Ashland-Warren, Inc. v. Sanford

497 F. Supp. 374, 30 Fed. R. Serv. 2d 1167, 1980 U.S. Dist. LEXIS 15536
CourtDistrict Court, M.D. Alabama
DecidedSeptember 3, 1980
DocketCiv. A. 79-366-N
StatusPublished
Cited by3 cases

This text of 497 F. Supp. 374 (Ashland-Warren, Inc. v. Sanford) is published on Counsel Stack Legal Research, covering District Court, M.D. Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ashland-Warren, Inc. v. Sanford, 497 F. Supp. 374, 30 Fed. R. Serv. 2d 1167, 1980 U.S. Dist. LEXIS 15536 (M.D. Ala. 1980).

Opinion

OPINION

HOBBS, District Judge.

This cause came on to be heard at trial before this Court on July 14, 1980. Final submission to the Court for decision was on August 7, 1980, the date the Court received the last brief from the parties. Jurisdiction of this cause is based on diversity, 28 U.S.C. § 1332, it being the finding of this Court that plaintiff is a Delaware corporation with its principal place of business in Delaware, that defendants are citizens of the State of Alabama, and that the amount in controversy herein exceeds $10,000 exclusive of interest and costs.

The areas of dispute herein are relatively narrow. Of the three contracts executed by the parties, liability is undisputed by the defendants on two of them with the contention being made that the third contract was executed under duress. The other area of dispute concerns the defendants’ counterclaim for damages as a result of plaintiff’s delay in performance. The Court holds defendants liable for the amount in suit, plus accrued interest and a reasonable attorney’s fee as provided in two of the contracts, for the reasons hereinafter shown. The Court denies defendants any relief on their counterclaim.

FACTS

Plaintiff and defendants entered into a contract dated March 22, 1978, wherein it was agreed that plaintiff would perform certain paving construction at the Cross Creek Apartments in Columbus, Georgia in exchange for defendants’ promise to pay $12,596.40 for the products and services stated in the contract. (See Pltf’s Ex. 14) Defendants made payments against this indebtedness in the amount of $6,900.00, leaving a balance due of $5,696.40 plus simple interest at 6 per cent per annum from May 14, 1979 in the sum of $447.06 and interest that had accrued prior to May 14, 1979 in the amount of $230.89, or a total of $6,374.35. Defendants concede this work was properly done, and this indebtedness is not in dispute.

Plaintiff and defendants had earlier entered into a separate contract dated March 6, 1978, wherein the parties agreed that plaintiff would perform certain paving construction at the York Elderly Housing Project in York, Alabama in exchange for defendants’ promise to pay at the agreed rate for the products and services stated in the contract. Plaintiff purportedly performed its obligations under the contract, *376 acknowledging a limited list of defects which plaintiff agreed to repair at no charge. Plaintiff had subcontracted the preparation of the road base to Charles Talbert Construction Company. The specifications in the contract called for specific grades which would allow water drainage over the asphalt surface in prearranged patterns. The initial paving job was rejected by defendants and by the inspector from the Department of Housing and Urban Development. The paving job had deteriorated in several areas caused by the seepage of water into the base material. Two factors contributed to this seepage: one was defendants’ failure to back fill around the curbs and gutters prior to the application of the asphalt, and the other, and more significant, factor was plaintiff’s failure to achieve the specified thickness of the asphalt.

After the rejection by the federal inspector of the asphalt paving job, the parties corresponded as to how their problem could be remedied. Several such letters were admitted in evidence. Kim Stokes, an employee of the plaintiff, examined the paving job and agreed that there were certain defects in the parking bays and that in those areas the grade was improper. He and defendant Bell discussed an arrangement whereby plaintiff agreed to do a complete asphalt overlay at the York Elderly Housing Project in exchange for defendants’ promise to pay at plaintiff’s cost for the paving. It was understood between the parties that there would be no charge for the new asphalt applied in the parking bay areas. During these discussions prior to the execution of the contract between the parties dated June 28, 1978, defendant Bell never contended that he was blackmailed or coerced into signing the June 28 contract. (Pltf’s Ex. 4) In communications to plaintiff after plaintiff had fully performed on the June 28 agreement, defendant Bell acknowledged his obligation to the plaintiff on the York Elderly Housing Project. Defendants were billed for 170.24 tons of applied asphalt at $20.00 per ton.

The defendants were sent invoices for the services and materials used in performance of the March 6, 1978 York Elderly Housing Project in the following amounts:

(1) Prepare subbase at hourly rate $ 4,021.00
(2) 820 cubic yards topping at $2.50 per cu. yd. 2,050.00
(3) 3,325 sq. yds. asphalt paving applied 9,143.75
TOTAL $15,214.75.

The above quoted figures appeared on plaintiff’s invoice dated May 7, 1978. The balance on said invoice remains.outstanding plus simple interest at 6 per cent per annum from May 7, 1978 in the amount of $2,123.28, or a total of $17,338.03.

Defendants received a second invoice dated July 16, 1978 for the products and services performed as a result of the contract entered into by the parties on June 28,1978. That invoice contained the following item:

Hot plant mix asphalt, 170.24 tons at $20 per ton, total $ 3,404.80.

The balance on this invoice remains outstanding plus simple interest at 6 per cent per annum from July 16,1978 in the sum of $436.02, or a total of $3,840.82, for a combined total outstanding balance on the two York Elderly Housing invoices of $21,-178.85.

Each of the three contracts in question in this cause was executed on a form which states: “Sam Finley Company, a division of Ashland Oil, Inc. ...” However, at the time that each of these contracts was executed, Sam Finley Company was simply a trade name of Ashland-Warren, Incorporated, a wholly owned subsidiary of Ash-land Oil, Incorporated.

CONCLUSIONS OF LAW

This Court takes jurisdiction of this cause under 28 U.S.C. § 1332. The substantive law to be applied in this case is the law of Alabama. Erie Railroad Co. v. Tompkins, 304 U.S. 64, 58 S.Ct. 817, 82 L.Ed. 1188 (1938).

Defendants assert that plaintiff is not the real party in interest as required by Rule 17(a), Federal Rules of Civil Procedure, which provides: “Every action shall *377 be prosecuted in the name of the real party in interest.... ” At the time of the execution of the contracts in question herein, it is uncontroverted that Sam Finley Company was neither a natural nor artificial person but was a trade name owned by AshlandWarren, Incorporated. The facts show that between September 19, 1976 and October 1, 1977, Sam Finley Company was a division of Ashland Oil, Incorporated. The forms on which these contracts were executed represented that Sam Finley Company was a division of Ashland Oil, Incorporated at the time of their execution.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Purcell Co., Inc. v. Spriggs Enterprises, Inc.
431 So. 2d 515 (Supreme Court of Alabama, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
497 F. Supp. 374, 30 Fed. R. Serv. 2d 1167, 1980 U.S. Dist. LEXIS 15536, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ashland-warren-inc-v-sanford-almd-1980.