Alliance Pipeline L.P. v. 4.360 Acres of Land

746 F.3d 362, 180 Oil & Gas Rep. 1072, 2014 WL 1141057, 2014 U.S. App. LEXIS 5388
CourtCourt of Appeals for the Eighth Circuit
DecidedMarch 24, 2014
Docket13-1003
StatusPublished
Cited by33 cases

This text of 746 F.3d 362 (Alliance Pipeline L.P. v. 4.360 Acres of Land) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alliance Pipeline L.P. v. 4.360 Acres of Land, 746 F.3d 362, 180 Oil & Gas Rep. 1072, 2014 WL 1141057, 2014 U.S. App. LEXIS 5388 (8th Cir. 2014).

Opinion

WOLLMAN, Circuit Judge.

Leonard and lone Smith (the Smiths) appeal from a district court 1 order condemning portions of their property for the construction of a natural gas pipeline owned and operated by Alliance Pipeline, L.P. (Alliance), and granting Alliance immediate use and possession of the condemned land. Alliance brought the condemnation action against the Smiths’ property after obtaining a certificate from the Federal Energy Regulatory Commission (FERC) authorizing Alliance to condemn land along the route of its proposed pipeline. The Smiths assert that Alliance’s certificate is ineffective against them because Alliance failed to provide the Smiths with notice of its application for the certificate and because FERC failed to consider relevant state law in granting the certificate. The Smiths also assert that Alliance’s condemnation action runs afoul of state and federal procedural law. We affirm.

I.

Alliance operates an approximately 2300-mile network of oil and natural gas pipelines in the United States and Canada. In 2011, Alliance began plans to construct a 79-mile-long underground pipeline from a natural gas processing plant near Tioga, North Dakota, to an interconnection with Alliance’s main pipeline near Sherwood, North Dakota. There was at that time (and there continues to be) an oil boom in North Dakota, and occasionally oil prospectors would find reservoirs containing both petroleum and natural gas. The oil companies, having no pipeline capacity to ship the gas to major markets, would burn the gas at the source — a practice called “flaring.” Alliance sought to take advantage of this market inefficiency by shipping the otherwise wasted gas east to Chicago.

Anyone who wishes to construct a natural gas pipeline in the United States must first obtain a certificate of public convenience and necessity from FERC, the federal agency responsible for supervising and coordinating the production of energy in the United States. See 15 U.S.C. § 717f(c)-(e). Such a certificate also gives the recipient the authority to condemn land along the route of its pipeline under the power of eminent domain. See 15 U.S.C. § 717f(h). Alliance applied to FERC for a certificate of public convenience and necessity on January 25, 2012. FERC published notice of Alliance’s application in the Federal Register on February 7, 2012.

The Smiths are an elderly couple who own a farm near Sherwood, North Dakota. The route of Alliance’s proposed pipeline crossed the Smiths’ property. Sometime in February 2012, Alliance representatives visited the Smiths’ farm to ask the Smiths if Alliance could purchase an easement across their land. Because the Smiths were in poor health, Alliance representatives met with Guy Solemsaas, the son of lone and stepson of Leonard, who lives next to the Smiths and helps tend the *365 Smiths’ farm. Solemsaas told Alliance that neither he nor the Smiths were interested in negotiating the sale of an easement across the Smiths’ land.

On April 13, 2012, Alliance representatives visited the Smiths again, this time to serve them with a state-court summons and petition to enter and survey their property. Alliance asserted that it needed access to the Smiths’ property to complete various field surveys required as part of its FERC application. The state court granted Alliance’s petition on May 15, 2012.

On September 20, 2012, FERC granted Alliance a certificate of public convenience and necessity, and on October 16, 2012, Alliance brought a condemnation action against two parcels of land owned by the Smiths. Alliance moved for summary judgment and for immediate use and possession of the Smiths’ land. The district court granted both motions. See D. Ct. Order of Nov. 26, 2012.

II.

We review the district court’s grant of summary judgment de novo, viewing the evidence in the light most favorable to the nonmoving party. Hill v. Walker, 737 F.3d 1209, 1216 (8th Cir.2013). Summary judgment is appropriate when there is “no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(a). In challenging the district court’s grant of summary judgment to Alliance, the Smiths attack both Alliance’s FERC certificate and the procedural propriety of Alliance’s subsequent condemnation action. We address each challenge in turn.

A.

We begin with the Smiths’ challenge to the FERC certificate, which is twofold. First, the Smiths assert that Alliance failed to provide them notice of its FERC application as required by both the Due Process Clause of the Fifth Amendment and FERC’s own landowner .notice requirements, set forth in 18 C.F.R. § 157.6(d). Second, the Smiths assert that FERC failed to consider state criteria for the siting of pipelines in approving Alliance’s application. These criteria are set forth in North Dakota Administrative Code (NDAC) § 69-06-08-01.

We conclude that we lack jurisdiction to consider the Smiths’ statutory challenges (in other words, the challenges based on 18 C.F.R. § 157.6(d) and NDAC § 69-06-08-01).

When Congress prescribes specific procedures for the review of an administrative order, courts outside the statutory review framework are precluded from hearing challenges to that order. See City of Tacoma v. Taxpayers of Tacoma, 357 U.S. 320, 336, 78 S.Ct. 1209, 2 L.Ed.2d 1345 (1958). Section 19 of the Natural Gas Act, 15 U.S.C. § 717r(a)-(b), sets forth specific procedures for challenging a FERC order:

(a) Any person, state, municipality, or State commission aggrieved by an order issued by the Commission in a proceeding under this chapter to which such person, State, municipality, or State commission is a party may apply for a rehearing within thirty days after the issuance of such order.... No proceeding to review any order of the Commission shall be brought by any person unless such person shall have made application to the Commission for a rehearing thereon....
(b) Any party to a proceeding under this chapter aggrieved by an order issued by the Commission in such proceeding may obtain a review of such order in the court of appeals of the *366 United States ... by filing in such court, within sixty days after the order of the Commission upon the application for rehearing,. a written petition praying that the order of the Commission be modified or set aside in whole or in part....

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
746 F.3d 362, 180 Oil & Gas Rep. 1072, 2014 WL 1141057, 2014 U.S. App. LEXIS 5388, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alliance-pipeline-lp-v-4360-acres-of-land-ca8-2014.