Apache Deepwater, LLC v. McDaniel Partners, Ltd.

485 S.W.3d 900, 59 Tex. Sup. Ct. J. 411, 2016 Tex. LEXIS 179, 2016 WL 766731
CourtTexas Supreme Court
DecidedOctober 14, 2015
DocketNO. 14-0546
StatusPublished
Cited by33 cases

This text of 485 S.W.3d 900 (Apache Deepwater, LLC v. McDaniel Partners, Ltd.) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Apache Deepwater, LLC v. McDaniel Partners, Ltd., 485 S.W.3d 900, 59 Tex. Sup. Ct. J. 411, 2016 Tex. LEXIS 179, 2016 WL 766731 (Tex. 2015).

Opinion

JUSTICE DEVINE,

delivered the opinion of the Court.

At issue in this case is how,to calculate a production payment reserved in the assignment of four oil and gas leaseholds. The four leases were assigned in one instrument. After two of the leases terminated, a dispute arosé over the production payment’s calculation. The payor asserted the production payment should be reduced to reflect the loss of the underlying mineral-lease interests. The payee disagreed, asserting the production payment burdened the four leases jointly and the assignment included no language authorizing an adjustment to the payment.

The trial court concluded the production payment ..could be adjusted to account for the termination of an underlying lease because the payment was carved respectively from the four leases. The court of appeals disagreed. 441 S.W.3d 530, 531 (Tex. App.—El Paso 2014). It concluded (1) the assignment fixed, the production payment at a stated percentage of the cumulative working interest assigned under the four leases, (2) the assignment provided no mechanism for reducing that payment if one or more of the underlying leases expired, and (3) the fixed payment endured so long as production continued under at least one of the . assigned leases. Id. at 536-37. Because we agree with the trial court’s, construction of the assignment as allowing for -the production payment’s adjustment ■ based on the expiration of an underlying'lease, we revérs'e and render.

I

The assignment at issue dates back to 1953. In it, Hugh W-. Ferguson, Jr., as[902]*902signed to L.H. Tyson four oil and gas leases Ferguson owned in Upton County, Texas. The four leases included the Pe-terman, the Broudy, and two Cowden Leases. Cowden Lease 36 was entirely within Survey 36; Cowden Lease 37 was entirely within Survey 37. The Peterman and Broudy Leases covered both Surveys 36 and 37. The Peterman and Broudy also included additional acreage outside these two surveys, but the Peterman and Broudy Leases were assigned to Tyson only insofar as they covered Surveys 36 and 37.

At the time of the assignment, the four leases represented a 35/64 mineral interest in the two surveys, derived from the respective leases as follows:

Cowden Lease, Survey 36: 1/2 of Survey 36
Cowden Lease, Survey 37: 1/2 of Survey 37
Peterman Lease: 1/64 of Surveys 36 and 37
Broudy Lease: 2/64 of Surveys 36 and 37

The two Cowden Leases thus comprised 32/64 of the working interest in Surveys 36 and 37, the Peterman and Broudy Leases adding another 3/64. The leases also reserved a 1/8 royalty to the lessors, leaving the operator a 7/8 working interest in the two surveys.

The assignment reserved to Ferguson a 1/16 production payment, which it described with the following equation: “l/16th of 35/64ths of 7/8ths” of the total production from Surveys 36 and 37.1 This descriptive equation included the fractional interest in production reserved from the conveyance (1/16); the fraction of the mineral estate within Surveys 36 and 37 conveyed in 1953 under the four leases (35/64); and the fraction representing the leasehold estate after subtracting the lessors’ 1/8 royalty interest (7/8). The assignment provided further that the production payment would continue until net proceeds from the reserved interest amounted to $3.55 million and 1.42 million barrels of oil.

About' twenty years after Ferguson assigned the four leases, both Cowden Leases expired for lack of production. Production on acreage outside of Surveys 36 and 37, however, perpetuated the Peterman and Broudy Leases. These two leases were still held by production in 2009 when Apache, as Tyson’s successor-in-interest, acquired its interest under the Ferguson assignment. Because production under the Cowden Leases had ceased long before, the 3/64 mineral interest attributable to the Peterman and Broudy Leases were [903]*903the only interests that Apache ■ acquired subject to the assignment. Apache, however, acquired additional leases in Surveys 36 and 37 that were not subject to the assignment, completed additional wells, and began production in the two surveys.

After obtaining production, Apache sent a division order to Ferguson’s successor-in-interest, McDaniel Partners, Ltd., stating that the production payment reserved in the 1953 assignment should now be 1/16 of 3/64 of 7/8, reflecting the expiration of the Cowden Leases. McDaniel disagreed and instead requested a new division order reflecting a production payment calculated under the assignment’s original equation. When Apache paid McDaniel for the 3/64 interest instead of the assignment’s original 35/64 interest, McDaniel sued.

After a bench trial, the trial court rendered a take-nothing judgment against McDaniel, issuing findings of fact and conclusions of law at McDaniel’s request. The court held that the production payment was reserved from the four leases separately and “was thus subject to extin-guishment upon expiration of each lease to the extent it existed as a burden against the production attributable to that lease.” The court concluded further that Apache’s division order, which provided for a production payment of 1/16 of 3/64 of 7/8, correctly reflected the production payment that remained after the 32/64 interest attributable to ■ the former Cowden Leases was extinguished. McDaniel appealed, and the court of appeals reversed the trial court’s judgment.

The appellate court held the assignment did not. authorize Apache to adjust the production-payment equation to reflect the effect of an expired lease on the assigned interests. 441 S.W.3d at 536-37. The court.reasoned that, even though the production payment was reserved out of the working interest conveyed and lease terminations effectively reduced that working interest, no adjustment could be made to the ■ production payment’s stated equation because the assignment did not contemplate such an adjustment. See Id. at 536 (finding in the assignment “no express language‘providing for a piecemeal reduction of the production payment”). Having concluded that McDaniel was entitled to 1/16 of 35/64 of 7/8 of production and had thus been underpaid, the court remanded the case to the trial court to calcúlate McDaniel’s damages and attorney’s fees. Id. at 538. Apache appealed to this Court, where the dispute over the assignment’s meaning remains the central issue.

II .

The focus of that dispute concerns the percentage that should- be used to calculate the production payment. McDaniel contends the correct percentage is approximately 3% of production' from the two surveys. McDaniel derives this figure from the equation the assignment uses to describe the production payment, that being'“l/16th of 35/64th of 7/8th [of the total oil and gas] which may be produced from the above described land, i.e., from each and both of said Surveys 36 and 37.” Because this equation states the production payment as a percentage of the cumulative working interests conveyed (35/64) and is used throughout the agreement, McDaniel views it as indicative of the parties’ intent to burden the individual leases jointly with a production payment básed upon the original, cumulative working interest conveyed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

OIL VALLEY PETROLEUM v. MOORE
2023 OK 90 (Supreme Court of Oklahoma, 2023)
Miner, Ltd. v. Anguiano
383 F. Supp. 3d 682 (W.D. Texas, 2019)
Eric Jonjak v. Kathye Marlene Griffith
Court of Appeals of Texas, 2019
Cimarex Energy Co. v. Anadarko Petroleum Corporation
574 S.W.3d 73 (Court of Appeals of Texas, 2019)
in the Interest of M.W.M., Jr., a Minor Child
Court of Appeals of Texas, 2018

Cite This Page — Counsel Stack

Bluebook (online)
485 S.W.3d 900, 59 Tex. Sup. Ct. J. 411, 2016 Tex. LEXIS 179, 2016 WL 766731, Counsel Stack Legal Research, https://law.counselstack.com/opinion/apache-deepwater-llc-v-mcdaniel-partners-ltd-tex-2015.