Arbitration Between Laminoirs-Trefileries-Cableries De Lens, S. A. v. Southwire Co.

484 F. Supp. 1063, 1980 U.S. Dist. LEXIS 10097
CourtDistrict Court, N.D. Georgia
DecidedFebruary 18, 1980
DocketCiv. A. C79-43N, C79-44N
StatusPublished
Cited by21 cases

This text of 484 F. Supp. 1063 (Arbitration Between Laminoirs-Trefileries-Cableries De Lens, S. A. v. Southwire Co.) is published on Counsel Stack Legal Research, covering District Court, N.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arbitration Between Laminoirs-Trefileries-Cableries De Lens, S. A. v. Southwire Co., 484 F. Supp. 1063, 1980 U.S. Dist. LEXIS 10097 (N.D. Ga. 1980).

Opinion

ORDER

TIDWELL, District Judge.

The above-styled matter is before the Court pursuant to Laminoirs-Trefileries-Cableries de Lens’ (“LTCL”) motion for confirmation of arbitral awards, and Southwire Company’s and ■ Southwire International Corporation’s (“Southwire”) opposition thereto. .

Background

Southwire, a Georgia corporation which manufactures cable products, and LTCL, a French société anonyme which manufactures steel wire and rope, entered into a purchase agreement in 1974, whereby LTCL agreed to manufacture and sell, and South-wire agreed to buy, galvanized steel wire during the period from September 1, 1974, through December 31, 1980. The price to be paid by Southwire was to be determined and adjusted according to a formula based on the world market price of steel wire (“world market price adjustment clause”). Said purchase agreement contained an arbitration clause, and also contained a governing law clause, stating that the agreement would be governed by the laws of Georgia insofar as these laws are in accordance with French laws.

Disputes arose as to the interpretation of the world market price adjustment clause, alleged corrosion of the goods supplied by LTCL (“corrosion claim”), and alleged flaking of the zinc coating on the wire (“flaking claim”).

Pursuant to the arbitration clause in the contract, LTCL demanded arbitration before an international tribunal in accordance with the rules of the International Chamber of Commerce (“ICC”). The Terms of Reference for such arbitration were signed by the parties and arbitrators on July 17,1979.

*1066 On February 8, 1979, the arbitrators made a partial arbitral award, which accepted LTCL’s interpretation of the world market price adjustment clause; ordered Southwire to pay LTCL the aggregate amount of underpayments caused by South-wire’s interpretation of the clause (plus interest at the French legal rate); found in favor of Southwire on the corrosion claim (so that the amount of damage would be withheld from funds due LTCL);. reserved judgment on the flaking claim and the costs of arbitration.

The parties thereafter settled the flaking claim, and on April 12, 1979, the tribunal entered a further arbitral award, confirming settlement of the flaking claim and allocating costs.

Southwire filed a state court action in Georgia, seeking, vacation of the awards, which was removed to this court by LTCL. LTCL also filed a separate suit seeking confirmation of the awards. These actions have been consolidated.

Southwire has three basic objections to confirmation of the arbitral awards. These are:

(1) that the award was not made within six months from the date of the signing of the Terms of Reference for arbitration (as required by the rules of the ICC);
(2) that the arbitrators refused to entertain certain evidence deemed by Southwire to be material to its presentation of the case;
(3) that the arbitrators erroneously adopted the French legal rate of interest on the amounts due, without the introduction of any evidence on the French law or notice being given to Southwire that French law would be invoked; that the French rate applied violates the enforcing forum’s public policy and is usurious; that the interest award is inconsistent with the Terms of Reference insofar as it awards post-award interest.

Timeliness

With respect to the fact that the award was not made within six months after the Terms of Reference were signed, the Rules of the ICC Court of Arbitration provide that the court may, “if need be on its own initiative extend this time limit if it decides that it is necessary to do so.” Art. 18, par. 2, ICC Rules. It appears from the record that when the date for the session of the court was moved from January 8, 1979 (before the six-month time period had elapsed) to January 19, 1979 (after the six-month limit), the court on its own motion extended the time in which a final award was to be rendered to April 30, 1979, and again on its own motion on April 11, 1979, further extended this date to July 21, 1979.

The above-cited rule for extension does not call for advance notice to the parties, should the court grant such an extension, on its own .motion. Further, there is nothing to indicate that Southwire lodged any protest once the initial six-month period had elapsed. In order to preserve one’s rights, it is essential to protest against continuance of the arbitration proceedings after the stipulated time has elapsed. Lodge No. 725, International Assoc. of Machinists v. Mooney Aircraft, Inc., 410 F.2d 681, 683 (5th Cir. 1969). A partial arbitral award, which dealt with the major substantive issues under submittal, was rendered three weeks after the initial six-month limit had elapsed. Southwire has not shown that any prejudice or actual harm was caused by the delay. See Hotel, Motel, Restaurant and Hi-Rise Employees and Bartenders Union, Local 355 v. Fontainebleau Hotel Corp., 423 F.Supp. 83 (S.D.Fla.1976). For these reasons, the Court declines to vacate the awards on the ground of untimeliness.

Exclusion of Evidence

Southwire contends that it was prevented from offering certain pertinent evidence at the arbitral hearing. In particular, it is argued that Southwire’s attorney was prevented from fully cross-examining LTCL’s international projects manager with regard to a renegotiation clause in the contract, and that allowance of such questioning would have been pertinent in showing an *1067 intent on the part of' LTCL to anticipatorily repudiate the contract.

The record reveals that the chairman of the arbitral tribunal expressed his willingness to allow Southwire to introduce facts relating to the renegotiation clause as having potential bearing on the intent of the parties at the time of the signing of the contract (T. 90). The arbitrators, however, were concerned that Southwire’s questioning was aimed at eliciting admissions from the witness as to future course of conduct which would have no bearing on the matter before the tribunal (T. 85). Therefore, the chairman limited the questioning to “matters of fact albeit recent matters of fact which might conceivably have some bearing on what was the intent of the parties several years ago” (T. 85) (see also TT. 90, 99). Southwire was allowed to introduce documentary evidence on the parties’ alleged intent as to future course of action, and allowed to make “argumentative interpretation” of such evidence in its summation to the tribunal (T. 104).

In its argument on improper exclusion of evidence, Southwire relies upon 9 U.S.C. § 10(c), which provides in pertinent part that a district court may vacate the award “where the arbitrators were guilty of misconduct ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yukos Capital S.A.R.L. v. OAO Samaraneftegaz
963 F. Supp. 2d 289 (S.D. New York, 2013)
Matthews v. Princess Cruise Lines, Ltd.
728 F. Supp. 2d 1326 (S.D. Florida, 2010)
Krstic v. PRINCESS CRUISE LINES, LTD.(CORP.)
706 F. Supp. 2d 1271 (S.D. Florida, 2010)
Green v. Ameritech Corp.
12 F. Supp. 2d 662 (E.D. Michigan, 1998)
Nitram, Inc. v. Industrial Risk
Eleventh Circuit, 1998
Ingersoll Milling MacHine Co. v. John P. Granger
833 F.2d 680 (Seventh Circuit, 1987)
Brandeis Intsel Ltd. v. Calabrian Chemicals Corp.
656 F. Supp. 160 (S.D. New York, 1987)
Rosenberg v. Rosenberg
497 A.2d 485 (Court of Special Appeals of Maryland, 1985)
UCO Terminals, Inc. v. Apex Oil Co.
583 F. Supp. 1213 (S.D. New York, 1984)
Cronel Watch, S.A. v. Peterson State Bank
565 F. Supp. 259 (N.D. Illinois, 1983)
In Re National Trade Corp.
22 B.R. 877 (N.D. Illinois, 1982)
Hammond v. James W. Griffin Co., Inc.
520 F. Supp. 162 (N.D. Georgia, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
484 F. Supp. 1063, 1980 U.S. Dist. LEXIS 10097, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arbitration-between-laminoirs-trefileries-cableries-de-lens-s-a-v-gand-1980.