American Family Insurance Company a/s/o Nicholas Oelke v. NB Electric, Inc. dba East Side Garage Doors, ...

Supreme Court of Minnesota·Decided July 22, 2026·No. A240377·Published

Opinion

STATE OF MINNESOTA

IN SUPREME COURT

A24-0377

Court of Appeals Hudson, C.J.

American Family Insurance Company a/s/o Nicholas Oelke,

Respondent,

vs. Filed: July 22, 2026 Office of Appellate Courts NB Electric, Inc. dba East Side Garage Doors,

Appellant,

Morningstar Remodeling, LLC, Respondent.

Jessica C. Richardson, Kelly Sofio, Tomsche, Sonnesyn & Tomsche, P.A., Minneapolis, Minnesota, for respondent American Family Insurance Company.

Colby B. Lund, Jeffrey M. Markowitz, Rakiah B. Adams, Arthur, Chapman, Kettering, Smetak & Pikala, P.A., Minneapolis, Minnesota, for appellant NB Electric, Inc. dba East Side Garage Doors.

Taylor Brandt Cunningham, Bolt Law Firm, Anoka, Minnesota, for amicus curiae Minnesota Association for Justice.

SYLLABUS

For purposes of triggering the two-year statute of limitations for defective construction claims involving an improvement to real property in Minn. Stat. § 541.051, subd. 1, a property owner’s termination of the construction contract with the general contractor constitutes “termination … of the construction or the improvement to real property.”

Reversed.

OPINION

HUDSON, Chief Justice.

This case is about whether an action brought by American Family Insurance Company against NB Electric, Inc. and Morningstar Remodeling, LLC, is time-barred by the statute of limitations in Minn. Stat. § 541.051, subd. 1, which applies to defective construction claims involving an improvement to real property. The action arose from a home remodeling project for which Morningstar was the general contractor and NB Electric was a subcontractor whose electrical work allegedly caused a fire.1 The district court dismissed American Family’s complaint based on the two-year statute of limitations in Minn. Stat. § 541.051, subd. 1, which specifies that a cause of action does not accrue “earlier than substantial completion, termination, or abandonment of the construction or the improvement to real property.” (Emphasis added.) The district

1 Morningstar participated in the appeal at the court of appeals but did not seek further review and did not file a brief in this court.

court concluded that American Family’s claims were time-barred at the time the action commenced in July 2023 because the cause of action accrued no later than April 2021 when the homeowner terminated the construction contract with the general contractor. A divided panel of the court of appeals issued a decision reversing the district court’s dismissal of the complaint. The court of appeals held that the phrase “substantial completion, termination, or abandonment of the construction or the improvement to real property” in Minn. Stat. § 541.051, subd. 1(c), refers to termination of the project as a whole, not termination of the construction contract with the general contractor. Thus, the court of appeals concluded that American Family’s action was not time-barred because the home remodeling project had not been substantially completed, terminated, or abandoned when the homeowner terminated the services of the general contractor.

We hold—consistent with the district court—that for purposes of the two-year statute of limitations in Minn. Stat. § 541.051, subd. 1, terminating the contract with the general contractor for the construction or the improvement to real property constitutes “termination … of the construction or the improvement to real property.” Accordingly, we reverse the court of appeals.

FACTS

In February 2020, Nicholas Oelke (“the insured”) hired Morningstar to serve as the general contractor for a home remodeling project. According to the general contract, the scope of construction included electrical improvements: “The electrical portion of this project includes the house side of the new service and wiring for all appliances and

lighting.” Morningstar subcontracted with appellant NB Electric to perform electrical work on the project.

On February 25, 2020, the City of Little Canada (“the city”) issued a building permit to Morningstar. The building permit application described the work to be done as “Interior remodel. Roof alteration.”

On July 29, 2020, during construction, a fire broke out at the insured’s home and caused extensive property damage. According to the complaint, the fire occurred in part because NB Electric and Morningstar (collectively “the contractors”) “utilized nonmetallic cabling … as opposed to the metallic cabling required by the plan specifications” and “failed to install no arc-fault circuit interrupters as required by the plan specifications.” As a result of the fire, the insured submitted an insurance claim to respondent American Family Insurance Company. American Family was required to and did pay for damages resulting from the fire.

About a month after the fire, the insured discontinued the services of NB Electric.

NB Electric performed no work on the home after the fire. Soon after March 8, 2021, the insured also discontinued the services of Morningstar. Neither Morningstar personnel nor its subcontractors performed any work on the insured’s home after April 2021. Although the city had completed initial inspections on work performed by Morningstar and its subcontractors, no final inspections occurred because of the fire.

By February 2021, the insured had engaged Solid Rock Construction (“Solid Rock”) as the new general contractor. Solid Rock’s building permit application described the work to be done as “[d]emolition of fire damage, repair after demo, replace trusses

and roofing, finish walls, miscellaneous finishes throughout.” Between May 5 and May 20, 2021, the city completed initial inspections on work done by Solid Rock and its subcontractors. On July 29, 2021, the city completed its final inspections and approved the work.

On July 31, 2023, American Family, as the insured’s subrogee, commenced a subrogation action2 against the contractors, asserting claims for negligence and breach of contract relating to the fire. See Minn. R. Civ. P. 3.01(c). NB Electric and Morningstar both filed motions to dismiss American Family’s complaint pursuant to Rules 12.02(e) and 56 of the Minnesota Rules of Civil Procedure, based on the two-year statute of limitations for defective construction claims in Minn. Stat. § 541.051, subd. 1.

The district court granted the contractors’ motions for summary judgment and dismissed American Family’s complaint with prejudice.3 The district court determined that American Family’s claims were time-barred under Minn. Stat. § 541.051, subd. 1, because the claims accrued no later than April 2021—when the insured terminated Morningstar as the general contractor. American Family appealed.

2 “In the insurance context, [s]ubrogation involves the substitution of an insurer (subrogee) to the rights of the insured (subrogor). The insurer stands in the shoes of the insured and acquires all of the rights the insured may have against a third party.” Getz v. Peace, 934 N.W.2d 347, 351 n.2 (Minn. 2019) (alteration in original) (citations omitted) (internal quotation marks omitted). 3 “If on a motion asserting the defense that the pleading fails to state a claim upon which relief can be granted, matters outside the pleading are presented to and not excluded by the court, the motion shall be treated as one for summary judgment and disposed of as provided in Rule 56.” Minn. R. Civ. P. 12.02. Here, matters outside the pleading were presented and not excluded by the district court.

The court of appeals reversed the grant of summary judgment in a 2–1 decision.

Free access — add to your briefcase to read the full text and ask questions with AI

American Family Insurance Company a/s/o Nicholas Oelke v. NB Electric, Inc. dba East Side Garage Doors, ..., (Mich. 2026).

American Family Insurance Company a/s/o Nicholas Oelke v. NB Electric, Inc. dba East Side Garage Doors, ... (American Family Insurance Company a/s/o Nicholas Oelke v. NB Electric, Inc. dba East Side Garage Doors, ...) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lietz v. Northern States Power Co.
718 N.W.2d 865 (Supreme Court of Minnesota, 2006)
Weston v. McWilliams & Associates, Inc.
716 N.W.2d 634 (Supreme Court of Minnesota, 2006)
Blaine Economic Development Authority v. Royal Electric Co.
520 N.W.2d 473 (Court of Appeals of Minnesota, 1994)
Roberts v. Baumgartner
391 N.W.2d 545 (Court of Appeals of Minnesota, 1986)
Premier Bank v. BECKER DEVELOPMENT, LLC
785 N.W.2d 753 (Supreme Court of Minnesota, 2010)
Cody Devereaux Sleiter v. American Family Mutual Insurance Company
868 N.W.2d 21 (Supreme Court of Minnesota, 2015)
Fletcher v. Scott
277 N.W. 270 (Supreme Court of Minnesota, 1938)
328 Barry Avenue, LLC v. Nolan Properties Group, LLC
871 N.W.2d 745 (Supreme Court of Minnesota, 2015)
State v. Thonesavanh
904 N.W.2d 432 (Supreme Court of Minnesota, 2017)