Arcadis S U Inc v. Stryker Demolition & Environmental Services L L C

CourtDistrict Court, W.D. Louisiana
DecidedMarch 1, 2021
Docket5:20-cv-00471
StatusUnknown

This text of Arcadis S U Inc v. Stryker Demolition & Environmental Services L L C (Arcadis S U Inc v. Stryker Demolition & Environmental Services L L C) is published on Counsel Stack Legal Research, covering District Court, W.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arcadis S U Inc v. Stryker Demolition & Environmental Services L L C, (W.D. La. 2021).

Opinion

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF LOUISIANA SHREVEPORT DIVISION

ARCADIS U.S., INC. CIVIL ACTION NO. 20-0471

VERSUS JUDGE S. MAURICE HICKS, JR.

STRYKER DEMOLITION & MAGISTRATE JUDGE HORNSBY ENVIRONMENTAL SERVICES, LLC

MEMORANDUM RULING

Before the Court is a Motion to Dismiss filed by Defendant Stryker Demolition & Environmental Services, LLC (hereinafter “Stryker”). See Record Document 9. Plaintiff Arcadis U.S., Inc. (“Arcadis”) opposes dismissal. See Record Document 15. Stryker has filed a reply. See Record Document 16. For the foregoing reasons, Stryker’s Motion is hereby DENIED. FACTUAL AND PROCEDURAL BACKGROUND This matter concerns the interpretation of a subcontracting agreement (the “Subcontract”) between Arcadis and Stryker. The relevant provision in the Subcontract itself states: 20. MEDIATION / ARBITRATION / ALTERNATIVE DISPUTE RESOLUTION If any dispute arises out of or relates to this Agreement, or the breach thereof, and the dispute cannot be settled through direct discussions by the representatives of the Parties, the Parties agree to submit the matter in accordance with the provisions of the Prime Contract between Arcadis and its Client… When not specified by the Prime Contract, the matter shall be submitted for mediation under the Construction Industry Mediation Rules of the American Arbitration Association before having recourse to a judicial forum. Record Document 9-2 (emphasis added). The referenced “Prime Contract” pertains to a Master Services Agreement between Arcadis and Ansell Healthcare Products, LLC (“Ansell”), whereby Arcadis agreed to hire a demolition subcontractor and manage the demolition of a battery manufacturing facility in west Shreveport. See Record Document 15 at 2. The relevant provision of the Prime

Contract (the “Mediation Provision”) provides: 34. Mediation If any dispute arises out of or relates to this Agreement or the breach thereof, then said dispute will first be referred to a panel consisting of at least one representative of each Party having authority to enter into agreements to settle the dispute… If the dispute cannot be settled through direct discussions by the panel representatives of the Parties, the Parties agree then to submit the matter to mediation under the Construction Industry Mediation Rules of the American Arbitration Association before having recourse to a judicial forum. Record Document 9-2 (emphasis added). The low bidder on this project was Stryker, and on December 11, 2018 Arcadis and Stryker entered into the Subcontract. See id. The project was scheduled to be completed by June 3, 2019; however, work was not substantially completed until July 26, 2019. See Record Document 1-2 at ¶¶12-13. Prior to completion, Stryker submitted a Change Order request for $169,679 for removal of hazardous roofing material that it claimed was heavier than expected due to rainfall saturation. See id. at ¶14. Arcadis denied this request. See id. at ¶15. In response, Stryker recorded a mechanic’s lien against the project site in the Caddo Parish mortgage records. See id. at ¶18. This dispute could not be resolved, leading Stryker to request mediation through the American Arbitration Association on November 22, 2019. See Record Document 9-1 at 4. Soon after, the parties agreed to a one-day mediation conference in New Orleans on March 11, 2020 with H. Bruce Shreves serving as mediator. See Record Document 15 at 3.

After a day of negotiations failed to produce an agreement, Stryker left Arcadis with a last-and-final settlement offer. See Record Document 9-1 at 4. Arcadis requested time to consider, and a response deadline of Friday March 13, 2020 was set. See id. at 4-5. As that deadline neared, Arcadis asked for and was granted an extension until the close of business on March 16. See id. at 5. Despite additional time, Arcadis ultimately rejected Stryker’s offer. See id.

Stryker replied to this email rejection by asking counsel for Arcadis if they were authorized to accept service of a complaint to be filed in Delaware state court. See id. Counsel for Arcadis responded that it had already filed suit against Stryker in the First Judicial District Court of the State of Louisiana, Caddo Parish, on March 11—the same day mediation commenced—and provided a copy of its complaint. See id. Further investigation by Stryker revealed that Arcadis had fax-filed this complaint while the mediation was ongoing and requested that service be withheld until March 23, 2020. See id. at 5-6. Frustrated by what it believed to be a premature filing, Stryker filed suit against Arcadis and Ansell in Delaware state court on March 17, 2020. See id. at 6.

Arcadis’ suit was removed by Stryker to this Court on April 15, 2020. See Record Document 1. Arcadis claims: (1) breach of contract for failure to timely perform, (2) breach of contract for filing an improper lien, and (3) damages for the filing of said lien. See Record Document 1-2. Stryker’s instant Motion is not directed towards these specific claims. Instead, Stryker argues for dismissal under Rules 12(b)(1) and 12(b)(6) for failure to abide by the Mediation Provision. See Record Document 9. LAW AND ANALYSIS

I. Evidentiary Objections Before considering the merits of Stryker’s Motion to Dismiss, the Court must first address a dispute over what documentary evidence it may consider. Although generally courts are constrained to the contents of the pleadings themselves when ruling on a 12(b)(6) motion to dismiss, limited exceptions do exist. See Collins v. Morgan Stanley Dean Witter, 224 F.3d 496, 498 (5th Cir. 2000). Specifically, a court may consider documents attached to the motion to dismiss if they are referenced in the plaintiff’s

complaint and are central to the plaintiff’s claims. See Scanlan v. Texas A&M University, 343 F.3d 533, 536 (5th Cir. 2003). Arcadis objects to three documents attached to Stryker’s Motion: (1) the declaration of Mark F. Klotzbach, Sr. (Record Document 9-3); (2) a Westlaw printout of a secondary source discussing mediation as a condition precedent in contracts (Record Document 9-4); and (3) the declaration of Anthony L. Byler (Record Document 9-7). See

Record Document 15 at 25. These documents were not referenced in Arcadis’ complaint, nor do they relate to Arcadis’ claims. Rather, all three documents are central to Stryker’s arguments in favor of dismissal based upon Arcadis’ failure to mediate. Having not met the limited exception for consideration, the Court will not rely upon these three documents when analyzing the instant Motion. II. Rule 12(b)(1) Dismissal for Lack of Subject Matter Jurisdiction

When a Rule 12(b)(1) motion is filed alongside other Rule 12 motions, the court must consider the jurisdictional attack before any merit-based arguments. See Hitt v. City of Pasadena, 561 F.2d 606, 608 (5th Cir. 1977). The burden of proof for a Rule 12(b)(1) motion is on the party asserting jurisdiction. See Menchaca v. Chrysler Credit Corp., 613 F.2d 507, 511 (5th Cir. 1980). A motion to dismiss for lack of subject matter jurisdiction should only be granted if it appears certain the plaintiff cannot prove any set of facts that

would entitle the plaintiff to relief. See Home Builders Ass’n of Miss., Inc. v. City of Madison, Miss., 143 F.3d 1006, 1010 (5th Cir. 1998).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Collins v. Morgan Stanley Dean Witter
224 F.3d 496 (Fifth Circuit, 2000)
Scanlan v. Texas A&M University
343 F.3d 533 (Fifth Circuit, 2003)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
United States v. Manning
526 F.3d 611 (Tenth Circuit, 2008)
Fluor Enterprises, Inc. v. Solutia Inc.
147 F. Supp. 2d 648 (S.D. Texas, 2001)
Stone & Webster, Inc. v. Georgia Power Company
968 F. Supp. 2d 1 (District of Columbia, 2013)
Alexander Edionwe v. Guy Bailey
860 F.3d 287 (Fifth Circuit, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Arcadis S U Inc v. Stryker Demolition & Environmental Services L L C, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arcadis-s-u-inc-v-stryker-demolition-environmental-services-l-l-c-lawd-2021.