Atlantic Shores Resort Joint Venture v. Martin

731 F. Supp. 1279, 1990 U.S. Dist. LEXIS 2505, 1990 WL 20755
CourtDistrict Court, D. South Carolina
DecidedMarch 2, 1990
DocketCiv. A. M90-2-13-H
StatusPublished
Cited by3 cases

This text of 731 F. Supp. 1279 (Atlantic Shores Resort Joint Venture v. Martin) is published on Counsel Stack Legal Research, covering District Court, D. South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Atlantic Shores Resort Joint Venture v. Martin, 731 F. Supp. 1279, 1990 U.S. Dist. LEXIS 2505, 1990 WL 20755 (D.S.C. 1990).

Opinion

ORDER

HAMILTON, District Judge.

Respondents, Richard E. Martin, A.I.A. and Associates and The Martin Organization (Martin), move the court, pursuant to the Federal Arbitration Act, 9 U.S.C. § 1, et seq., for confirmation of an arbitration award entered in their favor and against claimant, Atlantic Shores Resort Joint Venture (Atlantic Shores), in the amount of Sixty-Three Thousand Two Hundred Ninety-Four and No/100 ($63,294.00) Dollars. Claimant Atlantic Shores counterclaims on grounds that the arbitration award should be vacated and requests that respondents’ petition to confirm be stayed pending a determination of claimant’s alleged entitlement to relief. Jurisdiction is premised upon 28 U.S.C. § 1332. The court has concluded that respondents’ motion to confirm should be granted.

On January 17,1985, Atlantic Shores and Martin entered into a contract whereby Martin agreed to perform certain architectural services in connection with the design and construction of the Sheraton Atlantic Shores Hotel (hotel) in Myrtle Beach, South Carolina. The contract provided that all disputes between the contracting parties arising out of their agreement would be decided by arbitration. According to Article 9 of the contract:

All claims, disputes and other matters in question between the parties to this Agreement, arising out of or relating to this Agreement or the breach thereof, will be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining, unless the parties mutually agree otherwise....

The contract also provided that “[t]he award rendered by the arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law....” Article 9, § 3.

Atlantic Shores also entered into a contract with Metric Constructors, Inc. (Met *1281 ric) whereby Metric agreed to serve as general contractor on the project. The hotel was first occupied in March 1987. Apparently at the end of the first summer of occupancy, mold and mildew were noted in guest rooms. Leaks were also discovered in numerous places throughout the hotel. Atlantic Shores retained the services of Simpson, Gumpertz and Heger, Inc. to investigate the problems. In addition to forming an opinion as to the leaks, Simpson, Gumpertz and Heger, and other consultants retained by Atlantic Shores, reached the opinion that the mold and mildew were principally caused by the design of the heating, ventilation, and air conditioning (HVAC) system. It was Martin’s opinion, however, that the mold and mildew was caused by moisture which entered the building during construction, external leaks in the building, and the method by which hotel personnel operated the HVAC system.

Atlantic Shores filed arbitration against Metric and Martin in August 1988 and January 1989, respectively. Both arbitration proceedings were filed with the American Arbitration Association (Association). Although Atlantic Shores requested consolidation, under the provisions of the arbitration clause consolidation could not be required without the consent of all parties— and Martin objected. The Association did not consolidate the proceedings, and Atlantic Shores then requested that the arbitration with Martin be heard first. Martin objected on grounds that the problems Atlantic Shores complained of were construction problems, and thus that relief should first be obtained from Metric. Nevertheless, Atlantic Shores insisted upon proceeding with the arbitration against Martin first. After extensive evidentiary hearings held September 11-14, 1989, October 15-18, 1989, and November 6-9, 1989, the parties were afforded the opportunity to submit written briefs and conduct oral argument on December 7, 1989. The arbitration panel issued an award on December 21, 1989, in which it found Atlantic Shores was not entitled to recover from Martin, but that Martin was entitled to recover Sixty-Three Thousand Two Hundred Ninety-Four and No/100 ($63,294.00) Dollars on its counterclaim for architectural fees.

Martin has petitioned this court to confirm the arbitration award entered on December 21, 1989. Atlantic Shores, however, has moved this court to stay confirmation of the award, and has also moved to vacate the award. Atlantic Shores argues that the award should be vacated on grounds that the arbitrators allegedly acted with evident partiality; exceeded their power under the agreement and applicable rules, refused to hear material evidence; refused to grant relief where liability was admitted; and acted in a manner that constitutes a manifest disregard of the law.

The Federal Arbitration Act (Act), 9 U.S.C. §§ 1-14, evidences the well established federal policy favoring the arbitration of disputes. See, e.g., Corbin v. Washington Fire and Marine Ins. Co., 278 F.Supp. 393 (D.S.C.), aff'd, 398 F.2d 543 (4th Cir.1968). Indeed, “[a] confirmation proceeding under 9 U.S.C. § 9 is intended to be summary: confirmation can only be denied if an award has been corrected, vacated, or modified in accordance with the Federal Arbitration Act.” Taylor v. Nelson, 788 F.2d 220, 225 (4th Cir.1986). Significantly, “the showing required to avoid summary confirmation is high.” Ottley v. Schwartzberg, 819 F.2d 373, 376 (2d Cir.1987).

To advance the underlying purposes of arbitration, 1 the scope of federal judicial review is necessarily restricted. Specifically, the court may only vacate an arbitration award on “one of the grounds specified by 9 U.S.C. § 10_” Nat’l R.R. Passenger Corp. v. Chesapeake and Ohio Ry. Co., 551 F.2d 136, 142 (7th Cir.1977), or, presumably, where the arbitrator acted in manifest disregard of the law or the award *1282 is incomplete, ambiguous, or contradictory. See, e.g., Transit Casualty Co. v. Trenwick Reinsurance Co., Ltd., 659 F.Supp. 1346, 1351 (S.D.N.Y.1987), aff'd, 841 F.2d 1117 (2d Cir.1988). 2 Perhaps most important, the burden of proof falls squarely on the party moving to vacate the arbitration award, see Andros Compania Maritima v. Marc Rich & Co., A.G., 579 F.2d 691, 700 (2d Cir.1978), who must “establish substantially more than an erroneous conclusion of law or fact.” Local Union No. 251 v. Narragansett Improvement Co., 503 F.2d 309, 312 (1st Cir.1974) (emphasis added).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fisher v. Gibbs International, Inc.
Court of Appeals of South Carolina, 2010
Hayne, Miller & Farni, Inc. v. Flume
888 F. Supp. 949 (E.D. Wisconsin, 1995)
Pinnacle Group, Inc. v. Shrader
412 S.E.2d 117 (Court of Appeals of North Carolina, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
731 F. Supp. 1279, 1990 U.S. Dist. LEXIS 2505, 1990 WL 20755, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atlantic-shores-resort-joint-venture-v-martin-scd-1990.