Ballinger v. Gascosage Electric Cooperative

788 S.W.2d 506, 1990 Mo. LEXIS 44, 1990 WL 45735
CourtSupreme Court of Missouri
DecidedApril 17, 1990
Docket72068
StatusPublished
Cited by45 cases

This text of 788 S.W.2d 506 (Ballinger v. Gascosage Electric Cooperative) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ballinger v. Gascosage Electric Cooperative, 788 S.W.2d 506, 1990 Mo. LEXIS 44, 1990 WL 45735 (Mo. 1990).

Opinions

BLACKMAR, Chief Justice.

The plaintiff, an unskilled electrical construction worker, recovered judgment for $1,500,000 on a jury verdict against Gascos-age Electric Cooperative and its contractor, Tel-Elec Company. Both defendants appealed, and the plaintiff appealed from the refusal of his requested punitive damage instruction.1 The Court of Appeals, Southern District, reversed and remanded for new trial, treating the multiple issues in a comprehensive opinion. It transferred the case to us “because of the general interest and importance of a question involved in the ease or for the purpose of re-examining the existing law.” Mo. Const, art. V, § 10; Rule 83.02. We now assume jurisdiction of the entire case as on initial appeal. We affirm on the appeals of Gascosage and the plaintiff, but reverse and remand for further proceedings on Tel-Elec’s appeal. We borrow freely from Judge Flanigan’s well-crafted opinion without using quotation marks.

1. The Facts

On November 1, 1983, the plaintiff, while working as a “groundman,” was seriously injured by an electrical shock. The accident occurred during the course of a renovation project known as the “Iberia Re-[508]*508phase,” which included the installation of 19 new poles to replace the poles supporting a single phase line carrying 7,200 volts of electricity. The new poles, numbered from west to east, spanned a distance of approximately one mile on the north side of, and generally parallel to, Highway 42 west. The single phase line, consisting of one energized line called the “hot phase” and a “neutral,” was to be replaced by a three phase line consisting of three energized lines, or conductors, and one neutral.

On August 16, 1983, Gascosage and Tel-Elec entered into a contract for Tel-Elec to construct the Iberia Rephase. The contract provided that the work was to be done “hot,” that is, with the three phase line being strung while the “hot phase” of the single phase line remained energized so that the electrical service to customers would not be interrupted.

Eazy Construction Company was not a party to the action but played an important role in the litigated event. The precise business relationship between Tel-Elec and Eazy must be determined by further evi-dentiary hearing, but the parties agree that Eazy, and not Tel-Elec, did all the work on the Iberia Rephase, and that the plaintiff had been hired as a groundman by Eazy on October 28, 1983.

The accident occurred in the afternoon of November 1, 1983. The “A” and “C” conductors had been tightened up and the crew was working on the “B” conductor. To remove the excess slack a lineman up in a “cherry-picker” would attach a rope handline to the conductor. The rope ran through a set of pulleys on the pole to a pickup truck to which it was attached. The truck would pull the slack out of the conductor. The excess length of conductor ran down the backside of the pole, and was rolled up on a wire take-up reel.

At the time of the accident plaintiff was tending the wire take-up reel located near pole 1. He had his left hand on the reel and his right hand on the B conductor. While the B conductor was being pulled by the truck it came into contact with the hot phase at a point between pole 9 and pole 10. It became energized and as a result Ballinger sustained serious and multiple injuries.

Plaintiffs trial theory was that the accident was caused by the negligence of Eazy and that Tel-Elec and Gascosage were both vicariously liable for Eazy’s negligence under the “inherently dangerous activity” doctrine. Basing its verdict on Instruction 8, quoted below, the jury found the issues in favor of plaintiff and against Gascosage and Tel-Elec, finding that they were both responsible for the conduct of Eazy and 100 percent at fault, and that the plaintiff was without fault. The verdict assessed his damages at $1,500,000.

The lengthy jury trial was held in October of 1987. In April of 1985, in a proceeding under the Workers’ Compensation Act, the plaintiff had received a lump sum settlement payment of $90,000 in addition to benefits previously received. The transcript of the hearing at which the compromise settlement was approved lists Balling-er’s employer as “Tel-Electric (sic) d/b/a Eazy Construction Company.” That transcript contains a stipulation, to which the plaintiff and his attorney agreed, that on November 1, 1983, he “while in the employ of Tel-Electric, d/b/a Eazy Construction Company, sustained an accident arising out of and in the course of [his] employment.”

Prior to the jury trial, Tel-Elec moved for summary judgment on the ground that the workers’ compensation settlement was a bar to Ballinger’s civil action against Tel-Elec. The plaintiff requested a separate trial on the “workers’ compensation issues,” as did Tel-Elec. Tel-Elec’s motion stated that it was engaged in a joint venture with Eazy at the time of the accident. The trial court ordered a separate trial as sought, and the jury trial was not concerned with the workers’ compensation issues.

After the verdict was returned, the trial court sustained the plaintiff’s motion for summary judgment against Tel-Elec “on the issue of workers’ compensation immunity,” and denied Tel-Elec’s motion for summary judgment. Judgment was entered in accordance with the verdict against both defendants, with a $100,000 credit for [509]*509a prior settlement with a dismissed party. The three parties filed separate appeals.

2. Submissibility

Gascosage has three specifications as to why it considers that the plaintiff has not made a submissible case. The third, absence of evidence of negligence on the part of Gascosage, is ruled adversely to it for the reasons discussed in Part 3 of this opinion. We conclude that the others also lack merit.

Gascosage first asserts that Tel-Elec breached its contract by assigning its whole performance to Eazy, in violation of the contract provision against subcontracting more than 25% of the work. This argument fails for a number of reasons, the most evident being that the contract permitted subcontracting, rather than forbidding it. Gascosage cannot avoid liability simply because Tel-Elec may have exceeded the boundaries of its permission. See City of New York v. Benenson, 41 Misc.2d 20, 244 N.Y.S.2d 653, 657 (N.Y.Civ.Ct.1963). Cf. Porter v. Thompson, 357 Mo. 31, 206 S.W.2d 509, 511-12 (1947) (Employer still liable for employee’s conduct even though contrary to his orders); Baker v. McGue-Moyle Dev. Co., 695 S.W.2d 906, 912 (Mo.App.1984).2

It next argues that there is no evidence that the activity of installing new conductors in the vicinity of an energized line is an “inherently dangerous activity.” It points to evidence that “hot” installations of this kind are a normal part of the installation and renovation of electrical transmission lines and are regularly done without incident. The essence of inherent danger, however, is the need for special precaution. It is not sufficient for the defendant to show that the work can be done safely. For authority we need go no further than Smith v. Inter-County Telephone Co., 559 S.W.2d 518 (Mo.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

LUCAS HOLTERMAN v. LAVERNE COPELAND
Missouri Court of Appeals, 2024
J.J.'s Bar & Grill, Inc. v. Time Warner Cable Midwest, LLC
539 S.W.3d 849 (Missouri Court of Appeals, 2017)
George Donner v. Alcoa, Inc.
709 F.3d 694 (Eighth Circuit, 2013)
Syn, Inc. v. Beebe
200 S.W.3d 122 (Missouri Court of Appeals, 2006)
Pope v. Pope
179 S.W.3d 442 (Missouri Court of Appeals, 2005)
Maldonado v. Gateway Hotel Holdings, L.L.C.
154 S.W.3d 303 (Missouri Court of Appeals, 2005)
Ruzicka v. Ryder Student Transportation Services, Inc.
145 S.W.3d 1 (Missouri Court of Appeals, 2004)
Bowles v. Weld Tire & Wheel, Inc.
41 S.W.3d 18 (Missouri Court of Appeals, 2001)
Hatch v. V.P. Fair Foundation, Inc.
990 S.W.2d 126 (Missouri Court of Appeals, 1999)
K.C. 1986 Ltd. Partnership v. Reade Manufacturing
33 F. Supp. 2d 820 (W.D. Missouri, 1998)
Laseter v. Griffin
968 S.W.2d 774 (Missouri Court of Appeals, 1998)
Sarasohn & Co. v. Prestige Hotels Corp.
945 S.W.2d 13 (Missouri Court of Appeals, 1997)
Gillespie v. St. Joseph Light & Power Co.
937 S.W.2d 373 (Missouri Court of Appeals, 1996)
Morrissey v. Morrissey
935 S.W.2d 715 (Missouri Court of Appeals, 1996)
Amador v. Lea's Auto Sales & Leasing, Inc.
916 S.W.2d 845 (Missouri Court of Appeals, 1996)
Parker v. Springfield Railway Services/Anheuser-Busch, Inc.
897 S.W.2d 103 (Missouri Court of Appeals, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
788 S.W.2d 506, 1990 Mo. LEXIS 44, 1990 WL 45735, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ballinger-v-gascosage-electric-cooperative-mo-1990.