Austin Bridge Company v. State

427 S.W.2d 925, 1968 Tex. App. LEXIS 2598
CourtCourt of Appeals of Texas
DecidedApril 24, 1968
Docket11596
StatusPublished
Cited by11 cases

This text of 427 S.W.2d 925 (Austin Bridge Company v. State) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Austin Bridge Company v. State, 427 S.W.2d 925, 1968 Tex. App. LEXIS 2598 (Tex. Ct. App. 1968).

Opinion

HUGHES, Justice.

This suit was brought by Austin Bridge Company, Austin Contracting Company and B. G. Brown and Company, pursuant to legislative permission, 1 against the State of Texas and the Texas Highway Department to recover damages allegedly arising out of a contract entered into between Austin Bridge Company as prime contractor and the Texas Highway Department for the construction of a portion of State Highway No. 120 in Taylor County. The resolution authorizing this suit recites that the prime contractor and B. G. Brown of B. G. Brown and Company, a subcontractor, contend that the Texas Highway Department imposed additional burdens upon the contractors not contemplated by the contract and arbitrarily charged working days against the contractor, resulting in the imposition of liquidated damage penalties, when such charges were not justified.

The case was tried to a jury but upon the evidence being closed the trial court, upon appellees’ motion, withdrew the case from the jury and rendered judgment that appellants take nothing by their suit.

Appellants’ first three points, jointly briefed, are that the instructed verdict was erroneous for the reason that they were improperly charged working days ..during the period specified in the contract when the placing of asphalt was suspended resulting in the wrongful imposition of liquidated damages, and that the evidence either conclusively or factually so showed.

We copy the following general provisions of the contract in suit the consideration of which are relevant to a determination of these points:

“1.30 Working Day. A working day is defined as a calendar day, not including *927 Saturdays, Sundays, or legal holidays in which weather or other conditions not under the control of the Contractor will permit the performance of the principal unit or work underway for a continuous period of not less than seven (7) hours between 7 a. m. and 6 p. m., except for every Saturday on which the Contractor chooses to work, one day will be charged against the contract working time when weather conditions will permit seven (7) hours of work as delineated above. Nothing in this special provision shall be construed as prohibiting the Contractor from working on Saturdays if he so desires.
⅜ * ⅜ * * *
8.2. Prosecution of Work. Prior to beginning construction operations, the Contractor shall submit to the Engineer a chart or brief outlining the manner of prosecution of the work that he intends to follow in order to complete the contract within the allotted time.
No asphaltic materials or mixtures except Emulsions and cut-back asphalts shall be placed between October 1 and April 1, unless specifically authorized or directed by the Engineer in writing.
⅜ ⅜ ⅛ ⅜ ⅜ ⅜
8.4. Temporary Suspension of Work. The Engineer will have authority to suspend the work, wholly or in part, for such period as he may consider necessary, and the ‘Time Charge’ will be suspended during such period. Notice of such suspension with the reasons therefor will be given the Contractor in writing. The Contractor shall not suspend work without written authority of the Engineer.
8.5. Computation of Contract Time for Completion. The Contractor shall complete the work within the number of working days stated in the contract. For the purpose of computation, working days will be considered fifteen (IS) days after the date of the written authorization by the Engineer to begin work.
The Engineer will furnish the Contractor a monthly statement on forms furnished by the Department, showing number of working days charged during the month, total number of working days allowed in contract, and the working days remaining under the contract. The Contractor will be allowed ten (10) days in which to protest the correctness of the statement, otherwise the statement will stand. If the satisfactory completion of the contract shall require unforeseen work or work and materials in greater amounts of quantities than those set forth in the contract, then additional working days or suspension of time charge will be allowed the Contractor equal to the time which, in the opinion of the Engineer, the work as a whole is delayed.
8.6.Failure to Complete Work on Time. If the Contractor fails to complete the contract in the working days specified, the time charge will be made for each working day thereafter.
The time set forth in the Proposal for the completion of the work is an essential element of the contract. For each working day under the conditions described in the preceding paragraph that any work shall remain uncompleted after the expiration of the working days specified in the contract, together with any additional working days allowed, the amount per day given in the following schedule will be deducted from the money due or to become due the Contractor, not as a penalty, but as liquidated damages and added expense for engineering supervision :
5.1. Authority of Engineer. The work will be done under the supervision *928 of the Engineer, to his satisfaction, and in accordance with the contract, plans and specifications. The Engineer will decide all questions which may arise as to the quality or acceptability of materials furnished and work performed; the manner of performance and rate of progress of the work; the interpretations of the plans and specifications; and the acceptable fulfillment of the contract on the part of the Contractor. His decisions will be final, and he will have executive authority to enforce and make effective such decisions and orders as the Contractor fails to carry out promptly.
5.2. Engineer as Referee.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

in the Estate of Adel Sheshtawy
Court of Appeals of Texas, 2015
Kodiak 1981 Drill v. Delhi Gas Pipeline
736 S.W.2d 715 (Court of Appeals of Texas, 1987)
Kodiak 1981 Drilling Partnership v. Delhi Gas Pipeline Corp.
736 S.W.2d 711 (Court of Appeals of Texas, 1987)
State v. Clark
695 S.W.2d 673 (Court of Appeals of Texas, 1985)
Huey v. Davis
556 S.W.2d 860 (Court of Appeals of Texas, 1977)
City of Houston v. Gribble
542 S.W.2d 242 (Court of Appeals of Texas, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
427 S.W.2d 925, 1968 Tex. App. LEXIS 2598, Counsel Stack Legal Research, https://law.counselstack.com/opinion/austin-bridge-company-v-state-texapp-1968.