Adams v. Cosby

48 Ind. 153
CourtIndiana Supreme Court
DecidedNovember 15, 1874
StatusPublished
Cited by25 cases

This text of 48 Ind. 153 (Adams v. Cosby) is published on Counsel Stack Legal Research, covering Indiana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Adams v. Cosby, 48 Ind. 153 (Ind. 1874).

Opinion

Biddle, J.

Complaint by Cosby against Adams for materials furnished and work done in building a house.

Answer: 1. General denial; 2. Special contract; 3. Special contract, asking judgment against Cosby; 4. Payment; 5. Set-off.

Replies were filed, and issues of fact joined. No question is raised upon the pleadings; they need not, therefore, be more particularly stated.

A trial by jury was had, general verdict for plaintiff, and special findings:

1. That the materials were furnished and work done according to the special contract, and to the acceptance of Adams and the architect.

2. That the architect did not furnish a certificate of the tacts according to the special contract.

3. That Cosby never demanded such certificate from the architect.

Motion for new trial, causes filed, motion overruled, exception, appeal to the superior court in general term, judgment therein affirmed, and appeal to this court.

Various errors were assigned in the superior court in gen[155]*155eral term. The principal ones, and those which cover all the points raised, are, in brief, as follows:

1. The insufficiency oí the evidence to sustain the verdict.

4. Refusing to give proper instructions.

5. Giving improper instructions.

6. Admitting improper evidence.

7. Excluding proper evidence.

8. Refusing judgment on special findings.

9. Overruling motion for a new trial.

The proper error was assigned in this court raising the-above questions.

The appellant seems to have considered the case as if it was founded on the special contract and governed by the old rule, -which required a party to a special contract, while it remained executory, to seek his remedy under it and according to its specific terms, and which denied recovery as to part unless all had been performed. In this view he would have been sustained by the following cases: Cranmer v. Graham, 1 Blackf. 406; Hoagland v. Moore, 2 Blackf. 167; and De Camp v. Stevens, 4 Blackf. 24.

But in the case of Lomax v. Bailey, 7 Blackf. 599, the opinion in which was pronounced by Judge Dewey, the wisdom of the rule is doubted, and its rigor somewhat relaxed. In the case of McKinney v. Springer, 3 Ind. 59, and the case-of Epperly v. Bailey, 3 Ind. 72, the old rule, it may be said,, was abrogated. In McClure v. Secrist, 5 Ind. 31, the modern rule, that where one has entered into a special contract to perform work for another, and has done work, but not in the time or manner stipulated by the agreement, still, if the work done is accepted and used by the other party, the latter is answerable to the amount whereby he is benefited, upon an implied promise to pay for the value he has received,” may be regarded as having been settled. The benefit received by the party who is liable on the implied contract in such cases, must be over and above the damages he has sustained on account of the breach of the special contract by the other party. The old rule was strict, technical, and often unjust to one party; the-[156]*156modern rule is liberal, practicable, and never unjust to either party. The principle of the modern rule must be regarded as fully established in this State. For its support, see Ricks v. Yates, 5 Ind. 115; Wheatly v. Miscal, 5 Ind. 142; Persons v. McKibben, 5 Ind. 261; Kerstetter v. Raymond, 10 Ind. 199; Wolcott v. Yeager, 11 Ind. 84; Boyle v. Guysinger, 12 Ind. 273; and Garver v. Daubenspeck, 22 Ind. 238.

Upon this view, and the basis of this case, it is easy to perceive that the third instruction, which was asked for by the •appellant, and which was to the effect that the appellee could not recover except according to the terms of the special contract, was inapplicable, and, therefore, properly refused by the court.

The instructions given to the jury by the court, on its own motion, were as follows:

“1. In this case, if you believe from the evidence that the ■contract for the building of the house named was entered into between Mr. Cosby, the plaintiff, and Mr. Adams, the defendant, and that the same was completed according to the contract, and the certificate of the architect mentioned was obtained, waived, or unreasonably refused, your verdict will be made up by allowing the price of the house, and the value of the extra work done at the defendant’s request, if any was done, added together, deducting therefrom payments made by Adams, and offsets proved, added to the payments, and if the balance is in favor of the plaintiff, you will find in his favor for such balance, but if the balance is in favor of the defendant, you will find for him the amount of such balance.

2. But if you believe the plaintiff entered upon the erection of said house mentioned in the previous instruction, under the contract mentioned therein, and failed to complete it according to the contract, but the defendant nevertheless took possession of the house as left by the plaintiff, and occupied, and still occupies it, with his family, enjoying the benefits of the work done and materials furnished by the plaintiff, thus accepting them, then the plaintiff is entitled to recover the contract price of the house, less the cost of completing the [157]*157house according to the contract, and any special damages the defendant has proved himself to have sustained necessarily from the failure of the plaintiff to complete the house according to the contract, as the loss of rent, etc.; and in this state of facts, if it exists, you will deduct from the contract price of the house the cost of finishing it according to the contract and any special damages the plaintiff is shown to have sustained, as loss of rent, etc., on account of the failure to complete, and allow the plaintiff that sum, to which you will add the price as proved of the extra work, if any is proved to have been . done, and from the aggregate of these two sums you will deduct payments made and set-offs proved by the defendant,, Adams, and if they leave a balance in favor of Cosby, the plaintiff, that will be your verdict in his favor, but if the balance is in favor of Adams, the defendant, that balance will be your verdict in his favor.”

These instructions express the law which governs the case, and were properly given to the jury.

We find no question of evidence properly saved in the-record. There is an attempt to take exception to the introduction of evidence in these words:

“ Defendant objects to evidence showing the style of finish; court overrules objection, and permits evidence to show it is not finished or built of unusual material; excepted to.”

This does not show us what kind of evidence was offered,, nor the ground of the objection to it. We must therefore presume that the court properly refused its admission.

Again:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Western Wheeled Scraper Co. v. Scott Construction Co.
27 N.E.2d 879 (Indiana Supreme Court, 1940)
Bunn v. Crawford
133 N.E. 520 (Indiana Court of Appeals, 1922)
Cullen-Friestedt Co. v. Turley
97 N.E. 946 (Indiana Court of Appeals, 1912)
Jackson v. Creek
94 N.E. 416 (Indiana Court of Appeals, 1911)
Indianapolis Traction & Terminal Co. v. Springer
93 N.E. 707 (Indiana Court of Appeals, 1911)
Board of Commissioners v. Gibson
63 N.E. 982 (Indiana Supreme Court, 1902)
French v. Cunningham
49 N.E. 797 (Indiana Supreme Court, 1898)
Shepard v. Goben
39 N.E. 506 (Indiana Supreme Court, 1895)
Muncie Street Railway Co. v. Maynard
32 N.E. 343 (Indiana Court of Appeals, 1892)
Huntsvile Belt Line & Monte Sano Railway Co. v. Corpening & Co.
97 Ala. 681 (Supreme Court of Alabama, 1892)
Gastlin v. Weeks
28 N.E. 331 (Indiana Court of Appeals, 1891)
Everroad v. Schwartzkopf
23 N.E. 969 (Indiana Supreme Court, 1890)
Seavey v. Walker
9 N.E. 347 (Indiana Supreme Court, 1886)
Higham v. Vanosdol
101 Ind. 160 (Indiana Supreme Court, 1885)
Chambers v. Chambers
78 Ind. 400 (Indiana Supreme Court, 1881)
Vail v. Meyer
71 Ind. 159 (Indiana Supreme Court, 1880)
Rhodes v. Matthews
67 Ind. 131 (Indiana Supreme Court, 1879)
Grand Rapids & Indiana R. R. v. Boyd
65 Ind. 526 (Indiana Supreme Court, 1879)
Branham v. Johnson
62 Ind. 259 (Indiana Supreme Court, 1878)
Wiley v. Bradley
60 Ind. 62 (Indiana Supreme Court, 1877)

Cite This Page — Counsel Stack

Bluebook (online)
48 Ind. 153, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adams-v-cosby-ind-1874.