Algonquin Gas Transmission v. Weymouth Conservation Comm.

919 F.3d 54
CourtCourt of Appeals for the First Circuit
DecidedMarch 19, 2019
Docket18-1686P
StatusPublished
Cited by12 cases

This text of 919 F.3d 54 (Algonquin Gas Transmission v. Weymouth Conservation Comm.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Algonquin Gas Transmission v. Weymouth Conservation Comm., 919 F.3d 54 (1st Cir. 2019).

Opinion

KAYATTA, Circuit Judge.

Algonquin Gas Transmission, LLC ("Algonquin") seeks to build a natural gas compressor station in Weymouth, Massachusetts as one component of Algonquin's larger effort to improve its natural-gas delivery infrastructure in the northeastern United States. Algonquin has received a certificate of public convenience and necessity ("CPCN") from the Federal Energy Regulatory Commission ("FERC"), but that certificate is conditioned upon the receipt of a consistency determination from the Commonwealth of Massachusetts pursuant to the Coastal Zone Management Act ("CZMA"). To complete its CZMA review, Massachusetts requires Algonquin to furnish a permit from the Massachusetts Department of Environmental Protection ("MassDEP"). But MassDEP will not issue such a permit until the Town of Weymouth approves the project under its local ordinance or a court finds that ordinance preempted as applied to the project.

After unsuccessfully seeking Weymouth's approval to begin construction, Algonquin repaired to the U.S. District Court for the District of Massachusetts, from which it obtained a ruling that Weymouth's ordinance, as applied to the project, is indeed preempted. Weymouth now appeals that ruling. For the following reasons, we affirm.

I.

We briefly survey the regulatory topography, the pertinent facts, and the procedural history in this case.

A.

The federal Natural Gas Act ("NGA") governs the transportation and sale of natural gas in interstate commerce and the importation and exportation of natural gas in foreign commerce. See 15 U.S.C. § 717 (b). The NGA requires a prospective developer to obtain a CPCN from FERC prior to constructing a jurisdictional natural gas pipeline or ancillary facility. Id. § 717f(e). FERC must issue a CPCN if the applicant demonstrates that it "is able and willing ... to conform to the provisions of [the Act] ... and regulations of [FERC]" and the proposed construction is "required by the present or future public convenience and necessity." Id. In issuing a CPCN, FERC also has the authority to impose "reasonable terms and conditions as the public convenience and necessity may require." Id.

The other federal statute relevant to this appeal, the CZMA, provides grants of money to states that adopt federally approved coastal-management programs. See generally 16 U.S.C. § 1455 . Among other requirements, a coastal-management program must define the "permissible land uses and water uses" and promulgate "[b]road guidelines on priorities of uses" within the state's coastal zones. Id. § 1455(d)(2). The CZMA limits FERC's certificate-granting authority in at least one important way: It prohibits FERC from granting a permit to conduct an activity that will affect "any land or water use or natural resource of the coastal zone" until the state concurs with an applicant's determination that the proposed activity "complies with the enforceable policies of the state's approved [coastal-management program]." Id. § 1456(c)(3)(A). The Massachusetts Office of Coastal Zone Management ("Massachusetts OCZM") administers the Commonwealth's CZMA program.

Two local laws also bear on this dispute. The Massachusetts Wetlands Protection Act ("Massachusetts WPA") provides performance standards for construction activities in wetlands areas. See Mass. Gen. Laws ch. 131, § 40 . 1 The Act "sets forth minimum standards only, 'leaving local communities free to adopt more stringent controls.' " Lovequist v. Conservation Comm'n of Dennis , 379 Mass. 7 , 393 N.E.2d 858 , 863 (1979) (quoting Golden v. Selectmen of Falmouth , 358 Mass. 519 , 265 N.E.2d 573 , 577 (1970) ). It also requires a developer to file a notice of intention with and obtain an order of conditions from the municipality in which the construction is to be located prior to commencing construction. Mass. Gen. Laws ch. 131, § 40 . Finally, the Weymouth Wetlands Protection Ordinance ("Weymouth WPO") generally requires a developer to obtain a permit from the Weymouth Conservation Commission before construction can begin in a wetlands area. Weymouth, Mass., Code § 7-301(b). The Weymouth WPO gives the Conservation Commission the authority to impose permit conditions or deny an application in its entirety if it finds the project will not meet Conservation Commission performance standards or regulations. Id. § 7-301(k).

B.

Algonquin is a natural-gas transmission company that is headquartered in Houston, Texas. In response to rising demand for natural gas, Algonquin's proposed "Atlantic Bridge Project" aims to increase the delivery capacity of its existing natural-gas transmission system in the northeastern United States. Algonquin seeks to construct a new compressor station-an appurtenance that is placed alongside a gas pipeline to maintain pressure and gas-flow rates-in Weymouth, Massachusetts as part of this project. The proposed site is located within and adjacent to a wetlands area. It is also situated in a coastal zone subject to Massachusetts' coastal-management program.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
919 F.3d 54, Counsel Stack Legal Research, https://law.counselstack.com/opinion/algonquin-gas-transmission-v-weymouth-conservation-comm-ca1-2019.