Atlas Elec. Constr. Inc. v. Flintco, LLC

550 P.3d 881
New Mexico Court of Appeals·Decided March 18, 2024·No. A-1-CA-40100·Published·Cited by 2 cases

Opinion

Office of the New Mexico Director Compilation Commission 2024.06.27 '00'06- 08:21:31 IN THE COURT OF APPEALS OF THE STATE OF NEW MEXICO

Opinion Number: 2024-NMCA-046

Filing Date: March 18, 2024

No. A-1-CA-40100

ATLAS ELECTRICAL CONSTRUCTION INC.,

Plaintiff-Appellant,

v.

FLINTCO, LLC,

Defendant-Appellee,

and

TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA and BORDER STATES ELECTRIC SUPPLY OF NEW MEXICO,

Defendants.

APPEAL FROM THE DISTRICT COURT OF BERNALILLO COUNTY Nancy J. Franchini, District Court Judge

Holland & Hart LLP Larry J. Montano Judd C. West Santa Fe, NM

for Appellant

Lorber, Greenfeld & Polito, LLP

Louis W. Horowitz Linn E. Gillen Albuquerque, NM

for Appellee OPINION

HENDERSON, Judge.

{1} Plaintiff Atlas Electrical Construction, Inc. appeals the district court’s grant of Defendant Flintco, LLC’s motion to compel arbitration 1 and stay proceedings in Plaintiff’s claim for breach of contract. Plaintiff argues that the arbitration agreement provision of its subcontract with Defendant should not be enforced because the provision is facially one-sided and thus is substantively unconscionable. We conclude that the agreement is substantively unconscionable and thus reverse and remand.

BACKGROUND

{2} Plaintiff alleged that Defendant contracted with the City of Albuquerque for renovations of the Albuquerque International Sunport and entered into a subcontract with Plaintiff for performance of electrical work on the project. The subcontract contains a binding arbitration provision which states, in relevant part:

In the event [Defendant] and [Plaintiff] cannot resolve the Dispute through direct discussions or mediation . . . then the Dispute shall, at the sole discretion of [Defendant], be decided either by submission to (a) arbitration . . . or (b) litigation . . . .

Under the subcontract, “disputes” include all claims between Plaintiff and Defendant arising out of the subcontract, including breach of contract.

{3} Plaintiff later filed a breach of contract action in district court arising from the subcontract. 2 In response, Defendant moved to compel arbitration. After briefing and a hearing, the district court granted Defendant’s motion to compel arbitration without issuing findings of fact. However, the district court concluded in its oral ruling that the provision was neither procedurally nor substantively unconscionable. Plaintiff only appeals from the district court’s ruling regarding substantive conscionability.

DISCUSSION

1Even though orders granting motions to compel arbitration are final orders from which a party may appeal, see N.M. Dep’t of Health v. Maestas, 2023-NMCA-075, ¶¶ 15-16, 536 P.3d 506, not all claims against every defendant were compelled to arbitration in this case. However, under Rule 1-054(B) NMRA, when multiple parties are involved in an action, any order adjudicating the rights and liabilities of fewer than all the parties is not a final order unless the district court directs entry of a final judgment by expressly determining there is no just reason for delay. Here, the district court certified its order pursuant to Rule 1-054(B), stating that the referral of Plaintiff’s claims against Defendant to arbitration “is final . . . as there is no just reason for delay.” Thus, this appeal is properly before us. 2Plaintiff also named Travelers Casualty and Surety Company of America and Border States Electrical Supply of New Mexico as defendants in this action. Plaintiff’s claims against these defendants are not at issue on appeal. {4} We review a district court’s grant or denial of a motion to compel arbitration de novo. Cordova v. World Fin. Corp. of N.M., 2009-NMSC-021, ¶ 11, 146 N.M. 256, 208 P.3d 901. “Questions regarding substantive unconscionability present questions of law that are also reviewed de novo.” Peavy ex rel. Peavy v. Skilled Healthcare Grp., Inc., 2020-NMSC-010, ¶ 9, 470 P.3d 218.

{5} On appeal, Plaintiff argues that the district court erred in granting Defendant’s motion to compel arbitration because the arbitration provision is substantively unconscionable, and therefore is unenforceable. Defendant maintains that the arbitration provision is enforceable because it is commercially fair and reasonable. Alternatively, Defendant asserts that the provision should be enforced because New Mexico’s jurisprudence on unconscionability as applied to arbitration agreements violates the Federal Arbitration Act (FAA), 9 U.S.C. § 2. We address each issue in turn.

I. Conscionability of the Arbitration Clause

{6} A court should grant a motion to compel arbitration “unless it finds that there is no enforceable agreement to arbitrate.” NMSA 1978, § 44-7A-8(a)(2) (2001). “Arbitration agreements are a species of contract,” and thus to determine if there is an enforceable agreement to arbitrate, courts look “to principles of New Mexico contract law.” L.D. Miller Constr., Inc. v. Kirschenbaum, 2017-NMCA-030, ¶ 18, 392 P.3d 194. “Parties to a contract agree to be bound by its provisions and must accept the burdens of the contract along with the benefits.” Nearburg v. Yates Petroleum Corp., 1997-NMCA-069, ¶ 31, 123 N.M. 526, 943 P.2d 560. Thus, “courts may not rewrite obligations that the parties have freely bargained for themselves[ i]n the absence of fraud, unconscionability, or other grossly inequitable conduct.” Winrock Inn Co. v. Prudential Ins. Co., 1996-NMCA-113, ¶ 36, 122 N.M. 562, 928 P.2d 947 (emphasis added).

{7} “Unconscionability is an affirmative defense to contract enforcement.” Peavy, 2020-NMSC-010, ¶ 10. A contract may be procedurally unconscionable, substantively unconscionable, or both. Id. ¶ 11. “Substantive unconscionability concerns the legality and fairness of the contract terms themselves.” Cordova, 2009-NMSC-021, ¶ 22. “The substantive analysis focuses on such issues as whether the contract terms are commercially reasonable and fair, the purpose and effect of the terms, the one- sidedness of the terms, and other similar public policy concerns.” Id. Procedural unconscionability, on the other hand, “goes beyond the mere facial analysis of the contract and examines the particular factual circumstances surrounding the formation of the contract, including the relative bargaining strength, sophistication of the parties, and the extent to which either party felt free to accept or decline terms demanded by the other.” Id. ¶ 23.

{8} This is the first time since our Supreme Court reassessed unconscionability analysis in Peavy that we are being asked to address the unconscionability of a contract provision entered between two sophisticated commercial entities when it is undisputed that there was no procedural unconscionability in the contract formation. Much of our jurisprudence regarding unconscionability is in the context of consumer contracts, where procedural unconscionability is often present due to the unequal bargaining power of the parties. See, e.g., State ex rel. King v. B & B Inv. Grp., Inc., 2014-NMSC- 024, ¶¶ 13-27, 329 P.3d 658. This case requires us to consider how to weigh the absence of procedural unconscionability with assertions of substantive unconscionability in the commercial context, where procedural unconscionability is unlikely to be present due to the sophistication of the parties and the ability to freely negotiate the terms of a contract.

{9} In this case, Plaintiff concedes that the arbitration clause is procedurally conscionable.

Free access — add to your briefcase to read the full text and ask questions with AI

Atlas Elec. Constr. Inc. v. Flintco, LLC, 550 P.3d 881 (N.M. Ct. App. 2024).

550 P.3d 881 (Atlas Elec. Constr. Inc. v. Flintco, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Martinez v. Melloy Brothers, Inc.
New Mexico Court of Appeals, 2025
Schroeder v. Sw. Home Inspections, Inc.
New Mexico Court of Appeals, 2024