Appalachian Power Company v. FERC

CourtCourt of Appeals for the Fourth Circuit
DecidedMarch 4, 2025
Docket23-1192
StatusUnpublished

This text of Appalachian Power Company v. FERC (Appalachian Power Company v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Appalachian Power Company v. FERC, (4th Cir. 2025).

Opinion

USCA4 Appeal: 23-1192 Doc: 67 Filed: 03/04/2025 Pg: 1 of 15

UNPUBLISHED

UNITED STATES COURT OF APPEALS FOR THE FOURTH CIRCUIT

No. 23-1192

APPALACHIAN POWER COMPANY

Petitioner

BLUE RIDGE POWER AGENCY

Intervenor

v.

FEDERAL ENERGY REGULATORY COMMISSION,

Respondent.

On Petition for Review of an Order of the Federal Energy Regulatory Commission. (21- 97-000)

Argued: September 26, 2024 Decided: March 4, 2025

Before NIEMEYER, Circuit Judge, FLOYD, Senior Circuit Judge, and Kenneth D. BELL, United States District Judge for the Western District of North Carolina, sitting by designation.

Petition for review denied by unpublished per curiam opinion.

ARGUED: William Keyser, III, STEPTOE LLP, Washington, D.C., for Petitioner. Carol J. Banta, FEDERAL ENERGY REGULATORY COMMISSION, Washington, D.C., for Respondent. ON BRIEF: Karen Bruni, Megan McDowell, STEPTOE & JOHNSON USCA4 Appeal: 23-1192 Doc: 67 Filed: 03/04/2025 Pg: 2 of 15

LLP, Washington, D.C.; Jessica A. Cano, Assistant General Counsel, AMERICAN ELECTRIC POWER SERVICE CORPORATION, Columbus, Ohio, for Petitioner. Matthew R. Christiansen, General Counsel, Robert H. Solomon, Solicitor, FEDERAL ENERGY REGULATORY COMMISSION, Washington, D.C., for Respondent.

Unpublished opinions are not binding precedent in this circuit.

2 USCA4 Appeal: 23-1192 Doc: 67 Filed: 03/04/2025 Pg: 3 of 15

PER CURIAM:

This case concerns the interpretation of contracts between member utilities of the

Blue Ridge Power Agency and Petitioner Appalachian Power Company (APCO). The

Federal Energy Regulatory Commission (FERC) issued an order declaring that Blue Ridge

members may install battery storage, energize the batteries with electricity purchased from

APCO, and discharge that electricity during periods of peak demand without violating

those agreements. APCO filed a petition for review challenging the Commission’s

decision. For the reasons we explain below, we deny the petition.

I.

Blue Ridge, appearing as intervenor aligned with FERC, is a non-profit entity that

negotiates wholesale power purchase contracts on behalf of its members and monitors

performance of those contracts. In 2017, APCO and three Blue Ridge members—Craig-

Botetourt Electric Cooperative and the cities of Radford and Salem, Virginia (collectively,

the “Members”)—executed three respective agreements for “Full Requirements Electric

Service.” J.A. 352. Under these agreements, APCO sells to the Members all electricity

required to meet their end-use customers’ needs. In return, the Members purchase all the

electricity they require from APCO and no one else. These three agreements contained

substantially identical language and did not expressly authorize or forbid installation of

battery storage technology (BST). This technology is aptly named: it consists of large-

scale batteries capable of storing energy and discharging it to the electrical grid on demand.

A fourth agreement for APCO to supply wholesale electricity to Virginia Polytechnic

3 USCA4 Appeal: 23-1192 Doc: 67 Filed: 03/04/2025 Pg: 4 of 15

Institute and State University (Virginia Tech) in Blacksburg, Virginia, contained

provisions limiting BST installation. The Virginia Tech Agreement was executed in 2019.

Relevant to the present appeal, each of these contracts also contained a choice of law clause

providing for its interpretation under Virginia law.

In 2021, Blue Ridge informed APCO that its members intended to install BST to

manage electrical loads at times of peak demand. These batteries would be energized using

power purchased from APCO during off-peak times, when electricity costs less. The

Members intended to then discharge electricity to meet customer demand during peak

times, reducing the amount they must purchase from APCO at higher rates. APCO sent a

response to Blue Ridge indicating it did not believe the agreements permitted the

implementation of BST as contemplated by the Members.

Blue Ridge filed a petition seeking a declaratory judgment with the Commission

shortly thereafter. See 18 C.F.R. § 385.207(a)(2) (permitting party to file petition for

declaratory order); see also 5 U.S.C. § 554(e) (permitting FERC to issue “declaratory order

to terminate a controversy or remove uncertainty”). Blue Ridge asked the Commission to

declare that the agreements were not a barrier to installing BST and using it to manage

electricity demand. APCO filed a response arguing the agreements foreclosed BST

installation and its use in the manner the Members intended, and it asked the Commission

to issue a judgment declaring accordingly.

On October 21, 2022, FERC issued an order finding the Members’ agreements with

APCO permitted installation of BST. Specifically, the Commission concluded that “[t]he

use of battery storage does not affect the parties’ obligations under the Agreements”

4 USCA4 Appeal: 23-1192 Doc: 67 Filed: 03/04/2025 Pg: 5 of 15

because the Members would have all their electricity needs met by APCO—including the

power to energize the batteries—and the agreements contemplated that the quantity of

electricity the Members purchased would vary from day to day. Blue Ridge Power Agency,

181 FERC ¶ 61,048 at PP 29–36 (2022). Further, the Commission noted that the

agreements prohibited the installation of “generation resources,” but reasoned that “battery

storage cannot be defined as a generation resource” under the agreements “because a

battery can only store Energy for later use, but cannot produce energy.” Id. P 29 (citing N.

Carolina E. Mun. Power Agency (NCEMPA), 172 FERC ¶ 61,249 at P 37 (2020)

(concluding battery storage is not “inherently a form of generation” when charged with

electricity from wholesale seller)). The Commission also found that installation and use of

battery storage would not violate prohibitions on “newly constructed or purchased

generation resources” or entering “new power purchase agreements.” Id. P 36.

The Commission reached a different conclusion with respect to APCO’s contract

with Virginia Tech. It pointed to that agreement’s limitation on construction of “New

Generation” and the fact that the agreement expressly listed “battery storage” as a form of

New Generation. Id. PP 37–38. Further, the Virginia Tech agreement precluded the use

of BST for the purpose of demand reduction, and Blue Ridge intended to use it for that

purpose. The Commission disagreed with Blue Ridge’s arguments that the Virginia Tech

agreements permitted installation of greater BST capacity than its express terms.

Therefore, it concluded that Virginia Tech lacked “broad and uncapped” authority to install

BST, and any installation of that technology would be subject to the capacity limitations

and educational-purpose requirements contained in the contract. Id. P 44.

5 USCA4 Appeal: 23-1192 Doc: 67 Filed: 03/04/2025 Pg: 6 of 15

APCO timely appeals. It primarily focuses its arguments on the Commission’s

interpretation of the agreements with the Members. It argues that the agency decision

should be vacated because the Commission failed to cite to Virginia law, would have

reached a different result if it had, and substituted a policy judgment for a legal one.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barnhart v. Peabody Coal Co.
537 U.S. 149 (Supreme Court, 2003)
Blake Construction Co. v. Upper Occoquan Sewage Authority
587 S.E.2d 711 (Supreme Court of Virginia, 2003)
Smith Mountain Lake Yacht Club, Inc. v. Ramaker
542 S.E.2d 392 (Supreme Court of Virginia, 2001)
Government Employees Insurance v. Hall
533 S.E.2d 615 (Supreme Court of Virginia, 2000)
Berry v. Klinger
300 S.E.2d 792 (Supreme Court of Virginia, 1983)
Joseph Altiro Turner v. Commonwealth of Virginia
758 S.E.2d 81 (Court of Appeals of Virginia, 2014)
Appalachian Voices v. State Water Control Board
912 F.3d 746 (Fourth Circuit, 2019)
Defenders of Wildlife v. U.S. Dept. of the Interior
931 F.3d 339 (Fourth Circuit, 2019)
Louisville G&E Co. v. FERC
988 F.3d 841 (Sixth Circuit, 2021)
Mountain Valley Pipeline, LLC v. Sierra Club
990 F.3d 818 (Fourth Circuit, 2021)
Sierra Club v. State Water Control Board
64 F.4th 187 (Fourth Circuit, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
Appalachian Power Company v. FERC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/appalachian-power-company-v-ferc-ca4-2025.