Pohlman v. Aqua Condominium Developers, Ltd.

44 So. 3d 645, 2010 Fla. App. LEXIS 14005, 2010 WL 3655885
CourtDistrict Court of Appeal of Florida
DecidedSeptember 22, 2010
Docket1D09-5621
StatusPublished

This text of 44 So. 3d 645 (Pohlman v. Aqua Condominium Developers, Ltd.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pohlman v. Aqua Condominium Developers, Ltd., 44 So. 3d 645, 2010 Fla. App. LEXIS 14005, 2010 WL 3655885 (Fla. Ct. App. 2010).

Opinion

WOLF, J.

Appellants seek review of the trial court’s grant of appellee’s motion for summary judgment dismissing appellants’ rescission of contract claims. Appellants attempted to rescind a pre-development condominium sales contract alleging the contract violated the Interstate Land Sales Act (ILSA). The trial court determined the contract was exempt from the ILSA because the seller was obligated to complete its obligations under the contract within two years. We agree and align our court with the well-reasoned opinion in Aikin v. WCI Communities, 26 So.3d 691 (Fla. 2d DCA 2010), and declare express conflict with the decision in Plaza Court, L.P. v. Baker-Chaput, 17 So.3d 720 (Fla. 5th DCA 2009).

The ILSA is codified in 15 U.S.C. §§ 1702-1720 and was passed in the 1960’s to protect buyers of out-of-state parcels from scams, given the inability to inspect the pre-construction areas on site. 1 Among other things, the ILSA requires developers register with the United States Department of Housing and Urban Development (HUD) and furnish a “property report” to buyers before the signing of the agreement. See 15 U.S.C. §§ 1703, 1707 (2005). This report has lengthy disclosure requirements and is intended to insure the consumer is protected. 15 U.S.C. § 1707. In addition, the ILSA requires all sales contracts obligate the developer to complete all recreational amenities, roads, utilities, sewage services, water, etc., represented to be part of the project in advertisements. 15 U.S.C. § 1703.

However, the ILSA includes an exemption from these requirements in certain circumstances. The relevant exemption argued in the underlying case includes the following provision:

Unless the method of disposition is adopted for the purpose of evasion of this chapter, the provisions of this chapter shall not apply to—
[[Image here]]
*647 (2) the sale or lease of any improved land on which there is a residential, commercial, condominium, or industrial building, or the sale or lease of land under a contract obligating the seller or lessor to erect such a building thereon within a period of two years....

15 U.S.C. § 1702(a)(2).

Appellants assert the following contractual language creates an illusory obligation to complete the contract within two years, and thus, makes the contract ineligible for the ILSA exemption provided in 15 U.S.C. § 1702(a)(2):

Except as provided in the immediately following sentence, in no event shall the completion date of the Unit be later than two (2) years from the date Buyer executes this Contract. The date for completion may be extended by Seller by reasons of delays incurred by circumstances beyond Seller’s reasonable control, such as acts of God, war, civil unrest, imposition by a governmental authority of a moratorium upon construction of the Unit or the Condominium or the providing of utilities or services which are essential to such construction, casualty losses or material or labor shortages or any other grounds cognizable in Florida contract law as impossibility or frustration of performance, including, without limitation, delays occasioned by wind, rain, lightning and storms. It is the intention of the parties that this sale and purchase shall qualify for the exemption provided by the Interstate Land Sales Full Disclosure Act, 15 U.S.C. Section 1702(a)(2), and nothing contained in this Contract shall be construed or operate, as to any obligations of Seller or Buyer, in a manner which would render the exemption inapplicable.

Florida courts have grappled with the proper application of this ILSA exemption as far back as the 1980’s. In 1990, in Samara Development Corporation v. Marlow, 556 So.2d 1097 (Fla.1990), the supreme court considered whether a pre-development contract allowing for only specific performance or return of a deposit in the event of a breach was an illusory obligation to complete a contract within two years, thereby denying the builder the ILSA exemption. The court found the limitation on remedies and failure to allow a suit for damages created an illusory requirement to complete the project within two years, and thus, made the contract ineligible for the ILSA exemption. Id. at 1101. See also Hardwick Prop., Inc. v. Newbern, 711 So.2d 35 (Fla. 1st DCA 1998) (citing and discussing Samara, and finding the contractual allowance for only “general” damages, equitable remedies, and/or return of the deposit in the event of a breach did not render the promise to complete the project within two years illusory and, thus, did not trigger the ILSA requirements).

In Samara and Hardwick, the courts focused on whether the obligation to complete within two years was an illusory obligation based on the ease with which the builder could escape the contractual obligation. Given this focus, appellants assert the disputed contractual provision rendered appellee’s obligation to perform the contract within two years illusory. On the contrary, appellee asserts the obligation to complete within two years was not illusory because the only excuse for nonperformance would have been an event which created an impossibility of performance as that term is recognized in Florida law. Generally, courts have found contractual provisions similar to the one in question here are not illusory, and thus, the ILSA exemption applies.

*648 In Mailloux v. Briella Townhomes, LLC, 3 So.3d 394, 395 (Fla. 4th DCA 2009), the Fourth District recently considered whether a purchase contract which “permitted delays associated with acts of God, impossibility of performance, and frustration of purpose” created an illusory obligation to complete the project within two years. In finding the obligation was not illusory, the court noted “[i]n Florida, acts of God, impossibility of performance, and frustration of purpose are well-recognized defenses to nonperformance of a contract.” Id. at 396 (citations omitted). Based on the foregoing, the court held that “well-recognized defenses to contractual nonperformance which are included in the contract at issue do not render [the] obligation to complete construction within two years illusory within the ILSA context.” Id.

Recently, in Aikin, 26 So.3d 691, the Second District considered all relevant federal and Florida law and upheld a similar provision as excluding the purchase contract from ILSA. In doing so, the Aikin

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stein v. Paradigm Mirasol, LLC
586 F.3d 849 (Eleventh Circuit, 2009)
Samara Development Corp. v. Marlow
556 So. 2d 1097 (Supreme Court of Florida, 1990)
Aikin v. WCI Communities, Inc.
26 So. 3d 691 (District Court of Appeal of Florida, 2010)
Home Devco/Tivoli Isles LLC v. Silver
26 So. 3d 718 (District Court of Appeal of Florida, 2010)
Plaza Court, L.P. v. Baker-Chaput
17 So. 3d 720 (District Court of Appeal of Florida, 2009)
Mailloux v. Briella Townhomes, LLC
3 So. 3d 394 (District Court of Appeal of Florida, 2009)
Jankus v. Edge Investors, L.P.
650 F. Supp. 2d 1248 (S.D. Florida, 2009)
Hardwick Properties, Inc. v. Newbern
711 So. 2d 35 (District Court of Appeal of Florida, 1998)
Harvey v. Lake Buena Vista Resort, LLC
568 F. Supp. 2d 1354 (M.D. Florida, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
44 So. 3d 645, 2010 Fla. App. LEXIS 14005, 2010 WL 3655885, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pohlman-v-aqua-condominium-developers-ltd-fladistctapp-2010.