This text of 832 F.2d 357 (Armco, Inc. v. National Labor Relations Board) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Armco, Inc. v. National Labor Relations Board, 832 F.2d 357, 126 L.R.R.M. (BNA) 2961, 1987 U.S. App. LEXIS 14534 (6th Cir. 1987).

Opinion

BOYCE F. MARTIN, Jr., Circuit Judge.

Armco, Inc., and the United Steelworkers of America seek review of an order of the National Labor Relations Board finding them guilty of an overly-aggressive orga[359]*359nizational effort in violation of the National Labor Relations Act.

This case arises from Armco’s acquisition of an Allied Chemical coke plant in Ash-land, Kentucky on December 31, 1981. Armco owned and operated a steel production plant only a few miles from the coke plant, and it paid $100 million to Allied with the idea of obtaining a constant and high-quality supply of coke for its Ashland blast furnaces.

The controversy arose from Armco’s unilateral decision to accrete the coke plant workers to the Steelworkers’ bargaining unit at the steel plant, and from its failure to recognize or bargain with the Oil, Chemical and Atomic Workers (OCAW) which had always represented the workers at the coke plant. This decision resulted in a meeting at which the coke workers were required to sign Steelworkers’ dues checkoff cards if they wished to work for Armco. The National Labor Relations Board found that the coke workers represented a separate and appropriate bargaining unit and that Armco’s actions constituted unfair labor practices in violation of sections 8(a)(1), (2), (3), and (5), and 8(d) of the National Labor Relations Act, 29 U.S.C.A. §§ 158(a)(1), (2), (3), and (5), and § 158(d). The Board also found that, by its actions, the Steelworkers had violated sections 8(b)(1)(A) and (b)(2) of the Act, 29 U.S.C. §§ 158(b)(1)(A) and (b)(2). This decision appears at 279 N.L.R.B. 143 (May 30, 1986), and it affirms the lengthy rulings of the administrative law judge.

For the reasons that follow, we affirm, and we order that the decision of the Board be enforced.

I. FACTS

For approximately 35 years, Allied Chemical Corporation was engaged in the production of coke and its byproducts at the Ashland plant. Since 1952, that plant’s employees were represented by the OCAW International Union, its Local 3-523, and OCAW’s predecessor. The most recent collective bargaining agreement between Allied and OCAW was effective from August 5, 1979 through May 14, 1982. During 1981, the coke plant produced 500 tons per day, nearly all of which was sold to Armco. But, because the plant’s production capacity was 2800 tons per day, nearly two-thirds of the employees had been laid off.

The employees of Armco’s Ashland Works had been represented by the Steelworkers since 1942, and their most recent contract was effective from March 1, 1983 through July 31, 1986. During 1981, Arm-co needed about 2800 tons of coke per day to operate its Ashland Works. The coke Armco did not buy from Allied was purchased on the open market.

In 1979, Allied decided to withdraw from the coke-producing business, and it began selling its facilities. In 1981, Armco began looking toward the purchase of the Ash-land coke plant. Armco apparently considered a number of alternative methods of operating the plant, and it decided that the most efficient way would be to integrate the facility into its Ashland Works. There were two other alternatives: operating it as a self-standing unit, which Armco alleges would have caused redundancy in maintenance personnel and would have continued the need to stockpile coke as a hedge against production interruptions; and purchasing assets only, allowing the company to hire new labor. The latter option was apparently rejected as incompatible with the strong union ethic predominant in Ash-land. In addition, it would have been a great burden for Armco to train all new personnel.

In November 1981, Allied and Armco signed a letter of intent concerning the purchase. On November 25, two Allied representatives informed OCAW President Robert Goss of the purchase plan, telling him that Armco would not recognize the OCAW contract. Armco’s Corporate Director, James Wallace, informed the Steelworkers District Director Edgar Ball that Armco wished to bring the coke plant workers in under the Steelworkers contract and that the company would not recognize the OCAW. On November 30, Ball called Goss and related this development. Goss responded that, if satisfactory arrangements could be made with respect to job [360]*360security, seniority, and pensions, the OCAW would consider releasing the employees.

Numerous conversations between the various parties ensued. The Steelworkers union was concerned that the OCAW might file raiding charges with the AFL-CIO. The OCAW’s International Representative, Kenneth McKeand, said he intended to do everything in his power to keep the coke workers OCAW. It soon became clear, however, that the OCAW had little leverage against Armco. An Allied representative stated that, if Armco did not buy the plant, it would be shut down. Thus, despite an overwhelming vote among the coke workers to maintain their OCAW status and avoid accretion into the Steelworkers, the OCAW had no viable alternative because Armco was represented as “the only show in town.”

A memorandum of understanding was signed between the Steelworkers and Arm-co on December 15, 1981, detailing the arrangements governing the purchase of the plant and the hiring of the coke workers. As a result, Armco offered to hire all of the Allied employees, recalling laid-off workers as production increased, with no probationary period required. The Allied workers, though, would all be given a new seniority date of December 31, 1981, and they all would be required to sign Steelworkers dues checkoff and authorization cards as a condition of employment. Although both Goss and McKeand initially objected to this requirement, they eventually told the coke workers to sign the cards rather than risk losing their jobs. At no time, however, did OCAW unconditionally release the employees to the Steelworkers, and at no time did the workers vote to be represented by the Steelworkers.

The sale was final on December 31, 1981, and, as of January 2, 1982, Armco began applying the terms of its bargaining agreement with the Steelworkers to the coke plant employees. Armco had purchased all of Allied’s equipment, material, and supplies, and it operated the plant with the same machinery, equipment, and production methods previously used by Allied.

What then followed were disagreements and struggles within the OCAW itself, apparently caused by dissatisfaction of the Local members. In March 1982, the officers of the Local OCAW sent a letter to the Steelworkers denying that the coke plant was an accretion to the existing Armco unit, and the letter stated that the OCAW had never been notified of negotiations between Armco and the Steelworkers involving the coke plant employees. These negotiations involved the coke workers’ terms and conditions of employment and resulted in lost pensions, wages, seniority, vacations, and benefits. The Steelworkers did not respond to the letter.

In his letter of March 18, OCAW President Goss announced a meeting to be held March 28 to determine the position of the members on the issue of whether the OCAW should assert bargaining rights. The letter stated that the OCAW had not previously asserted those rights because its primary concern had been to ensure job opportunities and recall rights. Approximately 300 members attended the meeting, and they voted unanimously to assert the OCAW’s bargaining rights at the coke plant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Drake v. Richerson
948 F. Supp. 2d 817 (N.D. Ohio, 2013)
Stephen Glasser v. ADT Security Services, Inc.
379 F. App'x 483 (Sixth Circuit, 2010)
Cap Cleaning Contr v. NLRB
D.C. Circuit, 1998
Leach Corp. v. National Labor Relations Board
54 F.3d 802 (D.C. Circuit, 1995)
No. 93-1707
54 F.3d 802 (D.C. Circuit, 1995)
National Labor Relations Board v. Nta Graphics, Inc.
996 F.2d 1216 (Sixth Circuit, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
832 F.2d 357, 126 L.R.R.M. (BNA) 2961, 1987 U.S. App. LEXIS 14534, Counsel Stack Legal Research, https://law.counselstack.com/opinion/armco-inc-v-national-labor-relations-board-ca6-1987.