Arcadis S U Inc v. Stryker Demolition & Environmental Services L L C

District Court, W.D. Louisiana·Decided July 5, 2023·No. 5:20-cv-00471·Unknown

Opinion

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF LOUISIANA SHREVEPORT DIVISION

ARCADIS U.S., INC. CIVIL ACTION NO. 20-0471

VERSUS JUDGE S. MAURICE HICKS, JR.

STRYKER DEMOLITION & MAGISTRATE JUDGE HORNSBY ENVIRONMENTAL SERVICES, LLC

MEMORANDUM RULING

Before the Court is a Rule 12(c) Motion for Partial Judgment on the Pleadings [Fraud] filed by Plaintiff and Defendant-in-Counterclaim, Arcadis U.S., Inc.’s (“Arcadis”). See Record Document 93. Specifically, Arcadis seeks the dismissal of the fraud claims asserted in the Amended Counterclaim of Defendant and Counterclaimant, Stryker Demolition & Environmental Services, LLC (“Stryker”). See id. Stryker has opposed the motion. See Record Document 97. Arcadis replied. See Record Document 98. For the reasons set forth below, Arcadis’s Rule 12(c) Motion is hereby GRANTED. FACTUAL AND PROCEDURAL BACKGROUND This litigation arises from a large-scale demolition and abatement project (“the Project”) in Shreveport, Louisiana. Arcadis entered into an agreement with Ansell Healthcare Products, LLC (“Ansell”), whereby Arcadis agreed to contract with a demolition contractor and supply project management for the demolition of the former battery manufacturing facility located at 6901 Westport Avenue in Shreveport, Louisiana. In addition to demolition, the Project also included disposal of lead and asbestos roofing materials. In accordance with a Services Agreement between Ansell and Arcadis, Arcadis formulated the bid specification package, solicited bids from contractors, performed contractor evaluations, and provided related services for the Project. In September 2018, Arcadis prepared a request for proposals entitled “Work Plan – Environmental Removals and Demolition, Former Battery Manufacturing Facility, Shreveport, Louisiana” to solicit bids by contractors for the Project.

In October 2018, interested bidders, including Stryker, attended two site visits (“Bid Walks”). Arcadis maintains that during the Bid Walks, the prospective bidders observed layers of roofing material from the exposed, fire-damaged portions of the roof. Stryker submits that it was “unbeknownst” to it that there was a second roofing system hidden beneath the visible roofing system. Stryker also contends it was unknown that the roofing systems were heavily and pervasively saturated with water. According to Stryker, following the Bid Walks, the prospective bidders were permitted to submit questions to Arcadis seeking further information and clarification as to the Project requirements and site conditions. Specific questions were asked regarding whether the roof samplers dug into the roof to take “core” samples. Arcadis answered this question in the affirmative. It

was never disclosed that there was a second roofing system or that the roofing systems were heavily saturated. Thereafter, three bids were submitted for the Project, with Stryker’s bid as the lowest, responsive bid. Arcadis hired Stryker as the demolition subcontractor on the Project and, on December 11, 2018, they entered into an Agreement for Subcontractor Services. Schedule F of the Subcontract contained “Special Provisions for Construction Services.” Record Document 93-3 at 76. Subsection SP-F6 Site Conditions provides, in pertinent part: Subcontractor represents and warrants that it has had an opportunity to review and/or has carefully examined all necessary drawings, maps, schematics, specifications, governmental restrictions, permits and license requirements, and all applicable laws, regulations and rules relating to the Work to be done and the Site, it surroundings and local conditions, and has made all investigations based on reasonably available information that are necessary to develop a full understanding of the hazards and difficulties which can be encountered and are likely to impact the cost or schedule to perform the Work. SUBCONTRACTOR is thus familiar with conditions at the Site as are pertinent to or which may affect the Work and has been granted the right to conduct, and has conducted, all investigations it deems appropriate to determine that it can fulfill the requirements of this Contract. Notwithstanding any other provision of this Contract, SUBCONTRACTOR assumes the risk of all conditions, as specified in this Contract, that may affect SUBCONTRACTOR’s ability to perform the Work and will, regardless of such conditions, or the expense or difficulty of performing the Work or the negligence, if any, of Arcadis, with respect to same, fully complete the Work for the stated price without further recourse to Arcadis. Information on the Site and local conditions at the Site furnished by Arcadis are not guaranteed by Arcadis to be accurate, and is furnished only for the convenience of SUBCONTRACTOR.

The discovery of concealed conditions which could not reasonably have been anticipated by the SUBCONTRACTOR from information available to SUBCONTRACTOR may constitute a changed condition, which, to the extent such condition materially affects the cost or schedule to perform the Work, would entitle the SUBCONTRACTOR to a change and an equitable adjustment of the Contract price or time. SUBCONTRACTOR warrants that it shall conduct appropriate investigations to determine, with reasonable certainty, the location of utility and service lines, underground storage systems, and other subsurface structures of any kind before commencement of any drilling excavation, or other work that has the potential to disturb these structures. SUBCONTRACTOR further warrants that it shall conduct independent field investigations to confirm the location of subsurface structures before commencement of subsurface work and shall not rely exclusively on plot plans or other drawings provided to SUBCONTRACTOR in conducting these investigations.

Id. at 76-77.

Stryker began its work on the Project on December 19, 2018. In May 2019, Stryker submitted a change order request for additional compensation for work relating to removal of the hazardous roofing material, namely the unanticipated weight of the hazardous roofing material removed. Arcadis rejected the change order request because the request for proposal and the Subcontract dictated that all transportation and disposal costs were to be included in Stryker’s bid amount and that Stryker would assume the risk of all conditions regarding site conditions. Stryker substantially completed its work on the

Project by July 26, 2019. The Project was closed out on October 7, 2019. The full contract price of $2,049,369 was paid to Stryker. On October 10, 2019, Stryker filed a Lien for $388,587.90 for “concealed conditions for the removal, transportation, and disposal of lead contaminated non-friable asbestos material.” Record Document 1-2 at ¶ 18. The Lien was recorded in the mortgage records in Caddo Parish, Louisiana. See id. On October 22, 2019, Arcadis demanded Stryker release and cancel the Lien. See Record Document 1-2 at ¶ 20. Stryker canceled the Lien on April 14, 2020. On November 18, 2019, Arcadis submitted a “Notice of Claim” to Stryker “for all additional costs incurred by Arcadis as a result of Stryker’s delayed progress during

project implementation at the Ansell Battery Plant demolition project.” Record Document 60-4 at 23-24. Litigation then ensued. Arcadis asserted three claims against Stryker: failure to timely perform; breach of contract for filing a lien; and damages for wrongful filing of line. See Record Document 1-3.1 Stryker filed an Amended Counterclaim for, inter alia, fraud. See Record Document 88 at 29-32. Stryker alleges fraudulent misrepresentation under Louisiana Civil Code

1 Stryker filed a Motion for Summary Judgment (Record Document 50) seeking to dismiss these claims. Such motion was recently granted in part and denied in part. See Record Documents 103-104.

Free access — add to your briefcase to read the full text and ask questions with AI

Arcadis S U Inc v. Stryker Demolition & Environmental Services L L C, (W.D. La. 2023).

Arcadis S U Inc v. Stryker Demolition & Environmental Services L L C (Arcadis S U Inc v. Stryker Demolition & Environmental Services L L C) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

T L James & Co Inc v. Traylor Bros Inc
294 F.3d 743 (Fifth Circuit, 2002)
Doe v. MySpace, Inc.
528 F.3d 413 (Fifth Circuit, 2008)
Dorsey v. Portfolio Equities, Inc.
540 F.3d 333 (Fifth Circuit, 2008)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Plaquemines Par. Com'n Council v. Delta Dev. Co.
502 So. 2d 1034 (Supreme Court of Louisiana, 1987)
Becnel v. Grodner
982 So. 2d 891 (Louisiana Court of Appeal, 2008)
Thomas v. Pride Oil & Gas Properties, Inc.
633 F. Supp. 2d 238 (W.D. Louisiana, 2009)
Scheffler v. Adams and Reese, LLP
950 So. 2d 641 (Supreme Court of Louisiana, 2007)
Wilson v. Mobil Oil Corp.
940 F. Supp. 944 (E.D. Louisiana, 1996)
Allen Thompson v. City of Waco, Texas
764 F.3d 500 (Fifth Circuit, 2014)
Griffing v. Atkins
1 So. 2d 445 (Louisiana Court of Appeal, 1941)
McCarthy v. Evolution Petroleum Corp.
180 So. 3d 252 (Supreme Court of Louisiana, 2015)