Advent Trust Co. v. Hyder

12 S.W.3d 534, 2000 WL 4543
CourtCourt of Appeals of Texas
DecidedDecember 27, 1999
Docket04-98-00315-CV
StatusPublished
Cited by27 cases

This text of 12 S.W.3d 534 (Advent Trust Co. v. Hyder) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Advent Trust Co. v. Hyder, 12 S.W.3d 534, 2000 WL 4543 (Tex. Ct. App. 1999).

Opinions

OPINION

Opinion by

TOM RICKHOFF, Justice.

A, group of working interest owners in certain oil and gas leases sued the estate of a former operator of the leases, seeking to recover losses they incurred in prior litigation involving a farmout agreement. The jury returned a verdict in favor of the working interest owners for $4,261,000 in actual damages and $20,000 in punitive damages. We conclude that the limitations period for this suit commenced when the working interest owners were served with the petition in the prior litigation. Because this suit was commenced more than four years after that date, we reverse the judgment in favor of the working interest owners and render judgment that they take nothing.

Facts

In 1945, Noble Ginther and others entered into a joint operating agreement [537]*537(JOA), agreeing to cooperate in the development of oil and gas leases they owned in the Sarco Creek Field, located on the Carrie G. Wood Ranch in Goliad County. The operator and the working interest owners changed over the years. For purposes of this appeal, the relevant working interest owners were Noble Ginther, Conoco, and the Hyder-Rowan Group. Noble Ginther served as operator from 1972 until 1989.

The first oil well in the field was called Wood Well No. 1. It was originally completed to a depth between 4170 to 4180 feet. In 1961, the well was recompleted at 4050 feet. The well then produced from two formations (one formation at 4170-4180 feet and one formation at 4050 feet). It thus became a “dually completed” well. When the dual completion occurred, Gin-ther, Warren & Co. (GWC) was the operator under the JOA. The Ginther in GWC was Noble’s brother, Wilbur; Noble Gin-ther did not have a role in GWC. In 1988, another well, Wood Well No. 11, was dually completed.

In 1989, Conoco entered into a farmout agreement with CPX, Inc. On Noble Gin-ther’s recommendation, the other working interest owners entered into identical farmout agreements. The agreements granted CPX the right to drill one well. If this well was successfully completed, CPX would be assigned the working interest owners’ right to its production. The agreements provided that CPX could not produce from existing formations that were producing on adjacent leases. Pursuant to the farmout agreements, CPX drilled its single well, Whitlow Well No. 1, to a depth of 4050 feet and found that the formation was depleted.

In July 1989, CPX sued Ginther, Cono-co, and the Hyder-Rowan Group, asserting they failed to disclose that they had produced from the 4050-foot formation, that they represented that CPX could obtain the information it needed about their past and current production from records on file with the Texas Railroad Commission, and that, in fact, the proper filings had not been made with the Commission. CPX additionally filed an application with the Commission for a new field designation for Whitlow Well No. 1.

Also in July 1989, R.E. Keen, a petroleum engineer for Ginther, sent the working interest owners a letter on Noble Ginther’s letterhead, stating that a “misunderstanding” had arisen regarding the farmout agreements and that CPX was “wrongfully claiming” damages from the working interest owners. Summarizing CPX’s contentions, the letter stated, “Basically, CPX, Inc. is claiming we withheld information from them which is untrue.” Levy Goodrich, one of the working interest owners, testified that he was present at a meeting in which R.E. Keen and Noble Ginther stated that there were no “unfiled forms with the Railroad Commission and nothing was true about [CPX’s] allegations.”

In September 1989, Ginther died, and Keen replaced him as operator. In January 1992, CPX filed a complaint with the Railroad Commission, asserting that the working interest owners had violated Commission reporting requirements and had engaged in illegal, commingled production.

The Hyder-Rowans and Keen were aligned in the Railroad Commission proceedings, although they were represented by separate counsel. The central issues before the Commission were whether Wood Wells No. 1 and No. 11 were producing from two formations, and, if so, whether the dual completion of these wells and the production from them had been properly reported. The Hyder-Rowans and Keen argued that the dual completion report for Wood Well No. 1 may have been filed in 1961 and lost or returned to GWC by the Commission (apparently, pre-1966 Commission records regarding the Sarco Creek Field were in a state of disarray). Alternatively, they argued that a dual completion report did not have to be filed under the circumstances existing in the Sarco Creek Field.

[538]*538On August 12, 1992, Railroad Commission examiners issued a proposal for decision that rejected Keen’s and the Hyder-Rowans’ arguments. Largely adopting the examiners’ findings and conclusions, the Railroad Commission determined that the operators of the Sarco Creek Field violated Commission rules by failing to file a dual completion report for Wood Wells No. 1 and No. 11 and by failing to separately account for the production from two formations at these wells in periodic reports to the Commission, and that production from Wood Wells No. 1 and No. 11 had been commingled in violation of Commission rules. The Commission referred the matter to the Attorney General to assess administrative penalties. Ginther’s estate eventually paid a $10,000 penalty.

Following the Commission’s decision, all of the working interest owners settled with CPX. The Hyder-Rowans surrendered their interest in the Sarco Creek Field to CPX, and Conoco paid CPX $1.9 million. In a separate settlement, Ginther’s estate surrendered its interest in the field and also paid CPX $ 1.5 million.

On January 18, 1994, the Hyder-Row-ans instituted this suit against Ginther’s estate, seeking to recover the value of the surrendered interest in the field. At the time of trial, their live pleading included causes of action for negligence, negligent misrepresentation, fraud, breach of contract, and common-law indemnity. The Hyder-Rowans alleged that Ginther, as operator, was responsible for ensuring that required reports were filed with the Railroad Commission and that he negligently or fraudulently failed to file required dual-completion and production reports, thereby misrepresenting the nature and extent of gas in the Sarco Creek Field. In defense, Ginther’s estate argued that all the Hyder-Rowans’ claims were barred by limitations. The Hyder-Row-ans countered that the discovery rule, fraudulent concealment, and equitable es-toppel apply. In response to the discovery rule questions in the charge, the jury found that the Hyder-Rowans discovered their causes of action for negligence, negligent misrepresentation, fraud, and breach of contract on August 12, 1992, which was the day the Railroad Commission examiners issued their proposal for decision. The jury further found in favor of the Hyder-Rowans on all causes of action and awarded them $4,261,000 in actual damages and $20,000 in punitive damages. Advent Trust Company, successor independent executor of Ginther’s estate, appeals the judgment entered on this verdict.

Accrual of the Causes of Action

Generally, a cause of action accrues, and the limitations period begins running, when a wrongful act causes some legal injury, that is, an injury giving a cause of action by reason of its being an invasion of a right. See S.V. v. R.V., 933 S.W.2d 1, 4 (Tex.1996); Houston WaterWorks Co. v. Kennedy, 70 Tex.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United Healthcare Servs., Inc. v. First St. Hosp. LP
570 S.W.3d 323 (Court of Appeals of Texas, 2018)
in Re David Allan Edwards
Court of Appeals of Texas, 2015
Tipton v. Brock
431 S.W.3d 673 (Court of Appeals of Texas, 2014)
West v. Proctor
353 S.W.3d 558 (Court of Appeals of Texas, 2011)
Hunt Oil Co. v. LIVE OAK ENERGY, INC.
313 S.W.3d 384 (Court of Appeals of Texas, 2010)
in Re Ronnie J. Troglin, Jr.
Court of Appeals of Texas, 2009
Gambrinus Co. v. Galveston Beverage, Ltd.
264 S.W.3d 283 (Court of Appeals of Texas, 2008)
Quigley v. Bennett
256 S.W.3d 356 (Court of Appeals of Texas, 2008)
Smith International, Inc. v. Egle Group, LLC
490 F.3d 380 (Fifth Circuit, 2007)
Exxon Corporation v. Laurie T. Miesch
Court of Appeals of Texas, 2005
Sauceda v. Kerlin
164 S.W.3d 892 (Court of Appeals of Texas, 2005)
Sanders v. Construction Equity, Inc.
42 S.W.3d 364 (Court of Appeals of Texas, 2001)
Jackson v. West Telemarketing Corp. Outbound
245 F.3d 518 (Fifth Circuit, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
12 S.W.3d 534, 2000 WL 4543, Counsel Stack Legal Research, https://law.counselstack.com/opinion/advent-trust-co-v-hyder-texapp-1999.