Providence Elec. Co., Inc. v. Donatelli Bldg. Co., Inc.

356 A.2d 483, 116 R.I. 340, 1976 R.I. LEXIS 1283
CourtSupreme Court of Rhode Island
DecidedMay 6, 1976
Docket74-258-Appeal
StatusPublished
Cited by19 cases

This text of 356 A.2d 483 (Providence Elec. Co., Inc. v. Donatelli Bldg. Co., Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Providence Elec. Co., Inc. v. Donatelli Bldg. Co., Inc., 356 A.2d 483, 116 R.I. 340, 1976 R.I. LEXIS 1283 (R.I. 1976).

Opinion

*341 Doris, J.

This is a civil action to recover on a labor and material payment bond. The cause was tried to a Superior Court justice sitting without a jury. From a judgment awarding the plaintiff the sum of $2,853.59, the defendants have appealed to this court.

The plaintiff instituted action against defendants by placing a claim on a labor and material payment bond exe *342 cuted and delivered by defendants to the town of North Providence pursuant to a building contract between defendant, Donatelli Building Co., Inc., and said town of North Providence. The bond, and building contract, are each dated August 25, 1966. It was stipulated at trial below that plaintiff sent notice of its claim to defendants and to the town of North Providence in December 1967.

In the complaint filed in Superior Court on May 17, 1968, plaintiff alleges that it furnished materials to Rhode Island Electric Co., Inc., a subcontractor of defendant, Donatelli Building Co., Inc., and that the subcontractor had become insolvent and bankrupt while indebted to plaintiff for the cost of said materials. The plaintiff further alleges that said materials were furnished for use in the construction of a public building, the Senior High School addition, belonging to the town of North Providence, and that the materials in question were used or reasonably required for use in the erection of said building.

The plaintiff claims to be entitled to payment under the said bond by virtue of G. L. 1956 (1969 Reenactment) §§34-28-30 1 and 34-28-31. 2 The defendants contend that *343 the bond was furnished to the town as required by §37-13-13 3 and was therefore subject to the provisions of chapter 12 of title 37. The defendants argue that plaintiff’s admitted failure to comply with the notice requirements of §37-12-2 et seq., is a bar to plaintiff’s claim for recovery under the bond.

The trial justice found that §§34-28-30 and 34-28-31 were applicable to plaintiff’s claim and that plaintiff was not bound by the notice provisions contained in chapter 12 of title 37. The trial justice further found that §§34-28-30 and 34-28-31 were enacted into law by the Legislature in 1965 and in his opinion provide a new and broad remedy to a person performing labor or furnishing mate *344 rials under or pursuant to a construction contract where a bond has been given to the owner, and the labor or materials are furnished on a subcontract under the contract between the owner and the person contracting with the owner. The trial justice found that under the stated sections it is not necessary that the claimant knew of the bond or relied on it, nor that the surety received notice from the claimant. He concluded that it was the intention of the Legislature to establish a remedy contrary to the existing common law but in addition to and independent of chapter 28 of title 34 (Mechanics’ Lien Law) since under section 30, no notice of intention to claim a lien need be filed by the claimant to pursue his remedy thereunder.

Section 31 restates the law providing that a lien under §§34-28-1, 34-28-2 and 34-28-3 cannot attach to the property of a state or a municipality. However, it does preserve the remedy of §34-28-30 where the state or municipality is the owner of the land.

The defendants argue that plaintiff is not entitled to recover because it has not complied with §37-12-1 et seq., and §37-13-1 et seq., and particularly §37-13-13. The plaintiff, on the other hand, argues that because its remedy is provided by §§34-28-30 and 34-28-31 it is not required to comply with chapter 12 of title 37.

Where there are two repugnant statutory provisions, the provision which is most recent is to be preferred. Opinion to the Governor, 78 R. I. 144, 80 A.2d 165 (1951). Sections 34-28-30 and 34-28-31 are clearly later in time than chapter 12 of title 37. It is also true that repeals by implication are not favored and courts should attempt to construe two statutes that are in apparent conflict so that, if at all reasonably possible, both statutes may stand and be operative. State v. Bradshaw, 101 R. I. 233, 221 A.2d 815 (1966). Where a question arises as to whether

*345 one statute repeals an earlier one or is in conflict with it, the court should endeavor to determine the intention of the Legislature. Landers v. Reynolds, 92 R. I. 403, 169 A.2d 367 (1961), citing 82 C.J.S. Statutes §298 (b); see also Lederer Realty Corp. v. Hopkins, 71 A. 456 (R. I. 1908).

In some cases a supplier may be owed a very large sum and may desire that he be given prompt periodic payments on a regular basis. This could be accomplished by means of multiple notices at short periods under the provisions of chapter 12 of title 37. In other cases a supplier may be expecting few payments or only one payment for a number of small purchases which would not warrant sending multiple periodic notices for payment. In the latter situation or those similar to it, the supplier could rely on §§34-28-30 and 34-28-31. The provisions of the later sections protect the supplier against the sudden insolvency of the contractor or subcontractor while the provisions of chapter 12 of title 37 do not give such protection to the supplier. It is clear that the Legislature intended to give such protection to a supplier under the provisions of §§34-28-30 and 34-28-31.

The defendants rely on Worthington Air Conditioning Co. v. Lincoln & Lane Co., 106 R. I. 575, 261 A.2d 853 (1970), wherein this court stated that compliance with the provisions of §37-12-1 et seq. is a prerequisite to a suit on a labor and material payment bond. The record in Worthington, however, indicates that although the action was brought and decided after the enactment of §§34-28-30 and 34-28-31, it does not appear that the remedy provided by these sections was raised or argued. The only question for determination by that court was whether the remedy sought by the plaintiff was under the common law or under chapter 12 of title 37. Furthermore, a reading of the bond in the Worthington case shows that it provided for the incorporation by reference of the *346 conditions set forth in the contract to which the bond related. A condition of the Worthington contract required the contractor to furnish a bond that conformed to the various statutory requirements. Donatelli’s contract contains no such undertaking.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Air Distribution Corp. v. AIRPRO MECHANICAL CO.
973 A.2d 537 (Supreme Court of Rhode Island, 2009)
Such v. State
950 A.2d 1150 (Supreme Court of Rhode Island, 2008)
Horn v. Southern Union Co.
927 A.2d 292 (Supreme Court of Rhode Island, 2007)
McKenna v. Williams
874 A.2d 217 (Supreme Court of Rhode Island, 2005)
Rathbun v. Autozone, Inc.
361 F.3d 62 (First Circuit, 2004)
Shelter Harbor Fire District v. Vacca
835 A.2d 446 (Supreme Court of Rhode Island, 2003)
Extrusions Inc. v. National Grange Mutual Insurance
824 A.2d 439 (Supreme Court of Rhode Island, 2003)
Bethlehem Rebar Industries, Inc. v. Fidelity & Deposit Co. of Maryland
582 A.2d 442 (Supreme Court of Rhode Island, 1990)
Atlantic States Cast Iron Pipe Co. v. Forte Bros., Inc.
474 A.2d 1250 (Supreme Court of Rhode Island, 1984)
State ex rel. Thompson v. DeNardo
448 A.2d 739 (Supreme Court of Rhode Island, 1982)
Providence Electric Co., Inc. v. Diso Corp.
440 A.2d 751 (Supreme Court of Rhode Island, 1981)
Vaudreuil v. Nelson Engineering & Construction Co.
399 A.2d 1220 (Supreme Court of Rhode Island, 1979)
Vaudreuil v. NELSON ENGINEERING AND COSTRUCTION CO., INC.
399 A.2d 1220 (Supreme Court of Rhode Island, 1979)
Berthiaume v. SCHOOL COM. OF CITY OF WOONSOCKET
397 A.2d 889 (Supreme Court of Rhode Island, 1979)
Randall Engineering Corp. v. East Ray Associates, Inc.
119 R.I. 942 (Supreme Court of Rhode Island, 1978)
Estate of Eglee
383 A.2d 586 (Supreme Court of Rhode Island, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
356 A.2d 483, 116 R.I. 340, 1976 R.I. LEXIS 1283, Counsel Stack Legal Research, https://law.counselstack.com/opinion/providence-elec-co-inc-v-donatelli-bldg-co-inc-ri-1976.