FOURTH DIVISION DILLARD, P. J., MERCIER and MARKLE, JJ.
NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. https://www.gaappeals.us/rules
June 21, 2022
In the Court of Appeals of Georgia A22A0056. ARCO DESIGN/BUILD, LLC v. SAVANNAH GREEN I OWNER, LLC.
MARKLE, Judge.
This appeal addresses the discrete issue of whether the tolling provisions of the
2020 Statewide Judicial Emergency Orders extended the deadline for filing an
affidavit of nonpayment under Georgia’s lien waiver statute, OCGA § 44-14-366.1
The trial court determined that they did not and, for the reasons that follow, we
affirm.
The material facts of this case are not in dispute. In 2018, Savannah Green I
Owner, LLC (“SGO”) entered into a contract with Arco Design/Build, LLC, under
which Arco agreed to design and build a warehouse on SGO’s property in Pooler,
1 Unless otherwise noted, all references to OCGA § 44-14-366 are to the version that became effective on March 31, 2009. Georgia. The contract required Arco to submit periodic applications for payment, and
to execute conditional lien waivers to cover the exact amount requested in the
payment application. Pursuant to the terms of these waivers, Arco released “any and
all liens or claims of lien it has upon the . . . property” upon full payment of the
requested amount. Tracking the language of OCGA § 44-14-366 (f) (2), the waivers
also provided that Arco “shall be conclusively deemed to have been paid in full”
regardless of whether Arco actually received the payment, unless it filed an affidavit
of nonpayment or a claim of lien within 60 days of the date of the waiver.
On April 22, 2020, Arco submitted to SGO an application for payment in the
amount of $1,027,695.17, and executed the accompanying lien waiver. More than 60
days later, on September 14, 2020, Arco filed an affidavit of nonpayment under
OCGA § 44-14-366 in Chatham County Superior Court, claiming that it was still
owed $668,912.17 under this application for payment.2 The following month, Arco
recorded a claim of lien for the unpaid amount.
SGO filed suit, bringing a claim for breach of contract based on Arco’s
allegedly defective work, and sought a declaratory judgment that Arco’s affidavit of
2 On that same date, Arco filed an additional affidavit of nonpayment in the amount of $184,264.03, but that claim was not addressed in the trial court’s order on appeal.
2 nonpayment was untimely, and therefore any debt SGO owed was extinguished by
operation of law. Arco answered and brought counterclaims for breach of contract
based on SGO’s nonpayment and to foreclose its lien.3 In its pleadings, Arco asserted
that its affidavit of nonpayment was timely because the 60-day deadline under OCGA
§ 44-14-366 (f) (2) (c) was tolled, and did not begin to run until July 14, 2020, under
the Supreme Court of Georgia’s Order Declaring Statewide Judicial Emergency, and
the subsequent orders extending the judicial emergency. SGO moved for partial
summary judgment on this issue, which the trial court granted in a thorough and well-
reasoned order. Arco now appeals.
Arco challenges the trial court’s determination that its affidavit of nonpayment
was untimely because the Emergency Orders did not toll the filing requirements under
OCGA § 44-14-366. This appeal requires us to construe the applicable Emergency
3 The Georgia State-wide Business Court granted the parties’ joint motion to transfer the case from the superior court. This appeal is the first review of an order of the state business court. We have jurisdiction to consider this appeal pursuant to OCGA §§ 5-6-33 (a) (1) and 15-3-3.1 (a), and under Article VI, Section V, Paragraph III of the Georgia Constitution.
3 Orders,4 as well as the Georgia lien waiver statute, and we are bound by the following
rules of construction:
In interpreting any statute, we necessarily begin our analysis with familiar and binding canons of construction. And in considering the meaning of a statute, our charge is to presume that the General Assembly meant what it said and said what it meant. So, we must afford the statutory text its plain and ordinary meaning, consider the text contextually, read the text in its most natural and reasonable way, as an ordinary speaker of the English language would, and seek to avoid a construction that makes some language mere surplusage. Thus, when the language of a statute is plain and susceptible of only one natural and reasonable construction, courts must construe the statute accordingly.
(Citations and punctuation omitted.) Kemron Environmental Servs. v. Prospira
Paincare, 362 Ga. App. 727, 730 (870 SE2d 53) (2022). Because statutory
interpretation is a question of law, our review is de novo. Hill v. First Atlantic Bank,
323 Ga. App. 731, 732 (747 SE2d 892) (2013). And, as lien statutes are in derogation
4 The parties do not dispute that the rules of construction apply to the Emergency Orders as the Chief Justice’s authority to issue them is derived from statute. See OCGA § 38-3-60 et seq.; cf. Schwartz v. Black, 200 Ga. App. 735, 736 (409 SE2d 681) (1991) (where administrative agency’s authority to adopt rules and regulations is derived from statute, rules of statutory interpretation apply to their construction).
4 of the common law, they “must be strictly construed in favor of the property owner
and against the materialman.” (Citation and punctuation omitted.) Bibler Masonry
Contractors v. J. T. Turner Constr. Co., 340 Ga. App. 490, 493 (798 SE2d 19)
(2017).
Under the lien waiver statute, OCGA § 44-14-366:
(1) When a waiver and release provided for in this Code section is executed by the claimant, it shall be binding against the claimant for all purposes, subject only to payment in full of the amount set forth in the waiver and release.
(2) Such amounts shall conclusively be deemed paid in full upon the earliest to occur of:
(A) Actual receipt of funds;
(B) Execution by the claimant of a separate written acknowledgment of payment in full; or
(C) Sixty days after the date of the execution of the waiver and release, unless prior to the expiration of said 60 day period the claimant files a claim of lien or files in the county in which the property is located an affidavit of nonpayment.
OCGA § 44-14-366 (f) (1), (2).
5 On March 14, 2020, in response to the surging COVID-19 pandemic, Chief
Justice Harold D. Melton issued the first of several Emergency Orders, declaring a
statewide judicial emergency “affecting all courts and clerk’s offices in the State as
it relates to all judicial proceedings.” (Emphasis supplied.) Order Declaring Statewide
Judicial Emergency at 1, March 14, 2020. The Chief Justice also issued the following
directive:
Pursuant to OCGA § 38-3-62, during the period of this Order, the undersigned hereby suspends, tolls, extends, and otherwise grants relief from any deadlines or other time schedules or filing requirements imposed by otherwise applicable statutes, rules, regulations, or court orders, whether in civil or criminal cases or administrative matters, including, but not limited to any: (1) statute of limitation; (2) time within which to issue a warrant; (3) time within which to try a case for which a demand for speedy trial has been filed; (4) time within which to hold a commitment hearing; (5) deadline or other schedule regarding the detention of a juvenile; (6) time within which to return a bill of indictment or an accusation or to bring a matter before a grand jury; (7) time within which to file a writ of habeas corpus; (8) time within which discovery or any aspect thereof is to be completed; (9) time within which to serve a party; (10) time within which to appeal or to seek the right to appeal any order, ruling, or other determination; and (11) such other legal proceedings as determined to be necessary by the authorized judicial official.
6 (Emphasis supplied.) Id. at 2; see also OCGA § 38-3-62 (a).
Under the third extension of the Emergency Order, “many of the deadlines
imposed by law on litigants in civil and criminal cases that had been suspended,
tolled, or extended” were to be reinstated as of July 14, 2020. (Emphasis supplied.)
See Third Order Extending Declaration of Statewide Judicial Emergency at 1, 3 (II)
(2), June 12, 2020.
Arco thus posits that its September 14, 2020 affidavit of nonpayment was
timely because it was filed sixty days from the July 14th reinstatement date.5 See
OCGA § 44-14-366 (f) (2) (C). On appeal, it contends that the trial court incorrectly
construed certain provisions of the Emergency Orders, improperly limiting their
intended scope. We address each term in turn, and conclude that the trial court
correctly held that the Emergency Orders did not toll the filing requirements under
OCGA § 44-14-366 (f) (2) (C).
(a) “In civil or criminal cases or administrative matters.”
5 Under Arco’s proposed schedule, the 60-day deadline ran on Saturday, September 12, 2020. However, the trial court determined that OCGA § 1-3-1 (d) (3) applied to the lien waiver statute. This time computation issue is not raised on appeal, and is irrelevant in light of our decision.
7 Arco first takes issue with the trial court’s interpretation of the above language
from the first Emergency Order.6 Specifically, the trial court noted that the first
Emergency Order contained a significant limiter, restricting the tolling provision to
“any deadlines or other time schedules or filing requirements imposed by otherwise
applicable statutes, rules, regulations, or court orders, whether in civil or criminal
cases or administrative matters.” (Emphasis supplied.) Order Declaring Statewide
Judicial Emergency at 2, March 14, 2020. The trial court then found that “[t]he
statutory deadline for filing an affidavit of nonpayment or a claim of lien is plainly
not a deadline imposed in a civil or criminal case.” Arco contends that the phrase,
“whether in civil or criminal cases or administrative matters,” qualifies only the
immediately preceding phrase, “court orders”; thus, the tolling provision applies to
OCGA § 44-14-366 (f) (2) (C) as it is simply “an otherwise applicable statute.” Order
Declaring Statewide Judicial Emergency at 2, March 14, 2020.
The statutory interpretation Arco espouses is the “rule of the last antecedent,”
under which “a qualifying phrase should ordinarily be read as modifying only the
6 SGO asserts Arco waived many of its appellate arguments regarding the construction of the Emergency Orders because it did not assert identical arguments below. We find no such waiver. See Camelot Club Condo. Assn. v. Afari-Opoku, 340 Ga. App. 618, 620 (1), n. 5 (798 SE2d 241) (2017).
8 noun or phrase that it immediately follows.” (Citations and punctuation omitted.)
Cajun Contractors v. Peachtree Property Sub, 360 Ga. App. 390, 414 (3) (a), n. 16
(861 SE2d 222) (2021); see also Thornton v. State, 310 Ga. 460, 467 (3) (851 SE2d
564) (2020). However, as our Supreme Court has explained,
this rule is not absolute, and the inference it raises may be rebutted where the structure and internal logic of the statutory scheme so militate. Under the alternative “series-qualifier principle,” a qualifying phrase appearing at the end of a series should be read to apply to all items in the series when such an application would represent a natural construction. In choosing among the different understandings of the statute proposed by the parties, we must assess the qualifying phrase by reference to its situation within and relationship to the entire . . . text.
(Citations and punctuation omitted.) Thornton, 310 Ga. at 467-468 (3).
Looking at the first Emergency Order as a whole, the phrase in question is most
naturally and reasonably read to qualify the entire preceding series of terms. See
Thornton, 310 Ga. at 468 (3); see also Norman Singer, 2A Sutherland Statutory
Construction § 47:33 (7th ed. 2021) (“A qualifying phrase separated from antecedents
by a comma [as here] is evidence that the qualifier is supposed to apply to all the
antecedents instead of only to the immediately preceding one.”); Antonin Scalia &
Bryan A. Garner, Reading Law: The Interpretation of Legal Texts 144-146 (1st ed.
9 2012). In other words, the tolling provision applies to statutes that are “in civil or
criminal cases or administrative matters,” but not to all statutes containing a deadline,
time schedule or filing requirement.7 To find otherwise would confound reason.
Moreover, this construction comports with the textually stated purpose of the March
14, 2020 order, to declare an emergency “as it relates to all judicial proceedings.”
(Emphasis supplied.) Order Declaring Statewide Judicial Emergency at 1, March 14,
2020; see also Lucas v. Beckman Coulter, Inc., 303 Ga. 261, 264, n. 6 (811 SE2d 369)
(2018) (“[T]he last antecedent rule applies where no contrary intention appears.”)
(citation omitted). As discussed below, the filing of an affidavit of nonpayment under
OCGA § 44-14-366 (f) (2) (C) is not a judicial proceeding. Thus, the trial court did
not err in its interpretation of this phrase.
(b) “Judicial proceedings” and “legal proceedings.”8
7 Arco argues that, unlike court orders, statutes are not “in” civil or criminal cases. This argument ignores the language of the Emergency Order, which qualifies the phrase “statutes, rules, regulations, or court orders” with the adjective, “applicable.” Order Declaring Statewide Judicial Emergency at 2, March 14, 2020. Unquestionably, statutes are applicable in civil or criminal cases. See, e.g., Viskup v. Viskup, 291 Ga. 103, 107 (3) (727 SE2d 97) (2012) (noting that OCGA § 19-9-3 (g) “is applicable in an action seeking modification of child custody/visitation[.]”) (emphasis supplied). 8 Arco also identifies the term, “judicial process,” in its claim of error; however, we have already determined that a lien does not become an act of judicial
10 Arco next contends the trial court misinterpreted the above terms in the
Emergency Orders, and in ultimately concluding that the filing requirements imposed
by OCGA § 44-14-366 do not amount to a deadline in a “legal proceeding” or a
“judicial proceeding.” Arco also takes issue with the trial court’s observation that the
deadline under OCGA § 44-14-366 (f) (2) (C) cannot be in a legal or judicial
proceeding because it necessarily expires before a suit to foreclose the lien can
commence. We find no error in the trial court’s construction of these terms.
Plainly, the filing of an affidavit of nonpayment to nullify a lien waiver in the
property records is not a judicial or legal proceeding. A judicial proceeding is “[a]ny
court proceeding; any proceeding initiated to procure an order or decree, whether in
law or in equity.” Judicial Proceeding, Black’s Law Dictionary (11th ed. 2019); see
also Harkins v. CA 14th Investors, 247 Ga. App. 549, 550 (544 SE2d 744) (2001)
(“[D]ictionaries may supply the plain and ordinary meaning of a word.”). A legal
proceeding is “[a]ny proceeding authorized by law and instituted in a court or tribunal
to acquire a right or to enforce a remedy.” Legal Proceeding, Black’s Law Dictionary
(11th ed. 2019). A proceeding is generally defined as “[t]he regular and orderly
process until it is “attached to a lawsuit and verified notice of the suit is filed under OCGA § 44–14–361.1,” which has not occurred here. (Emphasis omitted.) Simmons v. Futral, 262 Ga. App. 838, 847 (586 SE2d 732) (2003).
11 progression of a lawsuit, including all acts and events between the time of
commencement and the entry of judgment” or as “[a]ny procedural means for seeking
redress from a tribunal or agency.” Proceeding, Black’s Law Dictionary (11th ed.
2019). Under these definitions, the filing of an affidavit of nonpayment or a claim of
lien is not a judicial or legal proceeding. Moreover, these terms, as used in the
Emergency Orders, would be mere surplusage if every filing with a court clerk’s
office amounted to a proceeding. See Stockton v. Shadwick, 362 Ga. App. 779, 783
(1) (a) (870 SE2d 104) (2022) (“[T]he fundamental rules of statutory construction . . .
require us to avoid a construction that makes some language mere surplusage.”)
(citation and punctuation omitted).
Arco nevertheless contends that the filing of the affidavit of nonpayment is
contemplated by these definitions because it cannot bring an action to recover the
alleged debt without first filing the affidavit of nonpayment. See ALA Construction
Servs. v. Controlled Access, 351 Ga. App. 841, 844 (833 SE2d 570) (2019) (analyzing
the version of OCGA § 44-14-366 (f) applicable here, and finding that the
materialman’s action for breach of contract was precluded because its failure to file
an affidavit of nonpayment or claim of lien within the 60-day period extinguished the
12 debt).9 However, the textually stated purpose of filing an affidavit of nonpayment or
a claim of lien is not to “seek redress from a tribunal,” but to establish a debt. See
ALA Construction Servs., 351 Ga. App. at 844 (The materialman “had a statutorily
imposed responsibility to file either a claim of lien or an affidavit of nonpayment if
it wished to keep the debt alive beyond 60 days.”) (emphasis supplied); see also Lien,
Black’s Law Dictionary (11th ed. 2019) (defining a lien as “[a] legal right or interest
that a creditor has in another’s property”). It is thus not a judicial or legal proceeding.
We find support for this interpretation in Simmons v. Futral, 262 Ga. App. 838,
847 (586 SE2d 732) (2003), a defamation case addressing whether statements made
in a surveyor’s lien were absolutely privileged. There, we noted that “a lien is not a
pleading . . . until the lien becomes attached to a lawsuit and verified notice of the suit
is filed under OCGA § 44-14-361.1. At that point, the lien becomes an act of legal,
or judicial, process[.]” (Emphasis in original.) Id. We also cited favorably to a South
Dakota Supreme Court opinion that held
9 OCGA § 44-14-366 was later revised to provide that the waiver and release rights “under this Code section shall be limited to waivers and releases of lien and labor or material bond rights and shall not be deemed to affect any other rights or remedies of the claimant.” (Emphasis supplied.) OCGA § 44-14-366 (a) (January 1, 2021).
13 A materialman’s lien may be ancillary to judicial action — the filing is a prerequisite to a lien foreclosure. Still, a lawsuit will not necessarily follow from filing a lien and often does not. . . . We conclude the filing of a materialman’s lien is not a judicial proceeding[.]
(Punctuation omitted.) Id. at 846, citing Gregory’s, Inc. v. Haan, 545 NW2d 488, 494
(II) (1996 SD 35) (1996); see also Tucker Door & Trim v. Fifteenth St. Co., 235 Ga.
727, 728 (221 SE2d 433) (1975) (“It is not until foreclosure of the lien, after a full
judicial proceeding, that any judgment attaches against the property.”) (emphasis
supplied). Accordingly, there is no basis to find that the filing of an affidavit of
nonpayment under our lien laws is a judicial or legal proceeding.
Arco attempts to equate the pre-litigation filing requirements at issue here to
the issuance of a warrant because warrants are often sought prior to a criminal
prosecution. This comparison is unpersuasive. First, warrants are expressly included
in the first Emergency Order’s tolling provision. Order Declaring Statewide Judicial
Emergency at 2, March 14, 2020; see also OCGA § 38-3-62 (a) (2). Second, without
question, the issuance of a warrant is a judicial proceeding because it requires a judge
to find probable cause. See OCGA §§ 17-5-21 (a); 17-4-40 (a); see also Judicial
Proceeding, Black’s Law Dictionary (11th ed. 2019) (A judicial proceeding is “[a]ny
court proceeding; any proceeding initiated to procure an order or decree”). No such
14 authority is required to file an affidavit of nonpayment under OCGA § 44-14-366 (f)
(2) (C).
Arco next attempts to equate this filing requirement to ante litem notices that
also must be filed before litigation may ensue. See OCGA §§ 50-21-26 (a); 36-33-5
(b). The Emergency Orders do not specifically mention ante litem notices in the
tolling provisions, and we do not decide in this appeal whether ante litem notices
were tolled under them. Yet, we note some significant distinctions between ante litem
notices and the affidavit of nonpayment at issue here. Most telling is their differing
results: an ante litem notice preserves a cause of action, whereas an affidavit of
nonpayment preserves an interest in property. Compare OCGA §§ 36-33-5 (b) (“No
action shall be entertained by the courts against the municipal corporation until the
cause of action therein has first been presented to the governing authority for
adjustment.”); 50-21-26 (a) (3) (“No action against the state under this article shall
be commenced and the courts shall have no jurisdiction thereof unless and until a
written notice of claim has been timely presented[.]”) with Lang v. Brand-Vaughan
Lumber Co., 339 Ga. App. 710, 714 (1) (792 SE2d 461) (2016) (physical precedent
only) (“[A] materialman’s lien is an interest perfected only by compliance with the
statutory requirements, including obtaining a judgment against the original debtor.”);
15 Simmons, 262 Ga. App. at 846 (“A materialman’s lien may be ancillary to judicial
action . . . . Still, a lawsuit will not necessarily follow from filing a lien and often does
not.”) (citation and punctuation omitted); see also Tucker Door & Trim Corp., 235
Ga. at 729 (“The filing of the claim of lien is similar to a lis pendens notice. It gives
notice to subsequent purchasers of the property, or persons who might extend credit
thereon, that there is superior charge on it; and gives protection to the materialman
until his claim can be foreclosed.”).
Moreover, the statutes providing for ante litem notices are procedural laws;
whereas the lien waiver statute grants substantive rights to both the property owner
and the materialman. See Burns v. State, 313 Ga. 368, 372 (3) (870 SE2d 360) (2022)
(explaining that a “procedural law is that law which prescribes the methods of
enforcement of rights, duties, and obligations,” whereas a substantive law creates
obligations and grants substantive rights) (citation and punctuation omitted); see also
Henderson v. Dept. of Transp., 267 Ga. 90 (2) (475 SE2d 614) (1996) (service and
notice requirements under the Tort Claims Act are procedural); see generally OCGA
§ 44-14-366. Accordingly, we are unpersuaded by this comparison, and conclude that
the trial court did not err in finding that the filing requirements under OCGA § 44-4-
366 (f) (2) (C) do not amount to a judicial or legal proceeding.
16 (c) “Litigants.”
With regard to this term,10 Arco takes issue, specifically, with the trial court’s
following finding:
The Chief Justice’s continual reference to the deadlines imposed on litigants in civil and criminal cases and the absence of any discussion, guidance, or reference to other miscellaneous filing or recording deadlines unrelated to judicial proceedings is telling. As reflected in the plain language of the original Emergency Order, and re-emphasized in the subsequent orders extending the same, the Chief Justice clearly intended to limit tolled deadlines to those affecting “litigants” — not all deadlines existing in the entirety of Georgia law.
See, e.g., Third Order Extending Declaration of Statewide Judicial Emergency at 3,
June 12, 2020 (“This order announces a plan to reimpose all deadlines and other time
schedules and filing requirements . . . that are imposed on litigants[.]”) (emphasis in
original); Fourth Order Extending Declaration of Statewide Judicial Emergency at 3,
July 10, 2020 (“[T]his order hereby reimposes all deadlines and other time schedules
. . . that are imposed on litigants[.]”) (emphasis in original).
10 Litigant is generally defined as a “party to a lawsuit; the plaintiff or defendant in a court action, whether an individual, firm, corporation, or other entity.” Litigant, Black’s Law Dictionary (11th ed. 2019).
17 Arco contends that the term, “litigant,” requires a broader interpretation because the
first Emergency Order did not include this term, and it expressly tolled the issuance
of warrants, a proceeding that does not involve a “litigant” per se. We are not
persuaded.
In Division (b) above, we explained how the administrative or clerical act of
filing an affidavit of nonpayment differs significantly from the judicial act of issuing
a warrant. Even setting aside this disparity, this claim of error fails because the trial
court did not base its analysis on this term alone. Rather, the trial court read all of the
relevant Emergency Orders in concert, as it was required to do. See Lathan v. Hosp.
Auth. of Charlton County, 343 Ga. App. 123, 128 (1) (805 SE2d 450) (2017) (“A
statute must be construed in relation to other statutes of which it is a part, and all
statutes relating to the same subject-matter, briefly called statutes ‘in pari materia,’
are construed together, and harmonized wherever possible[.]”) (citation omitted); Ivey
v. McCorkle, 343 Ga. App. 147, 153 (5) (a) (806 SE2d 231) (2017) (reading various
provisions of a city charter in pari materia).
Thus, in language overlooked by Arco, the trial court found that
with respect to the deadlines imposed on litigants (as opposed to the courts generally), the order applies only to deadlines, time schedules,
18 and filing requirements in judicial or legal proceedings related to civil or criminal cases. OCGA § 44-14-366 may be a statutory deadline, but it is not a “legal” deadline imposed on litigants, nor is it a deadline in a “legal proceeding” or “judicial proceeding.”
(Emphasis in original.)
For the reasons set forth above, we agree with this conclusion. We further note
that the trial court’s reasoning comports with the precept that our lien laws must be
strictly construed in favor of the property owner. See Bibler Masonry Contractors,
340 Ga. App. at 493; see also U. S. Filter Distribution Group v. Barnett, 273 Ga. 254,
255 (538 SE2d 739) (2000). Accordingly, the trial court correctly determined that the
Emergency Orders did not toll the filing requirements of OCGA § 44-14-366,11 and
we affirm.
Judgment affirmed. Dillard, P. J., and Mercier, J., concur.
11 Although this outcome may appear draconian as it relates to Arco’s claims for payment, we do “not have the authority to rewrite statutes.” (Citations and punctuation omitted.) Harris v. Mahone, 340 Ga. App. 415, 422 (1) (797 SE2d 688) (2017); see, e.g., OCGA § 44-14-366 (a) (January 1, 2021).