Adams v. NVR Homes, Inc.

142 F. Supp. 2d 649, 2001 U.S. Dist. LEXIS 5414, 2001 WL 471917
District Court, D. Maryland·Decided April 27, 2001·No. CIV. H-99-846·Published·Cited by 8 cases

Opinion

MEMORANDUM AND ORDER

ALEXANDER HARVEY, II, Senior District Judge.

Pending in this case are two motions *651 filed by third-party defendant Gutschick. 1 Before the Court are Gutschick’s motion for clarification and reconsideration of the Court’s denial of Gutschick’s motion for summary judgment and also Gutschick’s motion in limine.

Memoranda and exhibits in support of and in opposition to these motions have been filed by the parties. Following its review of the pleadings, memoranda and exhibits, this Court has concluded that Gutschick’s motion in limine should be granted. As the result of the granting of this motion, competent evidence does not exist to support the third-party claims of Brantly Development and Nantucket. Accordingly, the Court will also grant Gut-schick’s motion for reconsideration and will enter summary judgment in favor of third-party defendant Gutschick as to both Count I and Count II of the amended third-party complaint.

The background facts pertaining to the third-party claims of Brantly Development and Nantucket were set forth in this Court’s Memorandum and Order of March 22, 2001 and will not be repeated here. (Slip op. at 73-74). In denying Gutschick’s motion for summary judgment, this Court concluded that Gutschick had not met its burden of showing that there is an absence of evidence to support the claims of Brantly Development and Nantucket. (Id. at 78). The Court viewed the facts presented to it in the summary judgment papers and all reasonable inferences to be drawn therefrom in a light most favorable to Brantly Development and Nantucket and concluded that there were disputed issues of material fact which indicated that Gut-schick might be liable under the claims of negligence and breach of contract asserted against it in the amended third-patty complaint. Id. The Court noted that the third-party plaintiffs were not at the summary judgment stage of the case required to specifically identify expert testimony establishing that Gutschick had breached the applicable standard of care. (Id. at 79).

The inquiry to be made by the Court at this later time is quite different. A pretrial conference has now been held, and a Pretrial Order entered. In that Order, the third-party plaintiffs have listed only Raymond A. DeStephen as the sole expert to be called by them at the trial. In its motion in limine, Gutschick argues that the expert testimony of DeStephen to be offered in support of the third-party claims of Brantly Development and Nantucket should be excluded on grounds (1) that third-party plaintiffs’ sole expert was not timely identified before the close of discovery, and (2) that DeStephen is not a civil engineer and is therefore not qualified to render an opinion under Rule 702, F.R.E., concerning the standard of care applicable to the conduct of a civil engineering firm like Gutschick.

On February 17, 2000, this Court entered a Scheduling Order which required that defendants’ Rule 26(a)(2) expert disclosures (including those of defendants Brantly Development and Nantucket) be made on or before August 17, 2000. This deadline was later extended until September 15, 2000. On September 7, 2000, this Court entered a Revised Scheduling Order which required that depositions and all other discovery be completed by December 29, 2000.

On December 7, 2000, Brantly Development and Nantucket mailed their responses to Gutschick’s interrogatories. Their response to Interrogatory No. 11 indicated *652 that they intended to rely upon plaintiffs’ documents and contentions in support of the claim made in their amended third-party complaint that work performed by Gutschick at Calvert Ridge was defective. In response to Interrogatory No. 6, the third-party plaintiffs stated that they had not yet identified experts whom they expected to call at the trial. This statement was made in spite of the fact that it had been some three months since the deadline for expert disclosures had expired, and more than five months after plaintiffs had made available to other parties the Rule 26(a)(2) expert report of DeStephen.

On December 12, 2000, counsel for Gut-schick attended the deposition of DeStephen. Counsel for Brantly Development and Nantucket did not attend that deposition. Counsel for Gutschick asked DeStephen only a few questions, including the following:

Q. You don’t have any opinions as to the role of Gutschick, Little & Weber in this case, do you?
A. No.

Relying on this response and on the fact that DeStephen had not been identified as an expert witness by Brantly Development and Nantucket, counsel for Gutschick did not continue to question DeStephen and did not inquire into the basis for any opinion which he might present at the trial indicating that Gutschick breached the applicable professional standard of care.

On January 15, 2001, Gutschick filed its motion for summary judgment. In its motion, Gutschick argued, inter alia, that the third-party claims of Brantly Development and Nantucket should be dismissed because they had failed to offer or identify any expert testimony in support of their claim that Gutschick had breached its professional standard of care. On February 1, 2001, Brantly Development and Nantucket filed their opposition to Gutschick’s motion for summary judgment. For the first time, they indicated that they would be relying on DeStephen’s expert testimony in opposing the entry of summary judgment in favor of Gutschick. The Pretrial Order confirms that Brantly Development and Nantucket will be relying on DeStephen as the only expert to be presented by them in support of their third-party claims. 2

On the record here, this Court concludes that Brantly Development and Nantucket must be precluded from relying upon the expert testimony of DeStephen at the trial because they have failed to meet the deadlines, set by the Court for the identification of experts and for the completion of discovery. Under the circumstances here, Gutschick would be severely prejudiced if the third-party plaintiffs were now permitted to present DeStephen’s testimony at the trial. DeStephen was not identified as an expert to be called by Brantly Development and Nantucket until after the close of discovery. Counsel for Gutschick therefore did not have an opportunity to examine him at his deposition and test the opinions that he would be giving at the trial in support of the third-party claims asserted against Gutschick. Since counsel for Brantly Development and Nantucket was not present at DeStephen’s deposition, and since this expert witness had stated that he had no opinion as to the role of Gutschick in the case, counsel for Gut-schick were fully justified in declining to examine him further at his deposition. As indicated by his deposition testimony, *653 DeStephen did not analyze or comment on the specific services rendered by Gutshick pursuant to its contracts with Brantly Development and Nantucket.

Free access — add to your briefcase to read the full text and ask questions with AI

Adams v. NVR Homes, Inc., 142 F. Supp. 2d 649, 2001 U.S. Dist. LEXIS 5414, 2001 WL 471917 (D. Md. 2001).

142 F. Supp. 2d 649 (Adams v. NVR Homes, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related