Miller v. Central Trust & Savings Co.

132 A. 579, 285 Pa. 472, 1926 Pa. LEXIS 475
CourtSupreme Court of Pennsylvania
DecidedJanuary 4, 1926
DocketAppeal, 320
StatusPublished
Cited by34 cases

This text of 132 A. 579 (Miller v. Central Trust & Savings Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miller v. Central Trust & Savings Co., 132 A. 579, 285 Pa. 472, 1926 Pa. LEXIS 475 (Pa. 1926).

Opinion

Opinion by

Mr. Justice Kephart,

The proceeding in the court below was for an accounting. The chancellor found appellee had been fraudu *476 lently induced to enter a building operation whereby he was deprived of the sum of $117,000. From the decree entered for that sum this appeal has been taken.

The adjudication of the chancellor, made from a review of more than a thousand pages of testimony, was complete in every essential necessary to sustain the decree; it reflects the result of careful review and analysis. The findings of fact by a chancellor have the force and effect of a verdict of a jury and will not be disturbed on appeal if there is evidence to support them (Glenn v. Trees, 276 Pa. 165; Himrod v. McFayden, 283 Pa. 103), hence they are conclusive in this court except where the finding is based upon erroneous inferences or deductions from facts; in which case, being the result of reasoning, the appellate court will correct them: McConville v. Ingham, 268 Pa. 507; Woodward v. Carson, 208 Pa. 144; Com. v. T., I. & Tr. Co. v. Seltzer, 227 Pa 410, 416; Altaffer v. Anderson Auto. Co., 77 Pa. Superior Ct. 63, 65.

Appellant assails a number of the findings of the chancellor under this exception, and contends there is no evidence to support them. It becomes necessary to review the entire record and from the mass ascertain if there is sufficient to support the decree. There are forty-nine assignments of error to consider but we will limit our discussion to as narrow a space as possible. The following is the story presented by the record and as found by the court below:

Appellee, Miller, is a building contractor; appellant trust company, defendant below, engages in the business of issuing special insurance and otherwise financing building operations along with other business, piddle, another defendant, also a builder, is co-contractor with Miller. The third defendant is an employee of the trust company, a title holder of the real estate covered by the building operation. Biddle, who had a twenty-four house operation at 53d Street and Florence Avenue, conceived the plan of building sixty-eight houses at *477 Bemont and Litchfield Streets. He secured an option on the land, had plans and specifications prepared, and secured a number of contracts purporting to cover the entire operation. The total cost was to be $298,000; of this $234,000 must be procured in money. Biddle had arranged through loans for all but $52,000, but his project was about to fall through, when he met Miller at the trust company offices. This company was to be directly connected with the undertaking, as will later appear. Biddle explained his predicament to Miller, reviewing the facts above narrated, and further told Miller that he had sold his twenty-four house operation in the course of construction to the Mooney Co. at a figure which would net him a profit of $30,000, receiving a certified check of $5,000 on account. The contract and check were in the trust company’s hands. This was not sufficient to meet the cash balance necessary. If Miller helped out, the trust company agreed to accept the assignment of the Mooney contract to make up his share of the $52,000. While engaged in conversation, Evans, an officer of the trust company, called them into his office. Evans restated practically all Biddle had said, among other things saying that the trust company would accept the Biddle equity in the twenty-four house operation as Biddle’s share of the $52,000 shortage, and showed Miller the Mooney contract of sale with the $5,000 check attached. Biddle’s share in the new venture would be $26,000 to come out of the Mooney proceeds if Miller engaged in the contract. Evans also showed Miller a schedule prepared by him containing a list of what Evans said were good, reliable contractors, who had furnished bonds to complete the building operation. The cost of each contract was stated opposite the name of the contractor. Miller was assured by Evans the total cost would not exceed $4,400 per house, that all the work and material had been contracted for, and that the proposed undertaking was a very good one. An opportunity to investigate the entire matter, including *478 the contractors, the bonds and the operation in general, was requested, but Evans stated everything was all right and there was not sufficient time to make an investigation. The option on the land was about to expire, and unless expedited, the entire matter would be lost. Miller and Evans had known each other for a number of years. In view of their acquaintanceship, the positive assurance given, and relying on the representations, Miller shortly afterwards became a partner with Biddle in building the sixty-eight houses.

A finance agreement was-executed between the trust company, Biddle and Miller, and, because of it, the representations of Evans are of great consequence. This contract was well worded, calculated, in part, at least, to safeguard the trust company in financing the proposition, if its foundation was on solid ground. Because of the benefits to be received, it was imperative nothing should be said or done calculated to deceive any of the parties concerned. The written contract, after some preliminaries, required the trust company to insure against the noncompletion of the sixty-eight houses the following: (a) The mortgages through which the builders secured the first moneys, (b) The contractors furnishing labor and material, taking therefor the houses or the mortgages in payment. It also guaranteed payment to other persons who furnished work and material not paid in advance or otherwise protected. That the trust company might be protected in the assurance that the builders would complete their project, in addition to securing the partners’ bond in the sum of $286,000, it had the bond of a third person in the sum of $20,000. Miller and Biddle were required to do a great many things, all of which were directed to one end, — the successful completion of the project. All funds received from the sale of the mortgages or from the builders were to be deposited with the trust company, as well as the funds coming from the independent building operation of Biddle (being the twenty-four houses mentioned *479 above), and an independent operation of Miller (not heretofore spoken of), a seventy-house operation. The buildings were to be completed according to the plans and specifications, and all material from the several contractors was to be delivered to the trust company on the operation, to become its property, as an asset to the building operation, free from the interference of Biddle and Miller. While this was no doubt to protect the property from any claims, it emphasizes the extent of the trust company’s control in the interest of its guarantee to the policyholders. Free access was given to the buildings, and if the construction did not proceed in a satisfactory manner, the trust company could take charge of and complete it. All payments were to go through the trust company, approved by the builders, and if they refused, the trust company could sign the vouchers for them. Compensation was paid to the trust company in addition to the interest received, piddle and Miller then executed their agreement for the construction of the property, Biddle having sole charge of the job.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Allied Erecting & Dismantling, Co. v. USX Corp.
249 F.3d 191 (Third Circuit, 2001)
Babin v. City of Lancaster
493 A.2d 141 (Commonwealth Court of Pennsylvania, 1985)
Scaife Co. v. Rockwell-Standard Corp.
285 A.2d 451 (Supreme Court of Pennsylvania, 1971)
Linda Coal & Supply Co. v. Tasa Coal Co.
204 A.2d 451 (Supreme Court of Pennsylvania, 1964)
Wortex Mills, Inc. v. Textile Workers Union of America
109 A.2d 815 (Supreme Court of Pennsylvania, 1954)
Rekas v. Dopkavich
66 A.2d 230 (Supreme Court of Pennsylvania, 1949)
Suraci v. Ball
51 A.2d 404 (Superior Court of Pennsylvania, 1946)
Neuman v. Schweidel
50 Pa. D. & C. 311 (Philadelphia County Court of Common Pleas, 1944)
Union of Russian Societies of St. Michael & St. George, Inc. v. Koss
36 A.2d 433 (Supreme Court of Pennsylvania, 1944)
Lochinger v. Hanlon
33 A.2d 1 (Supreme Court of Pennsylvania, 1943)
Kimmey's Estate
191 A. 47 (Supreme Court of Pennsylvania, 1937)
Kimmey's Estate
27 Pa. D. & C. 608 (Philadelphia County Orphans' Court, 1936)
Hollowell's Estate
182 A. 779 (Superior Court of Pennsylvania, 1935)
Emery v. Third Nat. Bk. of Pittsburgh
171 A. 881 (Supreme Court of Pennsylvania, 1934)
Almar B. & L. Assn. v. Broad Street Trust Co.
169 A. 262 (Superior Court of Pennsylvania, 1933)
Hart, Schaffner & Marx v. Koch
164 A. 369 (Superior Court of Pennsylvania, 1932)
Emery v. Third Nat. Bank of Pbg.
162 A. 281 (Supreme Court of Pennsylvania, 1932)
Schwab v. Miller Et Ux.
153 A. 731 (Supreme Court of Pennsylvania, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
132 A. 579, 285 Pa. 472, 1926 Pa. LEXIS 475, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miller-v-central-trust-savings-co-pa-1926.