Barge v. St. Paul Fire & Marine Insurance

535 S.E.2d 837, 245 Ga. App. 112, 2000 Fulton County D. Rep. 2802, 2000 Ga. App. LEXIS 759
CourtCourt of Appeals of Georgia
DecidedJune 14, 2000
DocketA00A0363, A00A0364
StatusPublished
Cited by21 cases

This text of 535 S.E.2d 837 (Barge v. St. Paul Fire & Marine Insurance) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barge v. St. Paul Fire & Marine Insurance, 535 S.E.2d 837, 245 Ga. App. 112, 2000 Fulton County D. Rep. 2802, 2000 Ga. App. LEXIS 759 (Ga. Ct. App. 2000).

Opinion

Miller, Judge.

The question in Case No. A00A0363 is whether the adding of a $20 million indemnity claim to a pending $400,000 arbitration proceeding arising out of the same indemnity agreement, which was added with the consent of the arbitration panel, required that a separate arbitration panel be appointed to hear the new claim. The rules stipulated by the arbitration agreement authorized the panel to consider all new claims, and for this reason we answer this question in the negative and affirm. The question in Case No. A00A0364 is whether ordering a supersedeas appellate bond where the court has confirmed the underlying arbitration award but has not entered a written monetary judgment based upon this award is error. We answer this question in the affirmative and vacate the supersedeas bond order.

St. Paul Fire & Marine Insurance Company bonded certain construction projects of Barge-Wagener, Inc. When Barge-Wagener experienced financial difficulties in completing these projects, St. Paul in May 1994 agreed to advance funds to assist if John Barge (a principal in Barge-Wagener) and his wife agreed to turn over their tax refunds — about $400,000 — to St. Paul and agreed to indemnify St. Paul for any costs or losses arising out of these money advances to Barge-Wagener. The parties agreed to arbitrate any disputes related to the agreement “in accordance with the Construction Arbitration Rules of the American Arbitration Association.”

A dispute arose out of the tax refund turnover, resulting in St. Paul filing an arbitration demand with the AAA in January 1995. Per the AAA’s November 1993 rules that were in effect at the time of the *113 arbitration demand (and in effect at the time the agreement was executed), a three-member panel was chosen. While the proceedings were pending, St. Paul moved in May 1996 to amend its arbitration demand to include a new claim for more than $20 million in losses it had incurred in advancing funds to complete the Barge-Wagener projects. The Barges objected, pointing to new rules of the AAA (effective April 1, 1996) which required that construction claims over $1 million be heard by specialized arbitrators from a particular roster. The Barges argued that because no panel member was on that roster, the panel lacked the power to hear the $20 million claim. Over the Barges’ objection, the arbitration panel consented to hear the new claim as a part of the proceedings. In response to an inquiry and arguments by the Barges, the AAA itself confirmed that the panel had the authority to hear the new claim.

The Barges unsuccessfully sought to stay the arbitration proceedings. 1 The panel awarded St. Paul $21,748,310 plus interest. St. Paul immediately applied to the Superior Court of Fulton County to have the award confirmed, and the Barges counterclaimed to vacate it on the ground that the panel lacked the power to hear the $20 million claim. On the same ground, the Barges filed a federal court action to vacate the arbitration award and then moved the superior court to stay its proceeding in deference to the federal proceeding. Denying the stay, the superior court granted St. Paul’s motion for summary judgment and confirmed the award, which order the Barges appeal in Case No. A00A0363. The court then ordered the Barges to post a supersedeas bond of $24 million, which order the Barges appeal in Case No. A00A0364 on the ground that the court never entered a judgment on the award.

Case No. A00A0363

1. The only question in this appeal is whether the court erred in confirming the arbitration award. 2 The Barges contend that the award is invalid because under the Federal Arbitration Act the arbitrators had exceeded their powers, 3 and under the Georgia Arbitration Code they had overstepped their authority. 4

Under both federal and Georgia law, arbitration is a matter of contract, meaning that arbitrators derive their authority to resolve disputes only from the parties’ agreement. 5 Thus, the extent of that *114 authority depends on the language of the contract. 6

The contract here provided:

18. ARBITRATION. Any and all disputes arising out of or in connection with execution or performance of this Agreement, including any breach thereof, shall be resolved through Arbitration in accordance with the Construction Arbitration Rules of the American Arbitration Association. The decision of the arbitrators shall be final and binding upon the parties and enforceable in any court having competent jurisdiction.

At the time the agreement was executed in May 1994, the November 1993 AAA rules were in effect, which provided in Rule 1:

The parties shall be deemed to have made these rules a part of their arbitration agreement whenever they have provided for arbitration by the American Arbitration Association (hereinafter AAA) or under its Construction Industry Arbitration Rules. These rules and any amendment of them shall apply in the form obtaining at the time the demand for arbitration ... is received by the AAA.

In January 1995 when the AAA received St. Paul’s arbitration demand, the November 1993 rules were still in effect. Under Rule 6 of these rules, an arbitration demand is a written notice of an intent to arbitrate, describing the nature of the dispute, the amount involved, the remedy sought, and the hearing locale requested. The party demanding arbitration files with the AAA three copies of the demand, three copies of the arbitration provisions of the contract, and a filing fee. Rule 8 contemplates that after the filing of a claim, either party may assert any new or different claim or counterclaim in the arbitration proceedings if made in writing and filed with the AAA (with a copy to the other party), and if consented to by any arbitrators who may have been appointed before the filing of the new claim. No provision exists to have claims exceeding $1 million heard by specialized arbitrators from a separate roster.

Since St. Paul’s arbitration demand was made in January 1995, the November 1993 rules (incorporated as part of the arbitration agreement) applied per Rule 1 to the arbitration proceedings *115 throughout their life. The April 1996 revisions simply never applied. The November 1993 rules therefore governed the motion by St. Paul in May 1996 to add the $20 million claim to the proceedings. There was no rule which required large claims to be heard by a special group of arbitrators. Rule 8 empowered the arbitration panel to consider the new claim as a part of the proceedings if it consented. The panel consented, and therefore the Barges’ argument that the panel acted beyond its authority must fail. 7

Free access — add to your briefcase to read the full text and ask questions with AI

Related

GREEN TREE SERVICING, LLC v. JONES Et Al.
775 S.E.2d 714 (Court of Appeals of Georgia, 2015)
Adam Gaslowitz v. Stabilis Fund I, Lp
Court of Appeals of Georgia, 2015
Gaslowitz v. Stabilis Fund I, LP
770 S.E.2d 245 (Court of Appeals of Georgia, 2015)
Gary Alessi v. Cornerstone Associates, Inc.
Court of Appeals of Georgia, 2014
Alessi v. Cornerstone Associates, Inc.
765 S.E.2d 630 (Court of Appeals of Georgia, 2014)
Green Tree Servicing, LLC v. Maxwell Jones
Court of Appeals of Georgia, 2014
Joshua James Nanci v. Fortress Group, Inc.
Court of Appeals of Georgia, 2014
Russell Andrew Carbonara v. Fortress Group, Inc.
Court of Appeals of Georgia, 2014
Floyd K. Berger v. John F. Welsh
Court of Appeals of Georgia, 2014
Berger v. Welsh
756 S.E.2d 545 (Court of Appeals of Georgia, 2014)
Grant Nh, LLC v. Jonathan Sule
Court of Appeals of Georgia, 2013
Barngrover v. Hins
657 S.E.2d 14 (Court of Appeals of Georgia, 2008)
Ruskin v. AAF-McQuay, Inc.
643 S.E.2d 333 (Court of Appeals of Georgia, 2007)
Mandl v. Bailey
858 A.2d 508 (Court of Special Appeals of Maryland, 2004)
St. Paul Reinsurance Co., Ltd. v. Ross
596 S.E.2d 193 (Court of Appeals of Georgia, 2004)
Doman v. Stapleton
568 S.E.2d 509 (Court of Appeals of Georgia, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
535 S.E.2d 837, 245 Ga. App. 112, 2000 Fulton County D. Rep. 2802, 2000 Ga. App. LEXIS 759, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barge-v-st-paul-fire-marine-insurance-gactapp-2000.