Al Johnson Construction Co. v. Missouri Pacific Railroad

426 F. Supp. 639, 1976 U.S. Dist. LEXIS 14915
CourtDistrict Court, E.D. Arkansas
DecidedMay 25, 1976
DocketLR 72-C-80
StatusPublished
Cited by9 cases

This text of 426 F. Supp. 639 (Al Johnson Construction Co. v. Missouri Pacific Railroad) is published on Counsel Stack Legal Research, covering District Court, E.D. Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Al Johnson Construction Co. v. Missouri Pacific Railroad, 426 F. Supp. 639, 1976 U.S. Dist. LEXIS 14915 (E.D. Ark. 1976).

Opinion

MEMORANDUM OF DECISION AND ORDER

BENSON, District Judge.

NATURE OF THE CASE

This diversity contract action was tried to the Court without a jury. The uncontroverted facts and the unresolved issues were stipulated by the parties as follows:

The Missouri Pacific Railroad, Defendant herein, entered into agreements with the United States of America covering the *641 alteration of the Missouri Pacific Railroad Companies Junction Bridge (Contract No. 62450) and the Baring Cross Bridge (Contacts No. 62855), both across the Arkansas River at Little Rock, Arkansas. Under these contracts, the Defendant was required to make the necessary alterations to the bridges and the United States of America was required to compensate Defendant for money expended in making the alterations.
After plans for the required work were completed, bids were taken for performing the substructure alterations necessary for the two bridges and for construction of a shoofly bridge (a temporary bridge) for use during the construction work. The A1 Johnson Construction Company of Minneapolis, Minnesota' (Plaintiff) was the successful bidder for this work and accordingly the railroad entered into an agreement with Plaintiff on June 5, 1968 (Contract 64444) to perform the necessary substructure work.
During the' performance of this work, certain conditions were encountered that Plaintiff took exception to as being different from those shown in the plans and specifications. The Plaintiff filed with the Defendant the following claims for additional compensation. These claims are as follows:
1. Changed conditions at the South Pier, Junction Bridge — amount $257,000.00 —submitted November 3, 1969.
2. Changed conditions Shoofly Bridge— increased the driving and drilling costs — amount $40,000.00.
3. Changed conditions Baring Cross Bridge — driving and drilling 30 inch pipe piles through obstructions— amount $63,000.00 — submitted January 5, 1970.
4. Change in the work — Baring Cross Bridge, Pier 6 — explosives prohibited — amount $20,065.00 — submitted February 17, 1971.
5. Changed conditions — Shoofly Bridge— Cofferdam required — amount $5,381.-70 — submitted November 13,1969.
The Plaintiff claims that it encountered Changed Conditions as contemplated in paragraph 8 of Special Conditions of the contract and that Changes in the work took place within the meaning of paragraph 43 of the General Provisions of the contract, in each of the claims stated above. Defendant denied that Changed Conditions existed within the meaning of the contract and that no Changes in the contract occurred in connection with the above mentioned claims. 1

FINDINGS

A. GENERAL

The consulting engineers on the project, Sverdrup & Parcel and Associates, Inc., of St. Louis, Missouri (S & P), were retained by Defendant, Missouri Pacific Railroad Company, (MOPAC), in February, 1967, to perform engineering services including surveys, design, preparation of plans and specifications and contract documents, with estimates of quantities and costs. S & P was also retained by MOPAC under a separate contract to perform survey investigations which included core boring and seismic profiling. S & P also acquired and used boring data compiled by the United States Corps of Engineers (Corps), in 1964. In addition, 5 & P engaged EG & G International, (EG 6 G), to identify possible obstructions in the vicinity of Pier 5 of the Baring Cross Bridge. All of this information, with the exception of the EG & G report, was incorporated into the plans and specifications furnished to the bidders. The EG & G report was also furnished to prospective bidders. The invitation to bid was issued on May 1,1968, and the bid opening was set for June 5, 1968. The bid of Plaintiff, A1 Johnson Construction Co. of Minneapolis, Minnesota (Johnson Construction) was accepted and it was awarded the contract.

*642 Johnson Construction received the bid invitation and a copy of the plans and specifications and other information in early May, 1968. After studying the plans and specifications, and all other information provided by MOPAC, it made an on-site inspection on May 24 and 25, 1968. At that time, the river was running about ten feet higher than normal and the water was in a riled condition. Neither the logs nor the on-site inspection disclosed the existence of unusual subsurface conditions in the vicinity of the proposed construction.

Because of the short time interval between the invitation to bid and the bid opening and because of the high water level at that time of year, it was not possible for bidders to make their own subsurface exploration of site conditions prior to bidding, and MOPAC did not really expect that they would. In preparation of its bid, Johnson Construction relied on the subsurface information supplied to it by MOPAC. The contract clauses relevant to the issues in this case are found in the specifications and provide:

“GENERAL PROVISIONS.
“Article 7. EXAMINATION ' OF PLANS, SPECIFICATIONS AND SITE OR WORK. It shall be understood that the Contractor has, by careful examination, satisfied himself as to the nature and location of the work, the conformation of the ground, the character, quality and quantity of the materials to be encountered, the character of equipment and facilities needed preliminary to and during the prosecution of the work, the general and local conditions, and all other matters which can in any way effect the work under this Contract. . .
“Article 43. CHANGES. The Company shall have the right to make any changes that may be hereafter determined upon, in the nature or dimensions of the work, either before or after its commencement, and such changes shall in no way affect or void the obligations of this Contract. If such changes make any change in the cost of the work, an equitable adjustment shall be made by the Chief Engineer to cover the same, but the Contractor shall not claim compensation for anticipated profits.”
SPECIAL CONDITIONS.
“Article 6. SUBSURFACE CONDITIONS.
Certain boring information has been obtained for design purposes and the logs of borings are shown on the plans for the convenience of the Contractor and for such use, if any, as he may at his own risk desire to make of it. No representations or guarantees are made concerning the completeness of the boring data. Such data indicates an opinion as to materials encountered at the specification location of the respective borings and may not represent materials which will actually be encountered in performing the work.
The Contractor shall also be informed that an older bridge stood on the site of the present Baring Cross Bridge.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thomas Crimmins Contracting Co. v. City of New York
138 A.D.2d 138 (Appellate Division of the Supreme Court of New York, 1988)
Cook v. Oklahoma Board of Public Affairs
1987 OK 22 (Supreme Court of Oklahoma, 1987)
Pinkerton and Laws Co., Inc. v. Roadway Exp., Inc.
650 F. Supp. 1138 (N.D. Georgia, 1986)
M.C. Anderson v. Golden
569 F. Supp. 122 (S.D. Georgia, 1982)
Joseph F. Trionfo & Sons, Inc. v. BD. OF EDUC. OF HARFORD CTY.
395 A.2d 1207 (Court of Special Appeals of Maryland, 1979)
Johnson Constr. v. Mo. Pac. R. R. Co
553 F.2d 103 (Eighth Circuit, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
426 F. Supp. 639, 1976 U.S. Dist. LEXIS 14915, Counsel Stack Legal Research, https://law.counselstack.com/opinion/al-johnson-construction-co-v-missouri-pacific-railroad-ared-1976.