Snavely Siesta Associates, LLC v. Senker

34 So. 3d 813, 2010 Fla. App. LEXIS 7033, 2010 WL 2010843
CourtDistrict Court of Appeal of Florida
DecidedMay 21, 2010
Docket2D08-5044
StatusPublished
Cited by4 cases

This text of 34 So. 3d 813 (Snavely Siesta Associates, LLC v. Senker) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Snavely Siesta Associates, LLC v. Senker, 34 So. 3d 813, 2010 Fla. App. LEXIS 7033, 2010 WL 2010843 (Fla. Ct. App. 2010).

Opinion

KELLY, Judge.

Snavely Siesta Associates, LLC, an Ohio real estate developer, appeals a partial final judgment in favor of Richard C. Senker, as Trustee of the Richard C. Senker and Patricia A. Senker Land Trust. The judgment rescinds a condominium purchase agreement and orders Snavely to return Senker’s deposits based on the trial court’s determination that Snavely violated the Interstate Land Sales Full Disclosure Act (the Act), 15 U.S.C. § 1701-20 (2005), when it failed to provide Senker with a property report before the purchase contract was signed. We conclude that the contract obligates Snavely to complete construction of the condominium within two years and therefore it is exempt from the requirements of the Act. See 15 U.S.C. § 1702(a)(2). Accordingly, we reverse the judgment in favor of Senker.

Senker contracted with Snavely to purchase a condominium at Summer Cove, a condominium project on Siesta Key in Sarasota. The contract contained a presale contingency provision allowing Snavely to terminate the agreement if it was unable to obtain purchase contracts for at least sixty percent of the units in the condominium within 180 days from the date the first purchaser signed a purchase agreement. The contract specified that time was of the essence and that the condominium would be completed in two years. It also contained a force majeure provision stating that “the date for completion may be extended by reason of delays incurred by the circumstances beyond the Seller’s control, such as acts of God, or any other grounds cognizable in Florida contract law as impossibility or frustration of performance, including without limitation, delays occasioned by rain, wind and lightning storms.”

Snavely built the condominium and, a little less than two years after entering into the contract with Senker, scheduled the closing and notified Senker of the closing date. In response, Senker notified Snavely that he was revoking the contract pursuant to section 718.503, Florida Statutes (2007), and he demanded a refund of his deposits. When Snavely declined, Senker sued. Ten months later, Senker amended his complaint to include a count for rescission pursuant to 15 U.S.C. § 1703(c) based on Snavely’s failure to provide a property report as required by 15 U.S.C. § 1703(a). Snavely claimed that it was exempt from the Act pursuant to 15 U.S.C. § 1702(a)(2), which in pertinent part provides that the Act shall not apply to “the sale or lease of any improved land *816 on which there is a residential, commercial, condominium, or industrial building, or the sale or lease of land under a contract obligating the seller or lessor to erect such a building thereon within a period of two years.” Senker moved for summary judgment on his claim for rescission arguing that Snavely was not exempt because its contractual obligation to complete construction within two years was rendered “illusory” by the force majeure provision and the presale contingency provision. The trial court agreed and granted Senker’s motion for summary judgment.

Section 1703(a) of the Act makes it unlawful to sell or lease “any lot not exempt under section 1702” unless the seller complies with the provisions of the Act, including the requirement that the purchaser receive a printed property report prior to signing the purchase contract. If the seller has violated the Act, section 1703(c) gives the buyer the right to rescind the contract. At issue here is whether Snavely was exempt from the Act’s requirements because its contract obligated it to complete Senker’s condominium within two years. Because the Act is a federal statute, the meaning of the term “obligating” is a matter of federal law. Stein v. Paradigm Mirasol, LLC, 586 F.3d 849 (11th Cir.2009), cert. denied, — U.S. —, 130 S.Ct. 1903, 176 L.Ed.2d 366 (2010). In Stein, the Eleventh Circuit considered the meaning of the term “obligating” and concluded that “the § 1702(a)(2) exemption applies when a contract imposes a legal duty on the developer to perform his promise to construct the condominium or other building within two years.” Id. at 854. Whether the contract imposes a legally enforceable obligation to complete construction within two years is a matter of Florida law. Id. Thus, we must examine the presale contingency provision and the force majeure clause to determine whether, under Florida law, they relieve Snavely of its legal obligation to complete Senker’s condominium within two years.

We turn first to the presale contingency provision that allowed Snavely to terminate the purchase agreement if it did not obtain purchase contracts for at least sixty percent of the units in the condominium within 180 days from the date the first purchaser signed a purchase agreement. As is evident from its plain language, the objective of section 1702(a) is to ensure the timely completion of the building the purchaser is buying. In the case of a condominium unit, section 1702(a) presupposes that the building where the unit is located will actually be built. It is unreasonable to interpret section 1702(a) to require a seller to enter into a contract that would obligate it to go forward with construction of a particular unit even where it has not sold enough units to move forward with the entire project. Conditioning the sale of a unit on the seller’s ability to successfully sell enough units to make the entire project financially viable does not relieve the seller of its distinct obligation to timely complete an individual buyer’s unit once that contingency is met and the sale of the unit is consummated.

Senker’s interpretation is also inconsistent with the regulations adopted by the Department of Housing and Urban Development (HUD). HUD regulations interpret section 1702(a)(2) of the Act as permitting inclusion of a “presale clause conditioning the sale of a unit on a certain percentage of sales of other units ... if [the presale clause] is legally binding on the parties and is for a period not to exceed 180 days.” 24 C.F.R. § 1710.5. Because HUD is the agency responsible for enforcement of the Act, its regulations are entitled to deference as an authoritative interpretation of the statute unless it appeal's from the statute or its legislative *817 history that the agency’s interpretation is not one that Congress would have sanctioned. S ee Chevron, U.S.A., Inc. v. Natural Res. Def. Council, Inc., 467 U.S. 887, 104 S.Ct. 2778, 81 L.Ed.2d 694 (1984). We see nothing in the language of the statute or its histoiy that convinces us that we should reject HUD’s interpretation. 1

We turn next to the force majeure provision. The purchase agreement signed by Senker includes language that “[t]he Unit ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Beaver v. Tarsadia Hotels
978 F. Supp. 2d 1124 (S.D. California, 2013)
State v. Joseph
94 So. 3d 672 (District Court of Appeal of Florida, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
34 So. 3d 813, 2010 Fla. App. LEXIS 7033, 2010 WL 2010843, Counsel Stack Legal Research, https://law.counselstack.com/opinion/snavely-siesta-associates-llc-v-senker-fladistctapp-2010.