ACE American Insurance Company v. Toledo Engineering Co., Inc.

CourtDistrict Court, E.D. Michigan
DecidedJanuary 30, 2023
Docket2:18-cv-11503
StatusUnknown

This text of ACE American Insurance Company v. Toledo Engineering Co., Inc. (ACE American Insurance Company v. Toledo Engineering Co., Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ACE American Insurance Company v. Toledo Engineering Co., Inc., (E.D. Mich. 2023).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF MICHIGAN SOUTHERN DIVISION

ACE AMERICAN INSURANCE COMPANY, et al., Case No. 18-11503 Honorable Nancy G. Edmunds Plaintiffs, Magistrate Judge David R. Grand v. TOLEDO ENGINEERING CO., INC., and DREICOR, INC.,

Defendants. _______________________________/

OPINION AND ORDER GRANTING DEFENDANTS’ MOTIONS FOR PARTIAL SUMMARY JUDGMENT [88, 89]

This case stems from a large explosion and resulting fire at a glass factory operated by Guardian Industries, LLC (“Guardian”). Plaintiffs are insurers who bring this suit as subrogees of Guardian against the defendant-contractors whom Plaintiffs deem responsible for the incident (“Plaintiff-Insurers”). In their complaint, they allege negligence, gross negligence, breach of contract, and breach of warranty. On February 27, 2019, Defendants Toledo Engineering Co., Inc. (“TECO”) and Dreicor, Inc. (“Dreicor”) moved for partial summary judgment arguing that the waivers of subrogation clauses in the contracts they each had with Guardian bar all causes of action against them except those arising from gross negligence. (ECF Nos. 41, 42.) The Honorable Arthur J. Tarnow denied the motions without prejudice so as to give the parties adequate time for discovery. (ECF No. 56.) The case has since been transferred to the undersigned, and the parties have had an opportunity to engage in discovery. Defendants now bring renewed motions for partial summary judgment on the same issue of subrogation. (ECF Nos. 88, 89.) Plaintiffs filed responses in opposition to Defendants’ motions and Defendants filed replies to those responses. (ECF Nos. 92, 93, 94, 95.) Upon review of the pleadings and record, the Court finds its decision would not be aided by oral argument on Defendants’ motions. Accordingly, the Court declines to hold a hearing and the motions will be decided on the briefs. See E.D. MI L.R. 7.1(h).

For the reasons that follow, Defendants motions for partial summary judgment are GRANTED. I. Background In 2015 and 2016, Guardian retained TECO and Dreicor to perform a renovation of the glass furnace and associated equipment at Guardian’s glass manufacturing plant in DeWitt, Iowa (the “Project”). (ECF No. 93, PageID.2606.) TECO and Dreicor began to work on the Project in the spring of 2017 and had finished the portion of work known as “Cold Tank Repair” at some point before June 3, 2017. (ECF No. 93-3, PageID.2680.) On that date, a large explosion and fire occurred at Guardian’s plant causing extensive

damage. Investigations revealed that the explosion was caused from a gas release when the coupling Dreicor installed just weeks before separated. (ECF No. 93, PageID.2613.) Both TECO and Dreicor were involved in work performed on the gas line. (Id. at PageID.2612.) Following the explosion, Plaintiff-Insurers issued payments to or on behalf of Guardian in the amount of $80,000,000 to cover property damage and other losses. (ECF No. 93, PageID.2613.) Plaintiff-Insurers then filed the present lawsuit to recoup that money paid. At issue is whether the contracts between Guardian and TECO and Guardian and Dreicor permit Plaintiff Insurers’ subrogation claims for negligence, breach of contract, and breach of warranty.1 II. Legal Standard “Summary judgment is proper only if the moving party shows that the record does not reveal a ‘genuine dispute as to any material fact and the movant is entitled to

judgment as a matter of law.’” Benison v. Ross, 765 F.3d 649, 658 (6th Cir. 2014) (quoting FED. R. CIV. P. 56(a)). A genuine issue of material fact exists when there are “disputes over facts that might affect the outcome of the suit under the governing law.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). But “[w]here the record taken as a whole could not lead a rational trier of fact to find for the non-moving party, there is no genuine issue for trial.” Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587 (1986) (citing First Nat. Bank of Ariz. v. Cities Servs. Co., 391 U.S. 253, 289 (1968)). In reviewing a motion for summary judgment, a court must view the evidence in the light most favorable to the non-moving party and refrain from weighing

the evidence itself, or making credibility judgments. Gen. Motors Corp. v. Lanard Toys, Inc., 468 F.3d 405, 412 (6th Cir. 2006) (citing Bennett v. City of Eastpointe, 410 F.3d 810, 817 (6th Cir.2005)). III. Analysis A. Plaintiffs’ Claims Against TECO Plaintiff-Insurers’ Complaint alleges three causes of action against TECO: (1) Negligence and/or Gross Negligence (Count 1); Breach of Contract (Count 2); and Breach of Express and/or Implied Warranty (Count 3). TECO argues that each of these

1 Defendants address Plaintiffs’ gross negligence claim in separate motions that the Court will decide at a later date. (See ECF Nos. 97, 99.) causes of action, except for gross negligence, must be dismissed as the comprehensive contract between Guardian and TECO (the Engineering Service Agreement, or “ESA”) contains a mutual waiver of subrogation clause. (ECF No. 88, PageID.1789.) Plaintiff- Insurers argue against summary dismissal of these claims for three reasons. First, they argue the ESA did not apply to the Project and thus, there was no waiver of

subrogation. (ECF No. 93, PageID.2605.) Alternatively, Plaintiff-Insurers argue that even if the ESA applied to the Project, that TECO’s motion should still be denied as the ESA only applied to the “engineering” and “design” services that TECO performed for Guardian, not the project management or administration services that TECO also provided. (Id. at PageID.2605-06.) Finally, Plaintiff-Insurers argue that even if the ESA applies, the waiver of subrogation does not apply as it is inapplicable to damages that occurred once the Project was complete. (Id. at PageID.2606.) The Court takes each of these arguments in turn. 1. The operative contract is the ESA

On December 20, 2016, months before the June 3, 2017 explosion, Guardian and TECO executed the Engineering Services Agreement (“ESA”). (ECF No. 88-4.) The ESA includes a choice-of-law provision that establishes State of Michigan laws as governing. (Id. at PageID.1852.) It further establishes its “Purpose and Use” as follows: Guardian and TECO are entering into this Agreement to establish the terms and conditions on which Guardian may purchase services (including services to be performed at Guardian’s facilities) from TECO as an independent contractor, as the Parties may agree from time to time in one or more statements of work . . . which will not be binding until signed by both Parties . . . This Agreement supersedes and replaces any standard terms or forms that TECO or Guardian may submit to the other, whether submitted in a quote, purchase order or otherwise. (ECF No. 88-4, PageID.1844.) Importantly, the ESA also includes the following waiver of subrogation clause: Guardian and TECO waive all rights against each other . . . for damages caused by fire or other causes of loss to the extent covered by insurance obtained pursuant to this Section or other insurance applicable to the Services. The policies shall provide such waivers of subrogation by endorsement or otherwise.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Donald Bennett v. City of Eastpointe
410 F.3d 810 (Sixth Circuit, 2005)
Hartford Underwriters Insurance v. Phoebus
979 A.2d 299 (Court of Special Appeals of Maryland, 2009)
Old Kent Bank v. Sobczak
620 N.W.2d 663 (Michigan Court of Appeals, 2000)
Yerkovich v. AAA
610 N.W.2d 542 (Michigan Supreme Court, 2000)
Lamp v. Reynolds
645 N.W.2d 311 (Michigan Court of Appeals, 2002)
Michigan Mutual Insurance v. Dowell
514 N.W.2d 185 (Michigan Court of Appeals, 1994)
Citizens Insurance Co. of America v. American Community Mutual Insurance
495 N.W.2d 798 (Michigan Court of Appeals, 1993)
Trinity Universal Insurance Co. v. Bill Cox Construction, Inc.
75 S.W.3d 6 (Court of Appeals of Texas, 2002)
Safeco Insurance Co. of America v. CPI Plastics Group, Ltd.
625 F. Supp. 2d 508 (E.D. Michigan, 2008)
Kathleen Benison v. George Ross
765 F.3d 649 (Sixth Circuit, 2014)
Kyocera Corp. v. Hemlock Semiconductor, LLC
886 N.W.2d 445 (Michigan Court of Appeals, 2015)
In re: Automotive Parts Antitrust Litig.
997 F.3d 677 (Sixth Circuit, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
ACE American Insurance Company v. Toledo Engineering Co., Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/ace-american-insurance-company-v-toledo-engineering-co-inc-mied-2023.