Bibler Masonry Contractors, Inc. v. J. T. Turner Construction Co., Inc.

798 S.E.2d 19, 340 Ga. App. 490, 2017 WL 922955, 2017 Ga. App. LEXIS 86
CourtCourt of Appeals of Georgia
DecidedMarch 6, 2017
DocketA16A2094
StatusPublished
Cited by5 cases

This text of 798 S.E.2d 19 (Bibler Masonry Contractors, Inc. v. J. T. Turner Construction Co., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bibler Masonry Contractors, Inc. v. J. T. Turner Construction Co., Inc., 798 S.E.2d 19, 340 Ga. App. 490, 2017 WL 922955, 2017 Ga. App. LEXIS 86 (Ga. Ct. App. 2017).

Opinion

Branch, Judge.

After Bibler Masonry Contractors, Inc., finished its work as a subcontractor on a project to renovate the Savannah Law School, it signed — and contends it backdated — a lien waiver in anticipation *491 of final payment from the general contractor. The contractor, however, failed to pay Bibler, and Bibler filed an affidavit of nonpayment with the clerk of court but did so more than 60 days past the date shown on the lien waiver. When Bibler attempted to enforce the lien against the project owner, the trial court granted summary judgment in favor of the owner, holding that the affidavit was untimely under the relevant 60-day deadline. On appeal, Bibler argues that the 60 days should run from the day it actually signed the lien waiver, not from the backdated date. We disagree and affirm the trial court’s ruling.

A party is entitled to summary judgment if there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. OCGA § 9-11-56 (c).

On appeal from the grant of summary judgment, we construe the evidence most favorably toward the nonmoving party, who is given the benefit of all reasonable doubts and possible inferences. The party opposing summary judgment is not required to produce evidence demanding judgment for it, but is only required to present evidence that raises a genuine issue of material fact.

Ansley v. Raczka-Long, 293 Ga. 138, 140 (2) (744 SE2d 55) (2013) (citations omitted); see also Home Builders Assn. of Savannah v. Chatham County, 276 Ga. 243, 245 (1) (577 SE2d 564) (2003). Our review is de novo. Ansley, 293 Ga. at 140 (2).

The material facts are not in dispute. Appellee JMLS 1422, LLC, purchased property to house the Savannah Law School and hired J. T. Turner Construction Company (“JTT”) as the general contractor to renovate the property On May 23, 2013, JTT hired Bibler as a subcontractor to perform masonry work on the project. By the end of the project, although Bibler had been paid for most of its work, Bibler asserted that JTT had failed to pay Bibler $105,141.37. In exchange for a statutorily-required “Waiver and Release Upon Final Payment,” JTT promised that the full and final payment would be made. Bibler signed the waiver and release and dated it December 22, 2014; a witness also signed it. On February 17, 2015, Bibler forwarded the signed waiver to JTT, again demanding that Bibler be paid in full; JTT appears to have received the document that same day as evidenced by a stamp on its face. Payment never came, however, and on February 27, 2015, Bibler filed an affidavit of nonpayment with the applicable clerk of court, which, as shown below, is required by statute to suspend the effect of the waiver and release. On March 5, 2015, Bibler then recorded its claim of lien in the amount of *492 $105,141.37 against the project real estate owned by JMLS, but no payment was ever received.

In May 2015, Bibler filed suit against JTT and JMLS, raising several claims against JTT and asserting a right to an accounting and to foreclose on the lien against JMLS. Bibler also recorded a notice of its action to foreclose. Eventually Bibler settled its claims against JTT and entered into a consent judgment in the amount of $105,141.37, thereby leaving only the lien and accounting claim pending against JMLS. Bibler and JMLS then filed cross-motions for summary judgment on those claims.

Although the trial court agreed that Bibler had established a prima facie case that it complied with its subcontract but was not paid in full, the trial court found that Bibler’s affidavit of nonpayment was untimely in that it was not filed within 60 days of execution of the waiver and release as required by OCGA § 44-14-366 (f) (2). In so doing, the court found

that the only evidence in the record as to the date of execution of the Waiver and Release is the date contained on the face of the document, that being December 22, 2014. At best, Bibler has produced an affidavit indicating that Bibler submitted an executed Waiver to [JTT] on February 17, 2015. This submission date, however, sheds no additional light on the question of when the document was actually executed.

(Footnote omitted.) The court therefore granted summary judgment in favor of JMLS. On motion for reconsideration, Bibler filed an additional affidavit in which the person who signed the waiver and release on behalf of Bibler averred that she actually signed it on February 17, 2015, but backdated it to December 22, 2014, the date of substantial completion of the project, at the request of JTT. After the trial court denied Bibler’s motion for reconsideration, Bibler filed this appeal, which requires us to construe the applicable statute.

When construing a statute, “we must presume that the General Assembly meant what it said and said what it meant.” Deal v. Coleman, 294 Ga. 170, 172 (1) (a) (751 SE2d 337) (2013) (citation and punctuation omitted). Thus if the language of the statute “is plain and unambiguous, judicial construction is not only unnecessary but forbidden.” Six Flags Over Ga. II v. Kull, 276 Ga. 210, 211 (576 SE2d 880) (2003) (citation omitted). Where terms of art are not involved, we look to the common and customary usages of the words and their context. Zaldivar v. Prickett, 297 Ga. 589, 591 (1) (774 SE2d 688) (2015). “For context, we may look to other provisions of the same *493 statute, the structure and history of the whole statute, and the other law — constitutional, statutory, and common law alike — that forms the legal background of the statutory provision in question.” Id. (citation and punctuation omitted). Finally, in this State “lien statutes in derogation of the common law must be strictly construed in favor of the property owner and against the materialman.” Few v. Capitol Materials, 274 Ga. 784, 785 (1) (559 SE2d 429) (2002) (citation omitted).

The rationale is that there is usually no contract between the owner and supplier. Instead, a materialman’s lien effectively permits the transfer of liability from the person who actually contracted with the materialman for materials to be used in improving real estate to the owner of the improved property.

Id. (citation and punctuation omitted).

The lien statute, among other things, allows that once the labor, services, or materials have been furnished by a materialman such as Bibler, a contractor may ask the materialman “to execute a waiver and release in exchange for or in order to induce making of final payment.” OCGA § 44-14-366 (d). The waiver and release must substantially follow a form provided for that purpose in the statute, and it must include certain notice language. Id. The statutory form, in relevant part, provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
798 S.E.2d 19, 340 Ga. App. 490, 2017 WL 922955, 2017 Ga. App. LEXIS 86, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bibler-masonry-contractors-inc-v-j-t-turner-construction-co-inc-gactapp-2017.