Alliance Wall Corp. v. Ampat Midwest Corp.

477 N.E.2d 1206, 17 Ohio App. 3d 59, 17 Ohio B. 114, 41 U.C.C. Rep. Serv. (West) 377, 1984 Ohio App. LEXIS 12432
CourtOhio Court of Appeals
DecidedMay 28, 1984
Docket47280
StatusPublished
Cited by15 cases

This text of 477 N.E.2d 1206 (Alliance Wall Corp. v. Ampat Midwest Corp.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alliance Wall Corp. v. Ampat Midwest Corp., 477 N.E.2d 1206, 17 Ohio App. 3d 59, 17 Ohio B. 114, 41 U.C.C. Rep. Serv. (West) 377, 1984 Ohio App. LEXIS 12432 (Ohio Ct. App. 1984).

Opinion

Jackson, P.J.

This is an appeal from a judgment of the Cleveland Municipal Court, following a nonjury trial, which awarded damages to ap-pellee, Alliance Wall Corporation, in the amount of $9,639.76, and denied the counterclaim of appellant, Ampat Midwest Corporation.

The parties entered into a contract whereby Alliance Wall Corp. (“seller”) agreed to sell, and Ampat Midwest Corp. (“buyer”) agreed to buy, over two hundred aluminum panels.

There was no formal written contract between the parties. The companies did exchange a series of form purchase orders and acknowledgments prior to performance.

Ampat (buyer) sent its first purchase order in March 1978, consisting merely of a list of sizes and numbers of panels which would be ordered. This form was acknowledged by Alliance Wall (seller) in August 1978. It was noted “hold for final sizes,” and the price was listed as $29,217.

On January 26, 1981, buyer sent a second purchase order listing a number of panels, again stating “final sizes to be provided after approval of Midwest Architectural Metal shop drawings and your color samples.” The purchase order also states “ship all materials within five (5) weeks of release for production.” Delivery instructions were to ship “your [Alliance] truck,” “FOB Okmulgee, Oklahoma.” The contract price is stated to be $38,847.

Seller acknowledged this purchase order by letter dated January 29, 1981. The letter states: “We are placing your order in our ‘to be scheduled’ file until we are in receipt of the final sizes and quantities.” It adds, “Please keep in mind that our tentative shipping schedule is approximately five to six weeks after the final information is received.” Price is not mentioned.

By way of letter dated September 1, 1981, buyer irrevocably committed itself to ordering the aluminum panels from Alliance. The letter alters both the requested delivery date and the price. It states, in relevant part:

“Shipment should occur as soon as possible and certainly within seven (7) weeks of the date of this release. Please note that the order originally required a five (5) week production period but we have expanded that based on information from Andy Pappalardo.
<f* * *
“The total square footage on the order has been reduced from 3,692 square feet to 3,284 square feet. We assume that the price of the order will be reduced proportionally. That would result in a reduction of eleven (11%) per *61 cent so that the amount of the order would be $34,574.00. Please comment.”

The response to this was an acknowledgment, dated September 22, 1981, giving the price as $36,712.01, and providing that the “tentative shipping date” was to be November 6, 1981. The .acknowledgment again noted that the goods were to be shipped F.O.B. Okmulgee, Oklahoma, which is the site of the seller’s plant.

On October 22,1981, seller received the following letter from buyer, dated October 14, 1981:

“Subject order was released September 1, 1981 based on your guaranteed delivery schedule of five weeks A.R.O.
“Since then, we have had two revised shipping dates, the latest being November 20, 1981. This is not acceptable! We must demand better service.
“Our customer, A.M. Higley Company, has informed us that they are being forced to put in temporary enclosures due to our failure to meet our (your) commitment and charge us accordingly.
“This letter is your notice that all back charges caused by your delivery failure will be passed on to you.
“I expect an immediate reply to this letter.”

Buyer received an immediate reply from seller. The following mailgram, dated October 22, was entered into evidence.

“We are in receipt of your letter dated 10-14-81. The fact that you are threatening the Alliance Wall Corp. with backcharges which we will not accept under any condition has put us in the unenviable position of requiring a written revocation of those threats and acknowledgment of our standard terms and conditions of sale or we will cancel our order for the required aluminum [sic] and allow you to purchase the required material from another supplier. Please note that on 10-5-81 our L. Brick-ell advised your J. Mason of the tentative shipping schedule of 11-20-81.

“We very frankly are exerting all possible pressure on our supplier to speed up their delivery of the aluminium [sic] and our plant personnel has been alerted to the urgency of your order. However, we cannot and will not work under threat of backcharges for which we do not have total control.

“We await your reply, please respond by telephone no later than 10-23-81 and follow up with the necessary written correspondence.”

The goods were shipped November 20, 1981, and were received November 23, 1981. Twenty-six days later, on December 18, 1981, buyer sent seller a letter notifying seller of defects in one packet of the goods, and referring to the fact that oral notice of the defects had been given the previous day. The letter states, in part:

“This note is confirmation of our telephone conversation of December 17, 1981 in which we advised you of a potential ‘out of flatness’ problem.”

Ultimately forty-five panels were found to be defective. Some were corrected by buyer, some by seller. Buyer paid agreed damages of $3,000 to its general contractor for its delay in installing the aluminum panels. Buyer also incurred several thousand dollars of expenses in repairing the panels, and in renting equipment to install them over a period of several months. Buyer apparently did not pay to seller the full contract price. The exact amount paid by the buyer was not entered into evidence below, nor does either party contend that the trial court erred in determining the contract price of the goods. Accordingly, the issue of the exact amount of damages owed to the seller is not before this court of appeals. Appellant buyer assigns only two errors for review. 1

*62 I

Appellant contends for its first assigned error that the court erred in finding that the “delivery period” was modified from October 14, 1981 to November 20, 1981.

At issue, of course, was not the date of delivery, but the date of shipment. The goods were to be shipped F.O.B. seller’s plant. This was a shipment contract. R.C. 1302.32(A). 2 The seller was required only to place the goods in the possession of a carrier, make a reasonable contract for shipment, tender documents of title, and notify the buyer of the shipment. R.C. 1302.48. 3

The parties did not agree in their correspondence to a shipment date, nor is there persuasive evidence that the parties orally agreed upon a definite shipment date. Seller’s vice-president at trial admitted that seller was aware of buyer’s urgent need for prompt shipment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sanford v. 202 Racing, Inc.
2011 Ohio 3987 (Ohio Court of Appeals, 2011)
State v. Pillow, 07ca095 (11-21-2008)
2008 Ohio 6046 (Ohio Court of Appeals, 2008)
Tubelite Co. v. Original Sign Studio, Inc.
891 N.E.2d 820 (Ohio Court of Appeals, 2008)
E.C. Styberg Engineering Co. v. Eaton Corp.
492 F.3d 912 (Seventh Circuit, 2007)
In Re Mystic Tank Lines, Corp.
354 B.R. 694 (D. New Jersey, 2006)
Farmers Commission Co. v. Burks
719 N.E.2d 980 (Ohio Court of Appeals, 1998)
George v. Fannin
588 N.E.2d 195 (Ohio Court of Appeals, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
477 N.E.2d 1206, 17 Ohio App. 3d 59, 17 Ohio B. 114, 41 U.C.C. Rep. Serv. (West) 377, 1984 Ohio App. LEXIS 12432, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alliance-wall-corp-v-ampat-midwest-corp-ohioctapp-1984.