328 Barry Avenue, LLC v. Nolan Properties Group, LLC

871 N.W.2d 745, 2015 Minn. LEXIS 693, 2015 WL 7566613
CourtSupreme Court of Minnesota
DecidedNovember 25, 2015
DocketNo. A14-0724
StatusPublished
Cited by15 cases

This text of 871 N.W.2d 745 (328 Barry Avenue, LLC v. Nolan Properties Group, LLC) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
328 Barry Avenue, LLC v. Nolan Properties Group, LLC, 871 N.W.2d 745, 2015 Minn. LEXIS 693, 2015 WL 7566613 (Mich. 2015).

Opinion

OPINION

GILDEA, Chief Justice.

The questions presented in this case concern the interpretation and application of the 2-year statute of limitations in Minn-Stat. § 541.051, subd. 1(a) (2014), which applies to actions “arising out of the defective and unsafe condition of an improvement to real property.” Appellant 328 Barry Avenue, LLC (328 LLC) used respondent Nolan Properties Group, LLC' (NPG) as the general contractor for the construction of a building. The building had problems with water intrusion. 328 LLC brought an action claiming that NPG’s actions as general contractor were negligent. The district court dismissed the action as untimely under Minn.Stat. § 541.051, subd. 1(a). The court of appeals affirmed. Although we agree with the court of appeals that the plain lan[747]*747guage of Minn.Stat. § 541.051, subd. 1 does not require that construction be substantially complete to start the running of the statute of limitations, we reverse in part and remand because we conclude that there is a genuine issue of material fact as to when 328 LLC discovered its injury.

In 2008, construction began on a three-story commercial building located in Way-zata, Minnesota. The building site belonged to 328 Barry Avenue, LLC, a company solely owned by John Nolan. 328 LLC selected NPG, another company solely owned-by Nolan, to serve as the general contractor during construction of the building.1 According to 328 LLC, NPG’s duties as general contractor included hiring and supervising subcontractors and selecting construction materials. NPG did not personally perform any of the construction work, but claims that it was qualified to select, hire, and supervise subcontractors and ensure that the subcontractors’ work was completed according to the contract documents. NPG did not have a written contract with 328 LLC, but NPG did enter into written contracts with the subcontractors on the project, including respondents Carciofini Company, Marvin Windows,- Inc., Minuti-Ogle Co., Inc., and R.T.L Construction, Inc. .

In October 2009, during what Nolan referred to as the “punch list” phase of construction, NPG contacted Minuti-Ogle Co. (MOC),: the stucco contractor. NPG asked MOC about a leak around an1 east elevation window, indicating that there was “some water” on the property. A representative from MOC visited the property and, after observing “soaking wet” insulation and water “coming out by the window,” told NPG, “I think you’ve got a window issue.” A few days later, ■ NPG again contacted MOC regarding leakage at the same location. At NPG’s request, the same MOC representative returned to the property and applied small amounts of silicone sealant to the window corners, although he warned NPG that he feared that absence of sealant was not the issue.

On October 30, 2 weeks after his previous visit, the MOC representative received an email from NPG asking him to return to the property because water was again entering around the same window. In early November 2009, the MOC representative and two representatives of NPG "performed a garden-hose “spray test” to determine the location of the leak. The test revealed water “slowly seepfing] in on the right side of the [same] window.” Although MOC testified that it performed no work during this visit to repair or correct the issue, and NPG produced no specific evidence that NPG or any subcontractor attempted to repair the leak, the record does not reflect that there were any water leaks around the window or in other parts of the building between November 2009 and August 2010. Nolan, testifying on behalf of NPG, stated that “whatever [the subcontractors] did, they addressed [the leak] to [NPG’s] satisfaction because I didn’t hear anything, I didn’t see anything ... and we paid everybody. That issue was solved and done.” Nolan testified that 328 LLC observed no leaks or water intrusion damage from November 2009 until August 2010.

The City of Wayzata issued a certificate of occupancy for the building in January 2010, although parts of the building were still unfinished. The parties agree, however, that construction was substantially complete by May 2010 when 328 LLC [748]*748began to occupy the building for commercial purposes.

In August -2010, 328 LLC noticed water on the floor of the building. NPG again contacted the MOC representative who had observed the window leak in 2009, stating that “[t]his problem with water leaking around the windows needs to be solved.” Upon arrival at the property, the MOC representative noticed “water in the same spot” as the previous fall, and, as he said he did earlier, suggested that NPG “get [the] window tested.”

Throughout 2011 and 2012, NPG and 328 LLC hired a number of experts to investigate the extent and cause of the water damage to the building. A report released in June 2011 documented window leaks at multiple east and west elevation locations, the presence of “unspecified” building materials, and installation of materials contrary to project specifications. Invasive cuts into the stucco wall-covering revealed saturated sheathing and tar paper, as well as wet wood framing around the windows. An additional company hired by NPG to inspect the property in May and June of 2012 found heightened moisture levels in test sites around windows, stucco breaking away from beams, gaps around deck supports, and unsealed window joints.

Based on these reports, 328 LLC brought suit against NPG on June 14, 2012, alleging failure to exercise reasonable care in performing its duties as general contractor, including the negligent supervision of subcontractors and the negligent selection of building materials. NPG filed a third-party complaint against the respondent subcontractors for contribution and indemnity.

NPG and the subcontractors moved for summary judgment. The district court granted summary judgment, concluding that the negligence action was untimely under the 2-year statute of limitations for improvements to real property in Minn. Stat. § 541.051, subd. 1(a). As a threshold matter, the court rejected 328 LLC’s argument that a claim based on property damage cannot accrue prior to substantial completion of the construction. The court also concluded that there was “no genuine issue of material fact regarding 328 LLC’s discovery of the defect.” The court determined that 328 LLC discovered an actionable injury in the fall of 2009, because the water intrusion in August 2010 was “the same injury” as the water intrusion in the fall of 2009. The court also found that 328 LLC did not produce any evidence suggesting that it was reasonable to believe that the fall-2009 leak had been remedied or repaired. Therefore, because 328 LLC did not commence the negligence action until June 2012, the court ruled that 328 LLC’s action was untimely.

The court of appeals affirmed. 328 Barry Ave., LLC v. Nolan Prop. Grp., LLC, No. A14-0724, 2015 WL 404630 (Minn.App. Feb. 2, 2015). The court of appeals determined that “[t]he district court properly concluded that construction need not be completed before the start of the two-year limitation period.” Id. at *5. The court of appeals also held that “[t]he district court did not err in determining that there were no genuine issues of material fact regarding 328 [LLC] ’s knowledge of its injury in October 2009 and that the statute of limitations began to run at that time.” Id. at *4. We granted 328 LLC’s petition for review.

On appeal, 328 LLC contends that a claim' cannot accrue under Minn.Stat. § 541.051, subd. 1(a), prior to substantial completion of the construction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brenda Thormodson v. Kathryn Rae Zehnder
Court of Appeals of Minnesota, 2025
Maethner v. Someplace Safe, Inc.
929 N.W.2d 868 (Supreme Court of Minnesota, 2019)
Vill. Lofts At St. Anthony Falls Ass'n v. Hous. Partners Iii-Lofts LLC
924 N.W.2d 619 (Court of Appeals of Minnesota, 2019)
Otto v. Wright Cnty.
910 N.W.2d 446 (Supreme Court of Minnesota, 2018)
Montemayor v. Sebright Products, Inc.
898 N.W.2d 623 (Supreme Court of Minnesota, 2017)
City of Rochester v. Kottschade
896 N.W.2d 541 (Supreme Court of Minnesota, 2017)
State v. Boecker
893 N.W.2d 348 (Supreme Court of Minnesota, 2017)
Eugene Lee Rushton v. State of Minnesota
889 N.W.2d 561 (Supreme Court of Minnesota, 2017)
David B. Markle v. Metro Metals Corporation
Court of Appeals of Minnesota, 2016
Jason Hoff v. Earl Surman
883 N.W.2d 631 (Court of Appeals of Minnesota, 2016)
Lora Walker v. Hartford Life and Accident Ins
831 F.3d 968 (Eighth Circuit, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
871 N.W.2d 745, 2015 Minn. LEXIS 693, 2015 WL 7566613, Counsel Stack Legal Research, https://law.counselstack.com/opinion/328-barry-avenue-llc-v-nolan-properties-group-llc-minn-2015.