Automobile Insurance Co. of Hartford v. United H.R.B. General Contractors, Inc.

876 S.W.2d 791, 1994 Mo. App. LEXIS 697, 1994 WL 145078
CourtMissouri Court of Appeals
DecidedApril 26, 1994
Docket64060
StatusPublished
Cited by14 cases

This text of 876 S.W.2d 791 (Automobile Insurance Co. of Hartford v. United H.R.B. General Contractors, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Automobile Insurance Co. of Hartford v. United H.R.B. General Contractors, Inc., 876 S.W.2d 791, 1994 Mo. App. LEXIS 697, 1994 WL 145078 (Mo. Ct. App. 1994).

Opinion

AHRENS, Judge.

In this subrogation action to recover for property damage arising from a fire, the trial court sustained defendants’ motions for summary judgment and entered judgment for defendants. Plaintiff appeals. We reverse and remand.

In its petition, plaintiff alleged that it was a subrogated insurer of First Baptist Church of Jefferson City (First Baptist) and that it was required to pay $4,835,468.25 under its policies due to property damage sustained by First Baptist in a fire that took place on May 24, 1987. Plaintiffs petition alleged the fire was the result of the faulty installation of an electrical system and alleged alternate theories of general negligence, specific negligence and breach of contract and warranty.

Defendants filed motions for summary judgment which the trial court sustained. The trial court had before it materials submitted by the joint stipulation of the parties. These materials included the contract between First Baptist and defendant United H.R.B. General Contractors, Inc. (United H.R.B.), the General Conditions of that contract, and the subcontract between United H.R.B. and defendant Richard A. Howerton, Inc. (Howerton). In addition, the stipulation included affidavits as to the facts, the deposition of First Baptist’s building committee chairman, and the insurance policy. Also included were documents concerning the completion of the construction project, final payment and the final payment check.

The sequence of events relevant to this appeal are as follows: First Baptist entered into a contract for the construction of a new sanctuary and educational facilities with defendant United H.R.B. on March 12, 1984. United H.R.B. then subcontracted the electrical work to defendant Richard A. Hower-ton, Inc. The project was substantially completed on or about September 30, 1985. First Baptist dedicated the new facilities in October, 1985. First Baptist purchased its insurance policy from plaintiff, the effective dates of which were June 1, 1986 through June 1,1987. Final payment on the contract was made on December 22, 1986. The fire occurred on May 24, 1987.

Plaintiffs initial point on appeal is that the trial court erred in sustaining defendants’ motions for summary judgment and barring plaintiffs action. In support, plaintiff lists six separate subpoints as bases for the alleged error. In subpoint two, plaintiff claims the contract was ambiguous as to the duration of the waiver of liability. We find this point dispositive of the appeal.

Defendants’ motions for summary judgment relied primarily on the following provisions of the contract between First Baptist and defendant United H.R.B. Subparagraph 11.3.1 reads in part as follows:

Unless otherwise provided, the Owner shall purchase and maintain property insurance upon the entire Work at the site to the full insurable value thereof.

Subparagraph 11.3.6 reads as follows:

The Owner and Contractor waive all rights against (1) each other and the Subcontractors, Subcontracting agents and employees each of the other, and (2) the Architect and separate contractors, if any, and their subcontractors, sub-subcontractors, agents and employees for damages caused by fire or other perils to the extent covered by insurance obtained pursuant to this Paragraph 11.3 or any other property insurance applicable to the Work, except such rights as they may have to the proceeds of such insurance held by the Owner as trustee. *793 The foregoing waiver afforded the Architect, his agents and employees shall not extend to the liability imposed by Subpara-graph 4.18.3. The Owner or the Contractor, as appropriate, shall require of the Architect, separate Contractors, Subcontractors and Sub-subcontractors by appropriate agreements, written where legally required for validity, similar waivers each in favor of all other parties enumerated in this Subparagraph 11.3.6.

Subparagraph 1.1.3, which defines “work”, reads as follows:

The Work comprises the completed construction required by the Contract Documents and includes all labor necessary to produce such construction, and all materials and equipment incorporated or to be incorporated in such construction.

In their motions for summary judgment, defendants’ position was that the above provisions exonerated and discharged United H.R.B. from any claim by plaintiff based on fire damage done to the church as a result of construction activity, even though the fire occurred after final payment on the contract. The trial court agreed and found, as a matter of law, defendants were entitled to summary judgment.

An appellate court’s review of a summary judgment is fundamentally de novo. ITT Commercial Finance Corp. v. Mid-America Marine Supply, 854 S.W.2d 371, 376 (Mo. banc 1993). Our criteria for testing the propriety of summary judgment are the same as those employed by a trial court determining in the first instance the propriety of sustaining the motion. Id. “The burden on a summary judgment movant is to show a right to judgment flowing from facts about which there is no genuine dispute.” Id. at 378. “The key to summary judgment is the undisputed right to judgment as a matter of law; not simply the absence of a fact question.” Id. at 380.

In the present case, there is little dispute as to the facts. The issue is whether the language of the construction contract created a waiver of subrogation which extended after completion of the project and final payment on the contract. Plaintiffs position is that the trial court misconstrued the terms of the contract in ruling that defendants were entitled to summary judgment as a matter of law. We agree.

First Baptist purchased its insurance policy from plaintiff on June 1, 1986, approximately seven months prior to final payment on the project. The policy had a duration of one year. Of particular importance in this case is the fact that the fire occurred after completion of the project and final payment on the contract, but before the policy’s term had elapsed.

Plaintiff argues that there is no specific and express provision in the contract which unequivocally creates a waiver of subrogation which continues after final payment. Plaintiff also argues that the waiver of subrogation clause, subparagraph 11.3.6, when considered in the context of the whole contract, is ambiguous as to duration.

Defendants’ position is (1) under Subpara-graph 11.3.1, First Baptist was obligated to provide property insurance as long as defendants retained an insurable interest in the property; (2) the contract expressly and unambiguously waived the right of each party to assert claims against the other to the extent that those claims were covered by insurance; (3) that waiver applies for the entire term of the policy, i.e., “claims against the contractor are barred only so long as the owner retains insurance on the property;” and (4) having chosen to provide insurance beyond that required by the contract, First Baptist and plaintiff, its insurer, are bound by that choice and the resulting waiver.

Our inquiry is whether the contract was so clear and unambiguous as to entitle defendants to summary judgment as a matter of law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Groves v. Layton
Court of Appeals of Arizona, 2024
Haren & Laughlin Construction Co. v. Jayhawk Fire Sprinkler Co.
330 S.W.3d 596 (Missouri Court of Appeals, 2011)
John L. Mattingly Construction Co. v. Hartford Underwriters Insurance
999 A.2d 1066 (Court of Appeals of Maryland, 2010)
Hartford Underwriters Insurance v. Phoebus
979 A.2d 299 (Court of Special Appeals of Maryland, 2009)
Acuity v. Interstate Construction, Inc., 2007-P-0074 (3-7-2008)
2008 Ohio 1022 (Ohio Court of Appeals, 2008)
TX. C.C., Inc. v. Wilson/Barnes General Contractors, Inc.
233 S.W.3d 562 (Court of Appeals of Texas, 2007)
Lumbermens Mutual Casualty Co. v. Grinnell Corp.
477 F. Supp. 2d 327 (D. Massachusetts, 2007)
Colonial Properties Realty Ltd. Partnership v. Lowder Construction Co.
567 S.E.2d 389 (Court of Appeals of Georgia, 2002)
Town of Silverton v. Phoenix Heat Source System, Inc.
948 P.2d 9 (Colorado Court of Appeals, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
876 S.W.2d 791, 1994 Mo. App. LEXIS 697, 1994 WL 145078, Counsel Stack Legal Research, https://law.counselstack.com/opinion/automobile-insurance-co-of-hartford-v-united-hrb-general-contractors-moctapp-1994.