Kern River Gas Transmission v. Clark County, Nev.

757 F. Supp. 1110, 1990 U.S. Dist. LEXIS 18465, 1990 WL 267394
CourtDistrict Court, D. Nevada
DecidedDecember 3, 1990
DocketCV-S-90-638-PMP (RJJ)
StatusPublished
Cited by21 cases

This text of 757 F. Supp. 1110 (Kern River Gas Transmission v. Clark County, Nev.) is published on Counsel Stack Legal Research, covering District Court, D. Nevada primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kern River Gas Transmission v. Clark County, Nev., 757 F. Supp. 1110, 1990 U.S. Dist. LEXIS 18465, 1990 WL 267394 (D. Nev. 1990).

Opinion

ORDER

PRO, District Judge.

In accordance with its Order of November 15, 1990, the Court heard argument on Thursday, November 29, 1990, regarding whether Plaintiff should be allowed to occupy certain land for the purpose of installing and maintaining an interstate natural gas pipe line. Construction of the project is scheduled to begin on Monday, December 3, 1990, and will be completed in January 1992 at a cost of slightly under $1 billion. Plaintiff has alleged that it will lose valuable construction contracts if the Court does not act in its favor by that date.

Before the Court is Plaintiffs Emergency Motion for Expedited Consideration and Consolidation (# 11). That Motion requests a ruling on the following motions previously filed:

1. Plaintiffs Motion for Immediate Occupancy (# 8), filed on November 1, 1990. Defendant Clark County filed its Opposition (# 16) on November 16, 1990, which was Joined by the City of Las Vegas (# 14) on November 15, 1990, and by the City of North Las Vegas (# 17) on November 16, 1990. Plaintiff filed its Reply (# 20) on November 28, 1990.

2. Defendant Clark County’s Motion to Dismiss or In the Alternative for Summary Judgment (# 5), filed on October 23, 1990, which Defendant City of Las Vegas Joined (# 6) on October 24, 1990. Plaintiff filed an Opposition (# 10) to these Motions on November 13, 1990. Clark County filed its Reply (# 18) on November 26, 1990, and that Reply was Joined (# 19) by the City of Las Vegas on November 27, 1990.

3. Defendant City of North Las Vegas’ Motion to Dismiss (#7), filed on October 24, 1990, to which Plaintiff filed an Opposition (# 10) on November 13, 1990.

Kern River Gas Transmission Company (“Kern River”) holds a Certificate of Public Convenience and Necessity (“the Certificate”) issued by the Federal Energy Regulatory Commission (“FERC”) on January 24, 1990. That Certificate authorizes Kern River to construct, operate, and maintain an interstate natural gas pipeline to trans *1113 port gas from Wyoming, through Utah and Southern Nevada, ultimately ending near Bakersfield in Southern California. During the certification process, all interested parties were given the opportunity to comment and object to the proposed route and manner of construction. In fact, according to Kern River, all Defendants participated in the FERC certification process in 1987 when they submitted their concerns, in writing, for FERC’s consideration. See Exhibits 2-4 to Plaintiffs First Amended Complaint (# 3). No objections were made to the proposed pipeline route through Southern Nevada. See Motion for Immediate Occupancy at 11.

The Certificate is approved only for a 1-mile corridor stretching from its point of origin in Wyoming to its terminus in California. Kern River may not depart from the approved corridor without obtaining additional approvals from the FERC. Also provided for in the Certificate is a 12-month right-of-way and easement for the purpose of constructing the pipeline.

Defendants’ Motions to Dismiss

Defendants raise many of the same basic issues in their various Motions to Dismiss (## 5, 6 & 7). First, Defendants argue that the Court has no jurisdiction to hear this matter because Plaintiff has not complied with Natural Gas Act provisions which must be fulfilled prior to filing suit. Specifically, Defendants argue that Plaintiff did not conduct thorough, good faith negotiations prior to filing their eminent domain suit, and that the Court is therefore deprived of jurisdiction.

The Natural Gas Act provides in pertinent part that:

When any holder of a certificate of public convenience and necessity cannot acquire by contract, or is unable to agree with the owner of property to the compensation to be paid for, the necessary right-of-way to construct, operate, and maintain a pipe line or pipe lines for the transportation of natural gas, and the necessary land or other property, in addition to right-of-way, for the location of compressor stations, pressure apparatus, or other stations or equipment necessary to the proper operation of such pipe line or pipe lines, it may acquire the same by the exercise of the right of eminent domain in the district court of the United States for the district in which such property may be located, or in the State courts....

15 U.S.C. § 717f(h). Defendants argue that Plaintiff had to negotiate in good faith for the amount of compensation paid to Defendants for Kern River’s permanent and temporary easements.

Plaintiff responds that such negotiations did occur. Indeed, Plaintiff’s Opposition to the Motions to Dismiss (# 10) by the Affidavit of Kirk Morgan and the exhibits attached thereto, details and provides necessary supporting documentation of several months of negotiations between Kern River and Defendants. It appears that the parties had reached substantial agreement on everything except the actual location of the pipeline within the one-mile wide corridor provided by the certificate. See Proposed Agreements attached to Exhibits 2, 3, and 4 of Plaintiff’s Opposition. For example, Kern River had tentatively agreed to upgrade the safety standards significantly over those required by the federal certification. In the Affidavit of Urban C. Livengood, Jr., Clark County’s Deputy Director of Public Works, Mr. Livengood states that he talked to Mr. Morgan of Kern River and in doing so “did say that the terms and conditions in excess of minimum federal requirements could be considered compensation, if accepted as such, by the Clark County Board of Commissioners.” See Affidavit at 3. This statement by a County official is certainly evidence that all parties considered the increased accommodations regarding safety as partial if not total consideration for the contract under negotiation.

Furthermore, at the hearing conducted November 29, 1990, Defendants argued that no impasse in the negotiations was reached prior to the filing of Plaintiff’s Complaint on September 28, 1990. However, in Plaintiff’s Opposition to the Motions to Dismiss, it appears that on August 21, 1990, the Board of County Commission *1114 ers held a meeting at which Plaintiff and the Public Works Director, Mr. Manning, presented the substance of a proposed agreement that was complete except for minor technical details. At that meeting, several County Commissioners indicated that they would not approve such an agreement unless the route was changed to one outside the mile-wide corridor previously approved by FERC. Plaintiffs Opposition (# 10) at 17-19, Affidavit of Kirk Morgan at 10, Exhibit 5. Under these circumstances, it would have been reasonable for Plaintiff to discontinue negotiations and file their eminent domain suit. However, Plaintiff did not do so. Instead, it continued to attempt to negotiate in good faith and did not file this suit until more than one month later, in spite of the County’s insistence that Kern River move the route outside that provided for in its Certificate. The Court finds that negotiation attempts were sufficient to fulfill Plaintiff’s statutory obligations under the Natural Gas Act.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Transcon. Gas Pipe Line Co. v. Certain Easements
359 F. Supp. 3d 257 (M.D. Pennsylvania, 2019)
Alliance Pipeline L.P. v. 4.360 Acres of Land
746 F.3d 362 (Eighth Circuit, 2014)
Alliance Pipeline L.P. v. 4.500 Acres of Land
911 F. Supp. 2d 805 (D. North Dakota, 2012)
Alliance Pipeline L.P. v. 2.679 Acres of Land
911 F. Supp. 2d 816 (D. North Dakota, 2012)
Alliance Pipeline L.P. v. 3.304 Acres of Land
911 F. Supp. 2d 826 (D. North Dakota, 2012)
East Tennessee Natural Gas Co. v. Sage
361 F.3d 808 (Fourth Circuit, 2004)
East TN Natural Gas v. Sage
Fourth Circuit, 2004
Northern Natural Gas Co. v. Munns
254 F. Supp. 2d 1103 (S.D. Iowa, 2003)
Kansas Pipeline Co. v. 200 Foot by 250 Foot Piece of Land
210 F. Supp. 2d 1253 (D. Kansas, 2002)
Guardian Pipeline, L.L.C. v. 950.80 Acres of Land
210 F. Supp. 2d 976 (N.D. Illinois, 2002)
Guardian Pipeline, L.L.C. v. 529.42 Acres of Land
210 F. Supp. 2d 971 (N.D. Illinois, 2002)
Lakehead Pipeline Co. v. Illinois Commerce Commission
696 N.E.2d 345 (Appellate Court of Illinois, 1998)
Tennessee Gas Pipeline Co. v. New England Power
6 F. Supp. 2d 102 (D. Massachusetts, 1998)
USG PIPELINE v. 1.74 Acres in Marion County, Tenn.
1 F. Supp. 2d 816 (E.D. Tennessee, 1998)
No Tanks Inc. v. Public Utilities Commission
1997 ME 167 (Supreme Judicial Court of Maine, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
757 F. Supp. 1110, 1990 U.S. Dist. LEXIS 18465, 1990 WL 267394, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kern-river-gas-transmission-v-clark-county-nev-nvd-1990.