City of Fall River v. Federal Energy Regulatory Commission

507 F.3d 1, 169 Oil & Gas Rep. 664, 37 Envtl. L. Rep. (Envtl. Law Inst.) 20268, 2007 U.S. App. LEXIS 25146
CourtCourt of Appeals for the First Circuit
DecidedOctober 26, 2007
Docket06-1203, 06-2146, 06-1204, 06-2147, 06-1220
StatusPublished
Cited by50 cases

This text of 507 F.3d 1 (City of Fall River v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Fall River v. Federal Energy Regulatory Commission, 507 F.3d 1, 169 Oil & Gas Rep. 664, 37 Envtl. L. Rep. (Envtl. Law Inst.) 20268, 2007 U.S. App. LEXIS 25146 (1st Cir. 2007).

Opinion

TORRUELLA, Circuit Judge.

The City of Fall River, Massachusetts, the Attorneys General of the States of Massachusetts and Rhode Island, the Conservation Law Foundation (“CLF”), and Michael Miozza (together, “Appellants”) seek reversal of the July 2005 Order of the Federal Energy Regulatory Commission (“FERC”) granting conditional approval to Weaver’s Cove Energy (“WCE”) to site, construct, and operate a proposed liquified natural gas (“LNG”) terminal and associated pipeline in Fall River, Massachusetts, as well as the reversal of subsequent orders denying the reopening of the record and rehearing. The facility, which would include a marine berth (requiring dredging of the harbor and waterways, including the Taunton River), an LNG storage tank, re-gasification facilities, and an LNG truck distribution facility, would receive LNG from ocean-going ships for off-load to trucks or for regasification and delivery by pipeline to New England’s network of natural gas pipelines.

The conditional permit is subject to a number of stipulations, including approval of the vessel transportation plan by the United States Coast Guard (“USCG”) and consistency with the Wild and Scenic Rivers Act, as determined by the Department of the Interior (“DOI”). Because the USCG and the DOI have not completed their respective evaluations of these aspects of the project, we find that it would be premature to address the merits of the appeal. Appellants maintain the right to petition FERC, and subsequently seek appeal to this Court, if and when these and other relevant agencies have made their final recommendations.

I. Background

In 2004, FERC, USCG, and the United States Department of Transportation (“DOT”) entered into an Interagency Agreement to coordinate review of proposed LNG facilities. Under the agreement, FERC is the lead agency in autho *4 rizing LNG facilities and in preparing a proposed facility’s Environmental Impact Statement (“EIS”), 1 which is required by the National Environment Policy Act of 1969 (“NEPA”), 42 U.S.C. §§ 4321 et seq. Generally, authorization is granted (as it was in this case) on the condition that certain stipulations, environmental and otherwise, are met.

Here, the development of the EIS began on May 2, 2003, with a preliminary meeting between WCE, FERC staff, and key federal and state officials to discuss WCE’s proposal and the accompanying environmental review process. At that time, FERC invited all federal, state, or local agencies with jurisdiction or special expertise to cooperate in preparing the EIS, and also invited all interested parties to submit written comments and to attend a public scoping meeting to be conducted jointly by FERC and Massachusetts state officials on July 29, 2003. On December 19, 2003, WCE formally applied to FERC under the Natural Gas Act of 1938 (“NGA”), 15 U.S.C. §§ 717 et seq., requesting authority to site, construct, and operate the proposed LNG facility.

During the review process, FERC received voluminous comments from the public, as well as objections from government agencies. As part of this process, FERC’s Commissioner and Chairman also hosted a meeting in January 2005, at which Fall River’s Mayor, Senators Edward Kennedy and John Kerry, Congressman James McGovern, Massachusetts Representative David Sullivan, and then-Governor Mitt Romney’s representative presented their views on the proposal.

Based on those comments and the research conducted during the review process, FERC prepared and issued a Final EIS on May 20, 2005, and conditionally authorized the project on July 11, 2005. 2 The conditional authorization was based on an analysis of the need for the project, 3 project alternatives, 4 and safety and security considerations. 5

The conditions imposed on the project’s authorization include two significant hurdles: (1) approval of WCE’s transportation plan by the USCG, 6 and (2) the DOI’s *5 finding that the project is consistent with the Wild and Scenic Rivers Act. 7 Neither the USCG nor the DOI have completed their respective final evaluations.

Since the conditional approval, there have also been two changes in project conditions that could very well affect WCE’s final project approval. First, at the time of conditional approval, the Brightman Street Bridge, which crosses the river leading from the ocean to the planned LNG facility site, was scheduled for demolition. However, in late 2005, Congress passed legislation forbidding the demolition of the bridge, frustrating WCE’s original plan to use 150-foot wide vessels to bring LNG to the facility. A new, larger Brightman Street Bridge is still scheduled to be built next to the old protected bridge. In an amended proposal, WCE informed the USCG that it would use smaller ships that could pass through the ninety-eight foot wide opening of the Bridge, thereby increasing the frequency of shipments from the planned fifty to seventy deliveries up to 120 deliveries per year. Even with the smaller ships, however, transit through the new and old Bright-man Street Bridges would be “an extraordinary navigational maneuver” leaving “no margin for error,” according to the Coast Guard’s preliminary findings.

Second, seven months after FERC approval, DO! announced new restrictions that would limit the dredging of the necessary waterways to a few months of the year, likely delaying the completion of the project from 2010 to 2015.

On April 17, 2006, CLF petitioned FERC to reopen the record to consider the impact of those two developments on the project. FERC denied the motion, finding that there had not been a change in circumstances on which its conditional approval was based, and therefore review was not warranted. FERC explained that it is the USCG’s duty to review the changed shipment plan in its yet-to-be-released Letter of Recommendation, and that there is no change relative to FERC’s conditional approval unless the USCG’s review of this matter results in changes to the project that require a change to the plan authorized by FERC. 8 FERC did not address the potential impact of the changes in dredging regulations on the project’s start date.

Following FERC’s order denying the motion to reopen the record, CLF requested a rehearing based on the changes to WCE’s navigation plan and potential delays caused by the new dredging constraints. FERC denied CLF’s subsequent rehearing request on July 19, 2006. The explanation accompanying the denial of re *6 hearing was largely the same as the denial to the motion to reopen.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
507 F.3d 1, 169 Oil & Gas Rep. 664, 37 Envtl. L. Rep. (Envtl. Law Inst.) 20268, 2007 U.S. App. LEXIS 25146, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-fall-river-v-federal-energy-regulatory-commission-ca1-2007.