Arcadis S U Inc v. Stryker Demolition & Environmental Services L L C

District Court, W.D. Louisiana·Decided July 6, 2023·No. 5:20-cv-00471·Unknown

Opinion

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF LOUISIANA SHREVEPORT DIVISION

ARCADIS U.S., INC. CIVIL ACTION NO. 20-0471

VERSUS JUDGE S. MAURICE HICKS, JR.

STRYKER DEMOLITION & MAGISTRATE JUDGE HORNSBY ENVIRONMENTAL SERVICES, LLC

MEMORANDUM RULING

Before the Court are two Motions for Partial Summary Judgment (Record Documents 55 and 56) filed by Plaintiff and Defendant-in-Counterclaim, Arcadis U.S., Inc.’s (“Arcadis”). In the first motion, Arcadis seeks dismissal of Defendant and Counterclaimant, Stryker Demolition & Environmental Services, LLC’s (“Stryker”) breach of contract counterclaims relating to removal of roofing material, removal of sludge from tanks, draining and backfilling of subsurface vaults and holes, and costs incurred due to a threatened shooter on the Project. See Record Document 55. In the second motion, Arcadis seeks dismissal of Stryker’s breach of contract counterclaim relating to the removal of additional concrete on the Project. See Record Document 56. Stryker opposed both motions. See Record Document 64 and 65. Arcadis replied. See Record Documents 72 and 73. For the reasons set forth below, Arcadis’s motions are DENIED. FACTUAL AND PROCEDURAL BACKGROUND This litigation arises from a large-scale demolition and abatement project (“the Project”) in Shreveport, Louisiana. Arcadis entered into an agreement with Ansell Healthcare Products, LLC (“Ansell”), whereby Arcadis agreed to contract with a demolition contractor and supply project management for the demolition of the former battery manufacturing facility located at 6901 Westport Avenue in Shreveport, Louisiana. In addition to demolition, the Project also included disposal of lead and asbestos roofing materials. In accordance with a Services Agreement between Ansell and Arcadis, Arcadis formulated the bid specification package, solicited bids from contractors,

performed contractor evaluations, and provided related services for the Project. In October 2018, interested bidders, including Stryker, attended two site visits (“Bid Walks”). Arcadis maintains that during the Bid Walks, the prospective bidders observed layers of roofing material from the exposed, fire-damaged portions of the roof. According to Stryker, following the Bid Walks, the prospective bidders were permitted to submit questions to Arcadis seeking further information and clarification as to the Project requirements and site conditions. Thereafter, three bids were submitted for the Project, with Stryker’s bid as the lowest, responsive bid. In response to the Request for Proposal, Stryker submitted to Arcadis a “Work Plan & Proposal” for the Project, dated November 2, 2018 and November 15, 2018. See

Record Document 56-5 at 10-58. On December 11, 2018, Arcadis and Stryker entered into an “Agreement for Subcontractor Services” (“the Subcontract”). Id. at 1-79. Schedule A (General Terms and Conditions) of the Subcontract provided: 6. CHANGES. No changes to this Agreement and no extra charges will be allowed unless a duly authorized representative of Arcadis specifically agrees to them in writing. As a condition precedent to SUBCONTRACTOR’s recovery on any claim for an increase in the cost of the Work or for an extension of time to complete the Work (a “Claim”), SUBCONTRACTOR shall, immediately after the occurrence of the event which SUBCONTRACTOR believes may give rise to a Claim, give Arcadis written notice of the claim, which notice shall contain a verified statement that supports the claim and details the estimated change in the Subcontract cost and the time to complete the Work. SUBCONTRACTOR’s failure to provide notice as required by this paragraph shall be a waiver of SUBCONTRACTOR’s right to recovery under the terms of the Prime Contract between Arcadis and its Client on a Claim. In no event shall SUBCONTRACTOR be entitled to compensation for changes which are not reimbursable to Arcadis by its Client. In no event shall SUBCONTRACTOR be entitled to any reverse liquidated damages, charges, other expenses incurred by SUBCONTRACTOR by reason of delays in the performance of the Services, caused by Arcadis or its Client. Any determination by Arcadis or Client with regard to same shall be binding upon SUBCONTRACTOR.

Record Document 55-4 at 3 (emphasis added).1

Stryker began its work on the Project on December 19, 2018. See Record Document 1-2 at ¶ 12. Sometime in February or March 2019, Stryker discovered there were two roofing systems. See Record Document 55-6 (Deposition of Mark Klotzbach, Sr.) at 337. On May 14, 2019, Stryker submitted a Change Order Request (“COR”) for additional contract price for work relating to the unanticipated weight of hazardous roofing material removed from the site that Stryker alleges it did not account for in its bid. Arcadis rejected the COR because the subject request for proposals and Subcontract stated that all transportation and disposals costs were to be included in Stryker’s bid amount and that Stryker would assume the risk of all site conditions. The Project was closed out on October 7, 2019. See Record Document 1-2 at ¶ 17. The full contract price of $2,049,369 was paid to Stryker. See id. On October 10, 2019, Stryker filed a Statement of Claim and Privilege, or mechanic’s lien (“the Lien”), for $388,587.90 for “concealed conditions for the removal, transportation, and disposal of lead contaminated non-friable asbestos material.” Record Document 1-2 at ¶ 18. The Lien was recorded in the mortgage records in Caddo Parish, Louisiana. See id. On

1 The Prime Contract referenced in Schedule A(6) refers to the Services Agreement between Ansell and Arcadis. The Subcontract expressly incorporated the terms and conditions of the Prime Contract. See Record Document 55-4 at 1. October 22, 2019, Arcadis demanded Stryker release and cancel the Lien. See Record Document 1-2 at ¶ 20. Stryker canceled the Lien on April 14, 2020. On November 18, 2019, Arcadis submitted a Notice of Claim to Stryker for all additional costs incurred by Arcadis as a result of Stryker’s delayed progress during project implementation at the

Ansell Battery Plant demolition project. The Notice of Claim stated that the actual project completion exceeded 150 working days. See id. Litigation then ensued. Arcadis filed suit in state court on March 11, 2020. See Record Document 1. The suit was removed by Stryker to this Court on April 15, 2020. See id. Arcadis asserted three causes of action/claims: (1) breach of contract for failure to timely perform, (2) breach of contract for filing an improper lien, and (3) damages for the filing of said lien. See Record Document 1-2. Stryker’s motion seeking dismissal of these claims was granted in part and denied in part. See Record Documents 103 and 104. The motion was granted as to the failure to timely perform claim but denied as to the claims relating to the Lien. See id.

In its Amended Counterclaim, Stryker asserted counterclaims for breach of contract and fraud. See Record Document 88. The fraud counterclaim was dismissed by this Court on July 5, 2023. See Record Documents 105 and 106. The instant motions seek dismissal of the breach of contract counterclaims. See Record Documents 55 and 56. The first set of breach of contract counterclaims relate to additional costs regarding the removal of roofing material ($470,604.63), the removal of sludge from tanks ($9,784.80), the draining and backfilling of subsurface vaults and holes ($14,729.87), and a threatened shooter on the Project ($16,874.17). See Record Document 55; see also Record Document 88 at ¶¶ 50-80, 87-98. Arcadis argues Striker failed to follow the Subcontract and did not give immediate written notice to Arcadis regarding these claims, thereby waiving such claims. See Record Document 55.

Free access — add to your briefcase to read the full text and ask questions with AI

Arcadis S U Inc v. Stryker Demolition & Environmental Services L L C, (W.D. La. 2023).

Arcadis S U Inc v. Stryker Demolition & Environmental Services L L C (Arcadis S U Inc v. Stryker Demolition & Environmental Services L L C) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Streber v. Hunter
221 F.3d 701 (Fifth Circuit, 2000)
General Universal Systems, Inc. v. Lee
379 F.3d 131 (Fifth Circuit, 2004)
Boudreaux v. Swift Transportation Co.
402 F.3d 536 (Fifth Circuit, 2005)
Capitol Nursing Home, Inc. v. Nixon
764 So. 2d 1016 (Louisiana Court of Appeal, 2000)
Gravier Co. v. Satellite Business Sys.
519 So. 2d 180 (Louisiana Court of Appeal, 1987)
Wisinger v. Casten
550 So. 2d 685 (Louisiana Court of Appeal, 1989)
Grossie v. Lafayette Construction Co., Inc.
306 So. 2d 453 (Louisiana Court of Appeal, 1975)
Peter Vicari General Contractor, Inc. v. St. Pierre
831 So. 2d 296 (Louisiana Court of Appeal, 2002)
RHODES STEEL BLDGS. v. Walker Const. Co.
813 So. 2d 1171 (Louisiana Court of Appeal, 2002)
Pelican Elec. Contractors v. Neumeyer
419 So. 2d 1 (Louisiana Court of Appeal, 1982)
Hall v. Malone
104 So. 3d 593 (Louisiana Court of Appeal, 2012)
Landis Construction Co. v. St. Bernard Parish
151 So. 3d 959 (Louisiana Court of Appeal, 2014)