Allied Erecting & Dismantling, Co. v. USX Corp.

249 F.3d 191, 2001 U.S. App. LEXIS 7406
CourtCourt of Appeals for the Third Circuit
DecidedApril 23, 2001
Docket00-3064, 00-3105
StatusUnknown
Cited by3 cases

This text of 249 F.3d 191 (Allied Erecting & Dismantling, Co. v. USX Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allied Erecting & Dismantling, Co. v. USX Corp., 249 F.3d 191, 2001 U.S. App. LEXIS 7406 (3d Cir. 2001).

Opinion

OPINION OF THE COURT

NYGAARD, Circuit Judge.

Previous litigation between appellant, Allied Erecting and Dismantling, Co., Inc., and appellee, USX Corporation, was settled on the eve of trial. In this suit, Allied claims that USX violated several provisions of that settlement agreement. The District Court granted summary judgment in favor of USX, and Allied appeals. Many facts are contested, but we have isolated those that are germane to the three issues reaching us on appeal. As folly explained below, we will reverse the District Court’s judgment in two respects, affirm the balance, and remand the cause to the District Court.

I. BACKGROUND

On the eve of trial for the first action brought by Allied against USX Corporation, the two entities entered into a court-supervised Settlement Agreement. Allied claimed that it suffered sixty-six million dollars in damages as a result of contracts it entered into with USX to dismantle several of USX’s steelmaking facilities. The Settlement Agreement, which is at the heart of this controversy, provided: 1) USX would pay Allied eight million dollars; 2) Allied would be granted all dismantling projects at USX’s Fairless Works plant; 3) Allied could bid in good faith as a primary bidder on USX’s subsequent dismantling projects; 4) Allied would be granted “last look” rights for a period of seven years to equal or better the most acceptable bid received by USX for any dismantling projects; 5) Allied would be awarded dismantling contracts at USX’s Ambridge Works, Saxonburg Works, and McDonald Works.

*194 1. Allied’s Section V Claim

Allied’s first two claims arise from Section V of the Settlement Agreement, which reads:

Except as to any dismantling work at USX’s South Works facility in Chicago, Illinois, Allied shall be invited to bid in good faith as one of U.S. Steel Groups’ primary bidders on any dismantling work, of whatever nature or type at any steelmaking facilities, or former steel-making facilities, owned by the U.S. Steel Group consistent with and pursuant to specification and performance standards developed and issued by U.S. Steel Group for such work and, for a period of seven (7) years from the date of this Settlement Agreement and General Release, Allied shall be offered an opportunity to equal and/or to better the most acceptable bid received by the U.S. Steel Group for any such further dismantling activity. If, within ten (10) days of receipt of bids, Allied offers in writing to per form such work on such terms which are equal to or better than the bid otherwise most acceptable to the U.S. Steel Group, then, in such event, the work shall be awarded to Allied, provided, however, that Allied is then able to meet U.S. Steel Group performance standards then in effect and, further, that Allied has not been adjudicated to be in .default under any dismantling contract with U.S. Steel Group then in effect at the time of such bidding.

Under this “last look” provision, USX issued Allied and other dismantlers specifications for projects up for bid. The third parties then bid on the projects subject to the condition that “Purchaser [USX] reserves the right to reject any or all bids.” No third party was told that Allied held the right to review and match their final bids. For the first few sessions, Allied formulated and submitted earnest bids on the projects. Formulating a bid for projects such as these can be cost and labor intensive, and Allied later determined that instead of participating in the bidding process it would merely review the best bid offered to USX and decide if it wanted to take the job at that price.

Allied claims that USX violated the terms of Section V through its relationship with Allied’s arch-rival, Brandenburg Industrial Services Company, Inc. Because the litigation soured Allied and USX’s working relationship, USX awarded most of its dismantling projects thereafter to Brandenburg. As a result of this close working relationship, Brandenburg prepared most of the specifications for the projects on which Allied held the “last look” right. Because Brandenburg prepared these specifications, Allied argued, it held an “unquestioned and substantial advantage over the other bidders for this work.” Within one bid, Brandenburg offered to forgive $379,500 that USX owed for developing the project specifications if USX granted the project to Brandenburg. Allied was unable to compete with an offer that included debt forgiveness, and therefore claims that such dealings between USX and Brandenburg materially varied the terms of the project specifications and violated Allied’s last look rights.

2. Allied’s Fraudulent Inducement Claim

Allied next claims that it was fraudulently induced into accepting Section V of the Settlement Agreement. Allied claims that USX stated during the settlement bar gaining process that USX would be preparing the specifications for the projects on which Allied would bid pursuant to Section V. This statement led Allied to believe that its last look rights would not be undercut by a competitor who prepared the specifications and could therefore offer *195 a discount by including the price of the preparations in the bid. At the time USX allegedly made these statements to Allied, USX had already retained Brandenburg to prepare specifications for two of the projects on which Allied intended to bid.

Brandenburg subsequently used this leverage to outbid Allied on one of the projects.

3. Allied’s Saxonburg Claim

Allied expected to quickly raze the Sax-onburg Works plant, liquidate its materials for a substantial profit, and thereby recoup some of its losses associated with the litigation. Section IV of the Settlement Agreement reads, in part:

1) That all dismantling by Allied shall be per formed at no cost to USX;
2) That the dismantling specification will not include the provision for ... any environmental remediation (including any remediation and/or removal of asbestos) by Allied, it being understood and agreed that any ... environmental remediation shall be for USX’s account;
3) All ferrous and non-ferrous scrap produced at the dismantling projects shall belong to Allied.

The project, however, became complicated by a steel manufacturing byproduct known as “sinter dust.” According to Allied,

work in and around the dust was far more difficult than anticipated because ... [the sinter dust] impacted the way facilities were dropped, the dust had to be cleaned from the scrap generated during the dismantling before the scrap could be dismantled and processed, and, when the dust was dry it became airborne and impacted visibility, [and] while it was wet, it congealed into a soupy mush that significantly slowed the work.

In addition to the general difficulties Allied experienced in dismantling a plant full of beams, girders, and equipment caked with the dust, Allied discovered that some of the dust contained lead and therefore posed health risks to its employees working amidst more than 16,000 tons of the material. Allied notified USX of the hazard and reminded USX of the relevant terms governing the Saxonburg work:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
249 F.3d 191, 2001 U.S. App. LEXIS 7406, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allied-erecting-dismantling-co-v-usx-corp-ca3-2001.