Aikin v. WCI Communities, Inc.

26 So. 3d 691, 2010 Fla. App. LEXIS 902, 2010 WL 366584
CourtDistrict Court of Appeal of Florida
DecidedFebruary 3, 2010
Docket2D07-5721
StatusPublished
Cited by4 cases

This text of 26 So. 3d 691 (Aikin v. WCI Communities, Inc.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aikin v. WCI Communities, Inc., 26 So. 3d 691, 2010 Fla. App. LEXIS 902, 2010 WL 366584 (Fla. Ct. App. 2010).

Opinion

SILBERMAN, Judge.

Jan Aikin appeals a final summary judgment entered against her in the lawsuit she filed seeking declaratory relief and rescission of the residential purchase con *693 tract she entered into with WCI Communities, Inc. (WCI). In her complaint, Ms. Aikin sought rescission of the contract based on WCI’s alleged failure to comply with the reporting and registration requirements of the Interstate Land Sales Full Disclosure Act, 15 U.S.C. §§ 1701-20 (2005) (the Act). The circuit court concluded that WCI was exempt from the registration and disclosure requirements of the Act because the contract contained a binding obligation for WCI to construct Ms. Aikin’s condominium unit within two years from the date she signed the contract. We affirm.

BACKGROUND

On September 30, 2005, Jim and Jan Aikin executed a contract with WCI in which they agreed to purchase a condominium unit from WCI in the Westshore Yacht Club Townhomes II. 1 The contract required WCI to complete construction within two years of the date of signing as follows:

D. The Unit, as configured in Seller’s plans and specifications for the Unit and the Condominium, shall be completed not later than two (2) years from the date Purchaser signs this Contract. However, the date for completion may be extended by reason of delays incurred by circumstances beyond Seller’s control, such as acts of God, or any other grounds cognizable in Florida contract law as impossibility or frustration of performance, including, without limitation, delays occasioned by rain, wind and lightning storms. It is the intention of the parties that this sale qualify for the exemption provided by 15 U.S.C. Section 1702(a)(2), and nothing herein contained shall be construed or operate so as to any obligations of Seller or rights of Purchaser in a manner which would render said exception inapplicable.

WCI completed construction of the unit within two years as required. On March 1, 2007, it notified Ms. Aikin that she could close on the unit. On March 12, 2007, Ms. Aikin sent notice to WCI through her attorney that she was revoking and terminating the contract because WCI had failed to comply with the reporting and registration requirements of the Act. 2 WCI disputed that Ms. Aikin was entitled to rescind the contract.

THE CIRCUIT COURT LITIGATION

On May 21, 2007, Ms. Aikin filed a declaratory judgment action. In count I, she sought a declaration as to whether the contract imposed “an unqualified and unconditional guarantee on WCI to complete the Unit within two years,” as required by 15 U.S.C. § 1702(a)(2). She asserted that the transaction was not exempt under 15 U.S.C. § 1702(a)(2) from the Act’s reporting and registration requirements because the contract did not unconditionally require WCI to complete construction of the unit within two years. In count II, Ms. Aikin sought to rescind the contract based on WCI’s failure to comply with the Act’s reporting and registration requirements. In connection with the rescission claims, Ms. Aikin asked for the return of her *694 deposits plus interest, costs, and attorney’s fees.

WCI filed a motion for summary judgment, stating that there were no disputed issues of material fact. WCI argued that it was exempt from the Act’s registration and disclosure requirements because the contract required it to unconditionally complete construction of the unit within two years. Ms. Aikin responded to WCI’s motion and filed a cross-motion for summary judgment. She agreed that there were no disputed issues of fact but maintained that the contract did not unconditionally require completion of the unit within two years. She asserted that the contract was not exempt from the Act’s registration and disclosure requirements for several reasons.

First, she claimed that the force maj-eure language under section 3.D. of the contract, which permitted WCI to éxceed the two-year construction obligation under a number of circumstances, made the requirement that WCI complete the unit within two years conditional. Second, she argued that section 7.C. of the contract, which required her to give WCI twenty days’ notice of default and an opportunity to cure, provided WCI with the ability to extend the completion date beyond two years. Third, she contended that the two-year construction obligation was not unconditional because the contract placed limits on her remedies for breach of contract by WCI. Finally, she asserted that section 10 of the contract, which permitted WCI to unilatei'ally terminate the contract if it did not sell at least 65% of the units in the building within 180 days from the date the first purchaser signed a contract, effectively permitted WCI to breach the contract without consequence and limited her damages to a refund of her deposits plus interest.

Following a hearing, the circuit court ruled that the contract unconditionally obligated WCI to build the condominium unit within two years. The court first concluded that it need not determine the impact of the force majeure clause because under the savings clause in section 3.D. of the contract, ‘WCI forewent the opportunity to be protected by that defense.” Second, the circuit court determined that the default and remedies provision under section 7.C. of the contract did not render the two-year construction obligation illusory. It reasoned that section 7.C. “must be read so as to entitle WCI to 20 days’ notice of default, provided that the receipt of that notice does not extend the time for construction beyond two years, and thereby render the exemption to [the Act] inapplicable.” The court did not specifically address Ms. Aikin’s arguments with respect to the limitations on remedies and section 10, which allowed WCI to terminate the contract if it did not meet certain pre-sale requirements.

The circuit court summarized that “WCI was not required to comply with the registration and disclosure requirements of [the Act] because the Contract contained a binding obligation to construct the Unit within two years.” It granted final summary judgment in WCI’s favor and reserved jurisdiction as to WCI’s fees and costs. On appeal, Ms. Aikin raises the same arguments against the exemption.

ANALYSIS

1. The Force Majeure Language

The Act “is an anti-fraud statute that uses disclosure as its primary tool to protect purchasers from unscrupulous sales of undeveloped home sites.” Maguire v. S. Homes of Palm Beach, LLC, 591 F.Supp.2d 1263, 1267 (S.D.Fla.2008) (citing Winter v. Hollingsworth Props., Inc., 777 F.2d 1444, 1447 (11th Cir.1985)). *695 The Act is applicable to the sale of condominium units. See Stein v. Paradigm Mirasol, LLC,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pohlman v. Aqua Condominium Developers, Ltd.
44 So. 3d 645 (District Court of Appeal of Florida, 2010)
Snavely Siesta Associates, LLC v. Senker
34 So. 3d 813 (District Court of Appeal of Florida, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
26 So. 3d 691, 2010 Fla. App. LEXIS 902, 2010 WL 366584, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aikin-v-wci-communities-inc-fladistctapp-2010.