this case, rests with the Court of Claims under the Tucker Act____ Because plaintiff has an adequate remedy at law for money damages if, indeed, any taking of plaintiffs property has occurred, injunc-tive relief is not appropriate in this case.” Bayou Des Families Dev. Corp. v. United States Corps of Eng’rs, 541 F.Supp. 1025, 1042 (E.D.La.1982) (citations omitted), ajfd, 709 F.2d 713 (5th Cir.1983) (table), cert, denied, 465 U.S. 1065, 104 S.Ct. 1413, 79 L.Ed.2d 739 (1984).2

[1037]*1037Eventually, at the request of Jefferson Parish, the Corps in 1986 granted to the West Jefferson Levee District a permit to construct a hurricane levee. The approved levee alignment substantially differed from BDF’s original plan. The Levee District then filed in Louisiana state court an expropriation suit against BDF for the levee right-of-way. The state trial court awarded BDF something over $15 million.3 The Louisiana Court of Appeals affirmed the judgment. The Levee District sought and obtained review by the Louisiana Supreme Court. That court concluded that the lower courts had substantially overvalued the land since the property had a low likelihood of being develo-pable and correspondingly, a low market value. The fact that the low likelihood was a result of the government’s actions did not, in the court’s view, change the equation. The ease was remanded to the trial court for reassessment of the damages due BDF. See West Jefferson Levee Dist. v. Coast Quality Constr. Corp., 640 So.2d 1258,1284 (La.1994), cert, denied, 513 U.S. 1083,115 S.Ct. 736,130 L.Ed.2d 639 (1995).

While the Louisiana litigation was in progress, BDF filed its suit against the United States in the Court of Federal Claims on July 25, 1991, alleging a taking and demanding just compensation under the Fifth Amendment. The Court of Federal Claims found that the alleged taking first accrued on September 21,1979, the date when the Corps denied BDF’s levee permit. The court dismissed BDF’s complaint as untimely under 28 U.S.C. § 2501 since eleven years had transpired between the accrual of the cause of action and the filing of the suit. See 28 U.S.C. § 2501 (1994) (“Every claim of which the United States Court of Federal Claims has jurisdiction shall be barred unless the petition thereon is filed within six years after such claim first accrues.”).

DISCUSSION

“Ripeness” in takings jurisprudence, and in particular in cases such as this, is a blend of prudential and constitutional concepts. See, e.g., Suitum v. Tahoe Regional Planning Agency, — U.S.-,-& n. 7,117 S.Ct. 1659,1664 & n. 7,137 L.Ed.2d 980 (1997).4- In the federal courts, á dispute must have reached the point at which it can be said that the constitutional requirement of a case or controversy has been met. See U.S. Const, art. III, § 2; see also Buckley v. Valeo,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Beekwilder v. United States
55 Fed. Cl. 54 (Federal Claims, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
130 F.3d 1034, 1997 WL 751742, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bayou-des-familles-development-corp-v-united-states-cafc-1997.