Ajax Hardware Manufacturing Corporation v. Industrial Plants Corporation

569 F.2d 181
CourtCourt of Appeals for the Second Circuit
DecidedAugust 16, 1977
Docket32, Docket 75-7663
StatusPublished
Cited by78 cases

This text of 569 F.2d 181 (Ajax Hardware Manufacturing Corporation v. Industrial Plants Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ajax Hardware Manufacturing Corporation v. Industrial Plants Corporation, 569 F.2d 181 (2d Cir. 1977).

Opinions

TIMBERS, Circuit Judge:

In this diversity action plaintiff Ajax Hardware Manufacturing Corporation (Ajax) sought to recover from defendant Industrial Plants Corporation (Industrial) damages for breach of contract, negligence and fraud arising from Industrial’s performance under a contract to appraise certain machinery for Ajax.

There have been two jury trials in the Southern District of New York before Richard H. Levet, District Judge. Ajax appeals (1) from an order entered after the first trial denying its motion for judgment n. o. v. or a new trial limited to the issue of damages, but granting on the ground of an improper compromise verdict Industrial’s motion for a new trial on all issues; and (2) from a judgment dismissing the complaint entered upon a verdict for Industrial returned at the second trial.

We hold that a new trial on all issues was properly ordered after the first trial, but that at the second trial the court erred in dismissing Ajax’s claims for negligence and fraud and in restricting the scope of its claim for breach of contract. Accordingly, we reverse and remand for a third trial.

I. FACTS

In August 1966 Ajax was negotiating with the United States government for a $3,500,000 contract to manufacture time fuses. In order to perform the contract Ajax required a subcontractor which had light precision watchmaking equipment. Time & Micro Instruments, Inc. (T&M) had such a facility which was lying idle. Ajax, contemplating either a subcontractor or a joint venture, entered into negotiations [183]*183with T&M. Since the latter could not participate without an infusion of cash, the deal was to include a $350,000 loan from an institutional lender to T&M. Ajax, secured by the machinery at the T&M plant, was to guarantee T&M’s obligation.

In anticipation of a commitment to guarantee the loan to T&M, Ajax engaged Industrial to appraise the machinery at the T&M plant. Ajax acted through its Vice President, Howard Klein. On August 12 Klein concluded an oral agreement with Industrial’s Vice President, Jesse Thaler. The terms of this agreement give rise to the principal factual question in the case. According to Klein, he informed Thaler that Ajax intended to guarantee a loan and wanted to know whether the T&M machinery would be adequate security. Klein testified that he told Thaler that Ajax “wanted to know the forced liquidation value of the equipment in case there was a default on the loan. . . . ” According to Thaler, Klein requested an appraisal based on the market value of the plant in place, intact and ready for operation — not based on the forced liquidation value of the individual machines.

Thaler inspected the T&M plant on August 15 and telephoned a preliminary evaluation to Klein. According to Klein, Thaler reported fair market value of approximately $900,000 and a forced liquidation value of $500,000. Klein requested a confirming telegram which Thaler sent on August 17. The telegram stated that the machinery and equipment had a “fair market value” of $919,072 and an additional “in place value” of $137,806, for a “total in place value” of the plant of $1,056,878. The telegram further stated that “[wjhile it is difficult to project market values for the next two years it is inconceivable that the value of this plant would be less than 60 percent of the appraised figure.” The telegram further stated that the machinery was of Swiss manufacture and difficult to obtain in this country; that delivery of equivalent machinery required two or three years; that manufacturers would pay premiums to procure an existing plant; and that prices on the general “machinery market” were high at that time.

Industrial sent a formal appraisal report and letter to Ajax on August 19 which reiterated the substance of its telegram of August 17 in all material respects. The appraisal was received by Ajax on August 22. It set forth a list of each piece of machinery with an individual dollar value for each. The sum of these individual valuations was substantially in accord with the figures stated in the August 17 telegram.

On August 18 Ajax signed a commitment to obtain and guarantee a $270,000 loan to T&M. Under the agreement Ajax had until September 9 to perform or to cancel and pay a $20,000 penalty. Ajax performed, secured by the machinery appraised by Industrial. T&M later defaulted. A subsequent “forced sale” of the plant equipment at auction netted only $144,000. As a result, Ajax had to repay the lender $163,-270.70, the unpaid balance of the $270,000 T&M loan after application of the $144,000 proceeds from the sale. Ajax’s explanation for the discrepancy between the $144,000 figure and the values reported by Industrial is that in 1966 the watchmaking industry in this country was moribund; in fact no market existed for the T&M machinery.

Ajax commenced the instant diversity action on May 5, 1969 against Industrial to recover the resulting $161,895.75 deficiency on its T&M guaranty, i. e. $163,270.70 less certain adjustments. Ajax alleged breach of contract, negligence and fraud on the part of Industrial in rendering its appraisal.

II. FIRST TRIAL

The first trial began on April 23, 1975 and was concluded on May 1,1975 when the jury returned a $70,000 verdict in favor of Ajax on its negligence claim and a verdict against Ajax on its contract and fraud claims. Ajax made a motion to set aside the $70,000 verdict in its favor, requesting either that judgment be entered n. o. v. in amount of $161,895.75 or that there be granted a new trial limited to the issue of damages. Industrial moved that the entire verdict be set aside and for a new trial on [184]*184all issues on the alternative grounds that the $70,000 verdict was against the weight of the evidence or an improper compromise between liability and damages. Both parties argued that if Ajax was entitled to damages at all it was entitled to the liquidated sum of $161,895.75. Judge Levet, focusing on the jury’s return of a verdict which fell substantially below that liquidated sum, held that the verdict was a compromise one and granted Industrial’s motion for a new trial on all issues.

The facts as stated present the very situation out of which an inference of a compromise verdict most readily arises. As we said in Maher v. Isthmian Steamship Co., 253 F.2d 414, 416-17 (2 Cir. 1958), the inference of a compromise stems from an inconsistency between the verdict and the facts adduced at trial, and “[s]uch an inconsistency is most clearly apparent when the plaintiff sues for a liquidated sum . where the only defense is denial of the obligation, and the verdict for the plaintiff is in an amount substantially less than that claimed.” But a compromise on the issue of liability is not the only reasonable explanation for the instant $70,000 verdict. Judge Levet instructed the jury on compensatory damages as follows: “If you should find that the plaintiff is entitled to compensatory damages, your award cannot exceed the total sum claimed for such damages, which is $161,895.75.” (emphasis added). The jury might well have understood this to mean that it was permissible to award any sum that did not exceed the stated limit.1

Ajax contends that the district court’s finding of a compromise verdict must be reviewed in the light of the Maher

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maddox v. Francemone
N.D. New York, 2025
Spizz v. Eluz
S.D. New York, 2023
Lindsey v. Butler
S.D. New York, 2022
Banco Multiple Santa Cruz v. Moreno
888 F. Supp. 2d 356 (E.D. New York, 2012)
In Re Vivendi Universal, S.A. Securities Litigation
765 F. Supp. 2d 512 (S.D. New York, 2011)
Shema Kolainu-Hear Our Voices v. Providersoft, LLC
832 F. Supp. 2d 194 (E.D. New York, 2010)
Lewis v. City of New York
689 F. Supp. 2d 417 (E.D. New York, 2010)
Aczel v. Labonia
584 F.3d 52 (Second Circuit, 2009)
Schwartz v. Fortune Magazine
193 F.R.D. 144 (S.D. New York, 2000)
Fox v. City University of New York
187 F.R.D. 83 (S.D. New York, 1999)
Atkins v. New York City
143 F.3d 100 (Second Circuit, 1998)
Joseph v. David M. Schwarz/Architectural Services, P.C.
957 F. Supp. 1334 (S.D. New York, 1997)
Allen v. Westpoint-Pepperell, Inc.
11 F. Supp. 2d 277 (S.D. New York, 1997)
Dorking Genetics v. United States
76 F.3d 1261 (Second Circuit, 1996)
Goodman v. Waugh
882 F. Supp. 64 (S.D. New York, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
569 F.2d 181, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ajax-hardware-manufacturing-corporation-v-industrial-plants-corporation-ca2-1977.