Asset Recovery Contracting, LLC v. Walsh Construction Company of Illinois

2012 IL App (1st) 101226, 980 N.E.2d 708
CourtAppellate Court of Illinois
DecidedNovember 1, 2012
Docket1-10-1226
StatusPublished
Cited by43 cases

This text of 2012 IL App (1st) 101226 (Asset Recovery Contracting, LLC v. Walsh Construction Company of Illinois) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Asset Recovery Contracting, LLC v. Walsh Construction Company of Illinois, 2012 IL App (1st) 101226, 980 N.E.2d 708 (Ill. Ct. App. 2012).

Opinion

ILLINOIS OFFICIAL REPORTS Appellate Court

Asset Recovery Contracting, LLC v. Walsh Construction Co. of Illinois, 2012 IL App (1st) 101226

Appellate Court ASSET RECOVERY CONTRACTING, LLC, Plaintiff-Appellant, v. Caption WALSH CONSTRUCTION COMPANY OF ILLINOIS, PALMOLIVE TOWER CONDOMINIUM, LLC, PALMOLIVE BUILDING BASE, LLC, AND NATIONAL ELECTRICAL BENEFIT FUND, Defendants- Appellees.

District & No. First District, Fourth Division Docket No. 1-10-1226

Rule 23 Order filed August 16, 2012 Rule 23 Order withdrawn October 29, 2012 Opinion filed November 1, 2012

Held In an action arising from delays in connection with plaintiff’s subcontract (Note: This syllabus to perform interior demolition work, extrinsic evidence of schedule constitutes no part of revisions was properly considered and delay damages were properly the opinion of the court denied pursuant to the “no damages for delay” clause based on plaintiff’s but has been prepared agreement to modifications of the schedule with requests for increased by the Reporter of costs, and plaintiff’s destruction of business claim was denied based on Decisions for the the subcontract’s provision barring such consequential damages. convenience of the reader.) Decision Under Appeal from the Circuit Court of Cook County, No. 05-CH-1014; the Review Hon. Thomas R. Mulroy, Jr., Judge, presiding.

Judgment Affirmed.

Counsel on Eckert Seamans Cherin & Mellott, LLC, of Pittsburgh, Pennslyvania Appeal (Christopher R. Opalinski and Cornelius J. O’Brien, of counsel), and Conway & Mrowiec, of Chicago (Timothy R. Conway, of counsel), for appellant.

Kubasiak, Fylstra, Thorpe & Rotunno, P.C. (Raymond A. Fylstra and Manuel J. Placencia, Jr., of counsel), and Law Offices of E. Bryan Dunigan (E. Bryan Dunigan, of counsel), both of Chicago, for appellee Walsh Construction Company of Illinois.

Panel JUSTICE PUCINSKI delivered the judgment of the court, with opinion. Presiding Justice Lavin and Justice Fitzgerald Smith concurred in the judgment and opinion.

OPINION

¶1 Background ¶2 The instant case arose from a multimillion dollar redevelopment of the Palmolive Building at 919 North Michigan Avenue, Chicago, Illinois, to convert the commercial office building into residential and retail condominiums. Defendant Walsh Construction Company of Illinois (Walsh) was the general contractor for the “core and shell” phase of the project, which generally entails removal of the interior finishes and mechanical and electrical and plumbing systems in preparation for build-out work. Margaret Walsh was Walsh’s senior project manager and was on the site daily beginning in March 2004. Jeff Pezza was Walsh’s junior project manager and was on the jobsite daily. Walsh executed a contract with Palmolive Tower Condominiums, LLC (Palmolive), dated August 1, 2003. Pursuant to the terms of the prime contract, Palmolive’s designated representatives were agents at Draper and Kramer Inc. (Draper and Kramer). ¶3 Walsh entered into various subcontracts for the project, including a subcontract agreement with Asset Recovery Contracting, LLC (ARC), to perform the interior demolition, dated September 12, 2003. After the events related to this construction project, ARC filed

-2- for bankruptcy and then filed the instant lawsuit against the above-captioned defendants. ARC was owned by Daniel Hoffman, who was the company’s managing member; James Werner, who served as a project manager, supervisor and estimator; Allen Formeister, who was a project manager and the senior estimator; and Michael McCabe, who was ARC’s accountant. Todd Westmoreland was also ARC’s project coordinator and worked with Werner and Patricia Gruenke to prepare ARC’s estimate for the project. Westmoreland was on the site regularly. Michael Gibbons was one of ARC’s superintendents. ¶4 ARC decided to bid on the project in 2003. Westmoreland and Gruenke prepared ARC’s debris quantity estimate for the project. On March 10, 2003, ARC submitted its initial bid for the project, which assumed a 12-month schedule for a base price of $2.9 million. Werner voiced concerns to Walsh about the various delays on a previous project on which the parties worked, at 175 West Jackson, but was assured that this project would be different. ¶5 In July 2003, ARC began work on the project, before ARC and Walsh signed the subcontract agreement. ARC did not sign the subcontract until March 19, 2004 and Walsh did not sign the agreement until May 5, 2004. ¶6 The subcontract required ARC to do the following: “Furnish all labor, materials, equipment, insurance, taxes and supervision as required to fully fabricate, deliver F.O.B. Project and install all Demolition as more completely described in the exhibits attached hereto, in strict compliance with the plans and specifications and as directed by Contractor.” ¶7 The project schedule was attached to the subcontract agreement as Exhibit I, which set forth the timing, sequence and duration of the work of the prime contract. Included were dates related to the timing and sequence of ARC’s work under the subcontract. ARC’s work was divided into three major areas of the building, to be performed concurrently: (1) the tower (floors 18 through 38); (2) the base (floors 1 through 17); and (3) three basements. The project schedule set forth that ARC’s demolition work was to be completed in approximately 19 weeks. There were remaining isolated demolition activities scheduled for later in the project, but the bulk of the demolition work was scheduled to be completed within a four- month period. ¶8 ARC’s work schedule was critical to the project, as a delay in ARC’s demolition work would delay the overall schedule for the redevelopment of the building. The prime contract contained a schedule that was similar to the schedule of the ARC subcontract. Exhibit A of the prime contract contained a set of clarifications dated October 16, 2003, stating that “Walsh Construction has assumed unrestricted access to perform demolition and construction above and below existing tenants.” The prime contract further provided that the contract schedule was “predicated on a 10/1/03 Notice to Proceed. If this date is changed, the schedule may have to be accelerated or delayed, at the owner’s direction ***.”

¶9 I. Evidence Regarding Delays Prior to Execution of the Contract ¶ 10 In August 2003, ARC began its work, starting with demolishing the three basement levels of the building. On September 12, 2003, ARC was informed by Walsh at a meeting that the Chicago fire department (CFD) had issued an order prohibiting demolition below any

-3- occupied floor and within two floors above any occupied floor in the building. Walsh requested, and ARC provided, cost estimates for the potential effects of this delay. On September 16, 2003, Werner wrote to Walsh outlining the costs associated with six possible scenarios which could be caused by the CFD order. Scenario six assumed the CFD order would remain in place and stated that the estimate of the cost to ARC would be $390,000. Although at this point in time the subcontract agreement had not yet been signed, ARC did not include this additional cost in the subcontract. ¶ 11 The owner attempted to obtain relief from the CFD’s order for the next two months. However, while the owner did so, it allowed its tenants and sales staff, including its agent, Draper and Kramer, to remain in the building, thus effectively preventing any demolition under the prohibition of the CFD’s order. Also, at the same time, the owner’s funding did not come through as scheduled, which also delayed authorization to ARC to commence its work on all areas except a few selected areas of the basements. ¶ 12 Also, prior to the project, Elizabeth Arden, a tenant in the building, as well as other entities, initiated litigation against Palmolive over concerns about the impending construction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shoppes v. Wasabi Sushi Bar Seven
Appellate Court of Illinois, 2026
In re Marriage of Michl
Appellate Court of Illinois, 2026
Heimer v. Roundy's Illinois, LLC
2025 IL App (3d) 240667-U (Appellate Court of Illinois, 2025)
In re Marriage of Smith
2025 IL App (5th) 250235-U (Appellate Court of Illinois, 2025)
Blackhawk Building, LLC v. Stanton
2025 IL App (2d) 230278-U (Appellate Court of Illinois, 2025)
Bottalla v. Serpe
2024 IL App (1st) 231779-U (Appellate Court of Illinois, 2024)
Franciscan Sisters of Chicago Service Corp. v. Meadows Menonite Retirement Community Assoc.
2023 IL App (1st) 220602-U (Appellate Court of Illinois, 2023)
Grand Ridge National Bank v. Cullum
2022 IL App (2d) 210436-U (Appellate Court of Illinois, 2022)
The Bank of New York Mellon v. Fiorentino
2022 IL App (1st) 210660-U (Appellate Court of Illinois, 2022)
Greggs USA, Inc. v. 400 East Professional Associates, LP
2021 IL App (1st) 200959 (Appellate Court of Illinois, 2021)
Roberson Construction, LLC v. Ellerby
2021 IL App (2d) 191095-U (Appellate Court of Illinois, 2021)
Thai v. Triumvera 600 Naples Court Condominium Ass'n
2020 IL App (1st) 192408 (Appellate Court of Illinois, 2021)
Christopher Glass and Aluminum, Inc v. Tishman Construction Corporation of Illinois
2020 IL App (1st) 191972-U (Appellate Court of Illinois, 2020)
Thai v. Triumvera 600 Naples Court Condominium Association
2020 IL App (1st) 192408 (Appellate Court of Illinois, 2020)
Thouvnenin v. Conrad
2020 IL App (5th) 190291-U (Appellate Court of Illinois, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
2012 IL App (1st) 101226, 980 N.E.2d 708, Counsel Stack Legal Research, https://law.counselstack.com/opinion/asset-recovery-contracting-llc-v-walsh-constructio-illappct-2012.