Air Distribution Corp. v. AIRPRO MECHANICAL CO.

973 A.2d 537, 2009 R.I. LEXIS 87, 2009 WL 1841702
CourtSupreme Court of Rhode Island
DecidedJune 29, 2009
Docket2008-113-Appeal
StatusPublished
Cited by9 cases

This text of 973 A.2d 537 (Air Distribution Corp. v. AIRPRO MECHANICAL CO.) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Air Distribution Corp. v. AIRPRO MECHANICAL CO., 973 A.2d 537, 2009 R.I. LEXIS 87, 2009 WL 1841702 (R.I. 2009).

Opinion

OPINION

Justice ROBINSON

for the Court.

One of the defendants in this case, Hartford Accident and Indemnity Company (Hartford or defendant), appeals from the Superior Court’s grant of summary judgment in favor of the plaintiff, Air Distribution Corp. (Air Distribution or plaintiff). This case concerns the plaintiffs allegation that it was never paid for certain goods that it supplied to a subcontractor for a public building project. As a result of this nonpayment, the plaintiff filed a complaint against the defendant Hartford and code-fendant Airpro Mechanical Co., Inc. (Air-pro). In that complaint, a count for breach of contract and a count of unjust enrichment were directed against codefen-dant Airpro, while a third count (concerning a performance and payment bond) was directed against the defendant Hartford.

On March 13, 2007, the Superior Court heard and granted plaintiffs motion for summary judgment. The hearing justice’s ruling was predicated on this Court’s frequently articulated interpretation of G.L. 1956 §§ 37-12-1, 37-12-2, G.L. 1956 §§ 34-28-30, and 34-28-31. Final judgment was entered on November 2, 2007, and Hartford timely filed the instant appeal.

On appeal, Hartford’s sole argument is that this Court should overturn its longstanding precedent addressing the meaning of several sections of our General Laws concerning the legal recourse available to unpaid subcontractors against the sureties of general contractors engaged in public building projects. We decline to do so, and we therefore affirm the judgment of the Superior Court.

Facts 1 and Travel

In September of 2004, the state entered into a $3,987,000 construction contract with general contractor A.F. Lusi Construction, Inc. for construction of the Blackstone Val *539 ley Gateway Center in Lincoln, Rhode Island. Pursuant to § 37-12-1, Hartford acted as surety for A.F. Lusi by issuing a surety bond to ensure payment. 2

The plaintiff is a distributor of heating, ventilating, and air conditioning (HVAC) products, and it provided HVAC products for use in the Blackstone Valley Gateway Center. Said products were procured by, and delivered to, defendant Airpro Mechanical. Airpro was a subcontractor to Miller Mechanical, Inc. which was, in turn, a subcontractor to A.F. Lusi. 3 Invoices in the record reflect that products costing a total of $16,626.95 were supplied by Air Distribution to Airpro between May 23, 2005 and August 31, 2005.

Within ninety days of the date of the issuance of the last invoice, Air Distribution provided written notice to A.F. Lusi as the principal on Hartford’s payment bond. The notice was in the form of two facsimiles dated October 5, 2005 and November 16, 2005. Each facsimile detailed the outstanding monies owed to Air Distribution for products delivered for use in the Blackstone Valley Gateway Center project. The principal and owner of A.F. Lusi acknowledged the faeisimile, confirmed the amount due to Air Distribution, and promised that plaintiff would be paid. To date, Air Distribution has not received any payment.

In January of 2006, plaintiff commenced the instant lawsuit against Airpro and Hartford (as the surety on the general contractor’s payment bond) to recover the outstanding monies owed for the HVAC products delivered by Air Distribution.

In May of 2006, plaintiff filed an amended complaint. Count one (breach of contract) and count two (unjust enrichment) of the amended complaint were directed against Airpro; those counts concerned the subcontracts plaintiff had with Airpro for the supply of HVAC products. Count three of the amended complaint was directed against Hartford. Air Distribution stated that it was entitled to payment of outstanding monies owed by Airpro under the bond issued by Hartford for the Blackstone Valley Gateway Center project. Soon after the lawsuit was filed, Airpro went into receivership.

The only defense raised by Hartford in its answer to Air Distribution’s complaint was that plaintiff was barred from recovery by virtue of Chapter 12 of title 37 of the General Laws. Hartford’s argument (developed more fully in later arguments before the Superior Court) was essentially twofold. First, Hartford contended that Air Distribution is not a proper party for recovery under § 37-12-2 because it is a “Tier 3” subcontractor. 4 Second, it argued *540 that Air Distribution failed to provide notice of its claim on the bond as required by § 37-12-2-specifícally, Hartford accurately notes that plaintiff failed to provide the principal on the bond (A.F. Lusi) with notice of plaintiffs claim within ninety days by certified mail as required by that section of the General Laws.

*539 "[A]ny person having a direct contractual relationship with a subcontractor but no contractual relationship express or implied with the contractor furnishing the payment bond shall have a right of action upon the payment bond upon giving written notice to the contractor within ninety (90) days from the date on which the person 'f * * fur-

*540 The plaintiff filed a motion for summary judgment against Hartford pursuant to Rule 56(b) of the Superior Court Rules of Civil Procedure. The plaintiff indicated that it was pursuing its claim against Hartford under § 34-28-30 and § 34-28-31, as opposed to § 37-12-2. It asserted that, pursuant to this Court’s well-settled precedent, it was entitled to bring suit against Hartford and to receive summary judgment in the matter because the requirements of § 37-12-2 were inapposite.

A hearing on the motion was held before the Superior Court on March 13, 2007. At that hearing, the hearing justice indicated that she agreed with Hartford’s arguments concerning the interpretation of the statutes at issue; nevertheless, she indicated that she was bound by the precedent of this Court, which clearly states that a subcontractor can pursue remedies of a payment bond under § 34-28-30. For this reason, the hearing justice granted summary judgment in favor of plaintiff. An order granting summary judgment against Hartford was entered on March 29, 2007. Partial final judgment was entered on November 2, 2007 pursuant to Rule 54(b) of the Superior Court Rules of Civil Proee-dure. 5 Hartford timely filed its appeal to this Court.

On appeal, Hartford’s solitary argument is that this Court should reverse its well-settled precedent concerning the ability of a subcontractor to recover on a payment bond pursuant to § 34-28-30 and § 34-28-31. We decline to do so and hereby affirm the judgment of the Superior Court.

Standard of Review

This Court reviews the granting of a motion for summary judgment on a de novo basis. Planned Environments Management Corp. v. Robert, 966 A.2d 117, 121 (R.I.2009);

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Frank Diaz v. Select Portfolio Servicing
Supreme Court of Rhode Island, 2026
Russell Henry v. Media General Operations, Inc.
Supreme Court of Rhode Island, 2021
Rhode Island v. Atl. Richfield Co.
357 F. Supp. 3d 129 (D. Rhode Island, 2018)
State v. Linda A. Diamante
83 A.3d 546 (Supreme Court of Rhode Island, 2014)
DeMarco v. Travelers Insurance Co.
26 A.3d 585 (Supreme Court of Rhode Island, 2011)
Generation Realty, LLC. v. Catanzaro
21 A.3d 253 (Supreme Court of Rhode Island, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
973 A.2d 537, 2009 R.I. LEXIS 87, 2009 WL 1841702, Counsel Stack Legal Research, https://law.counselstack.com/opinion/air-distribution-corp-v-airpro-mechanical-co-ri-2009.