Haren & Laughlin Construction Co. v. Jayhawk Fire Sprinkler Co.

330 S.W.3d 596, 2011 Mo. App. LEXIS 66, 2011 WL 204327
CourtMissouri Court of Appeals
DecidedJanuary 25, 2011
DocketWD 72333
StatusPublished
Cited by4 cases

This text of 330 S.W.3d 596 (Haren & Laughlin Construction Co. v. Jayhawk Fire Sprinkler Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Haren & Laughlin Construction Co. v. Jayhawk Fire Sprinkler Co., 330 S.W.3d 596, 2011 Mo. App. LEXIS 66, 2011 WL 204327 (Mo. Ct. App. 2011).

Opinion

THOMAS H. NEWTON, Presiding Judge.

Harén & Laughlin Construction Company, Inc. (H & L) appeals a summary judgment in favor of Jayhawk Fire Sprinkler Co., Inc. (Jayhawk). H & L, through its insurance company, paid for damages to a facility caused by a sprinkler system that Jayhawk, its subcontractor, had installed. H & L sued Jayhawk for remuneration under several theories including indemnity. Jayhawk claimed that it did not have to remunerate H & L because under then-contract, Jayhawk did not have to pay for damages covered by H & L’s insurance policy. Both parties moved for summary judgment. The circuit court denied H & L’s motion and granted Jayhawk’s. We reverse and remand.

Factual and Procedural Background

H & L was hired by KCHR Senior Care, LLC (KCHR) to build a senior living facility. KCHR and H & L executed a General Contract that required H & L to indemnify KCHR against all liabilities arising from “any defect in the Work or equipment or materials used to perform the Work” and in several other circumstances in which H & L or its subcontractors were at fault. In section 3.18.4, the parties then waived “their respective rights of recovery against each other for Injuries covered by the standard Causes of Loss — Special Form (formerly ‘All Risk’) and Business Income insurance policies *598 used in the state where the Project is located at the time the Injury is incurred.”

H & L then hired Jayhawk to install fire sprinklers and perform all necessary tasks associated with installing and maintaining a fire sprinkler system such as complying with the applicable codes. H & L and Jayhawk executed a Subcontract that required Jayhawk to indemnify H & L against “all liability, loss, cost damage or expense arising out of its failure” to replace parts of the project and its content damaged or moved as a result of “defect in material or workmanship” within a year of final acceptance of the project. In paragraph 3, the parties agreed that H & L had the “same rights and privileges hereunder against [Jayhawk] in relation to the work hereunder” as KCHR had against H & L “under the General Contract.”

Subsequently, KCHR accepted the project on November 26, 2007. A few weeks later, on December 6, 2007, “a leak occurred in a fitting connecting the sprinkler line to a sprinkler head,” causing damage to the floors and the furniture of the facility. KCHR informed H & L, who paid for the damages through its insurer. H & L filed a claim against Jayhawk’s insurer but was unsuccessful. Jayhawk refused to reimburse H & L because H & L’s insurer was responsible for covering the damages. H & L brought a subrogation action against Jayhawk; the petition contained nine counts including negligence, breach of contract, and indemnification. Jayhawk filed an answer, alleging several affirmative defenses.

Thereafter, the parties entered into a stipulation of undisputed facts as stated above. H & L filed a motion for summary judgment on its breach of contract claims. Jayhawk also filed a motion for summary judgment on the affirmative defense of waiver of subrogation rights/claim. The trial court found that language within the Subcontract incorporated the waiver of subi'ogation rights from the General Contract, which barred the subrogation action against Jayhawk. Consequently, the trial court granted Jayhawk summary judgment. H & L appeals.

Standard of Review

Our review of a trial court’s decision to grant summary judgment is de novo. Nodaway Valley Bank v. E.L. Crawford Constr., Inc., 126 S.W.3d 820, 823 (Mo.App. W.D.2004). In determining the propriety of the summary judgment, we use the same criteria the circuit court used in determining whether to grant summary judgment: a movant must show that there is no genuine dispute as to the material facts and that it was entitled to judgment as a matter of law. Id. at 823-24. We view the record and any accompanying reasonable inferences in the light most favorable to the non-movant. ITT Commercial Fin. Corp. v. Mid-Am. Marine Supply Corp., 854 S.W.2d 371, 382 (Mo. banc 1993). The movant has the burden of proving that no genuine issue of material fact exists and that it has a right to judgment as a matter of law. Nodaway, 126 S.W.3d at 824; ITT, 854 S.W.2d at 382.

Legal Analysis

In its first point, H & L argues that the trial court erred in finding that H & L waived its rights to subrogation because it disregarded paragraph 19 of the Subcontract requiring Jayhawk to indemnify H & L. In its second, third, and fourth points, H & L argues that the trial court erred in finding that H & L waived its right to subrogation because it misinterpreted the Subcontract by disregarding its plain and unequivocal language. Because these points challenge the trial court’s interpretation of the Subcontract, we discuss them together.

*599 To receive summary judgment for its affirmative defense of waiver of subrogation, Jayhawk had to show: (1) a contractual provision waiving H & L’s right to subrogation to claims covered by insurance, (2) H & L’s contractual obligation to maintain insurance was effective at the time of property damages, and (3) the property damages were covered under that required property insurance. See Butler v. Mitchell-Hugeback, 895 S.W.2d 15, 21-22 (Mo. banc 1995); see also Knob Noster R-VIII Sch. Dist. v. Dankenbring, 220 S.W.3d 809, 818-19; Nodaway, 126 S.W.3d at 826, 828, 831.

The trial court found that paragraph 3 of the Subcontract clearly granted H & L the same rights against Jayhawk as KCHR had against H & L under the General Contract. It further found that under the General Contract, section 3.18.4.2, KCHR waived any rights of subrogation to claims covered by insurance against H & L, and “specifically, [the] ‘Contractor Party,’ which included any subcontractors, expressly or impliedly as a third-party beneficiary of the General Contract.” It concluded that because H & L had no greater rights against Jayhawk under the Subcontract than existed under the General Contract, H & L’s claims were barred under the waiver of subrogation rights pursuant to section 3.18.4 of the General Contract.

We interpret contracts to ascertain the parties’ intent and give effect to that intent. Nodaway, 126 S.W.3d at 825. In doing so, we assign the plain and ordinary meaning to the terms of the contract and “consider the document as a whole.” Id. (internal quotation marks and citation omitted). An instrument that incorporates specific sections of another instrument must be construed together with the original instrument, but such construction is limited to the incorporated language’s specified purpose. Wilson Mfg. Co. v. Fusco,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
330 S.W.3d 596, 2011 Mo. App. LEXIS 66, 2011 WL 204327, Counsel Stack Legal Research, https://law.counselstack.com/opinion/haren-laughlin-construction-co-v-jayhawk-fire-sprinkler-co-moctapp-2011.