Western Wheeled Scraper Co. v. Scott Construction Co.

27 N.E.2d 879, 217 Ind. 408, 1940 Ind. LEXIS 191
CourtIndiana Supreme Court
DecidedJune 10, 1940
DocketNo. 27,366.
StatusPublished
Cited by4 cases

This text of 27 N.E.2d 879 (Western Wheeled Scraper Co. v. Scott Construction Co.) is published on Counsel Stack Legal Research, covering Indiana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Wheeled Scraper Co. v. Scott Construction Co., 27 N.E.2d 879, 217 Ind. 408, 1940 Ind. LEXIS 191 (Ind. 1940).

Opinion

Fansler, J.

The Scott Construction Company contracted with the State Highway Commission to build a certain paved highway. George W. Gist contracted with the Scott'Construction Company to make certain cuts and fills and bring the base for such work to the grade required in the plans and specifications. The Scott Construction Company agreed, “in consideration of the full performance of the work,” to pay George W. Gist at the rate of 45 cents per cubic yard for all material, except special borrow, moved in preparing, the grade, the material to be measured according to the provisions of the contract between the Scott Construction Company and the State Highway Commission, and to pay for all special borrow at the rate of 35 cents per cubic yard. The contract between the Scott Construction Company and the State Highway Commission provided that where rock was moved it should be computed at three times the price of earth removed. Gist was to be paid monthly a sum equal to 90 per cent, of the estimate of the engineer of the State Highway Commission of the quantity of material moved according to the provisions of the principal contract. It was agreed that Gist would not remove any equipment supplied by him during the work until the contract was fully performed, and that in the event he failed to make progress in the prosecution of the work, so that delays resulted in other work upon the job, the Scott Construction Company should have the right to hire additional labor and equipment and take over his equipment and operate the same and complete the contract and charge the cost to Gist.

*412 Gist began work under the contract and was paid 90 per cent, of the engineer’s estimates as the work progressed, and it is claimed that he finished the grade according to the contract. The Scott Construction Company completed its pavement upon the grade, and finished its contract with the state. After the work was completed there was litigation between the Scott Construction Company and the State Highway Commission. This controversy concerned the amount of excavation that should be paid for as rock rather than earth. In this litigation the Scott Construction Company recovered a judgment, increasing the amount payable because of rock excavation by many thousands of dollars. Much of this excavating was done by Gist under his contract, and, by reason of the judgment, the amount due under Gist’s contract was increased by approximately $30,000. While this litigation was progressing, Gist assigned his contract and his rights thereunder to the appellant, and the contract and the rights of the Scott Construction Company were assigned to various appellees.

The appellant brought this action against the appellees and the State Highway Commission to obtain a judgment against the principal contractor for the balance due under Gist’s subcontract, and to enforce a lien upon the balance due the principal contractor. The State Highway Commission paid the money involved into court and interpleaded certain creditors of the principal contractor, who were claiming liens upon the proceeds of the judgment and who are appellees. In the complaint the facts are alleged concerning the contracts above referred to. It is alleged that Gist performed all of his obligations under the contract; that there remained due the sum of at least $22,500. There were answers, which we need not notice now, a trial *413 by the court, special findings of fact and conclusions of law, and judgment against the plaintiff (appellant).

On the 9th day of June, 1925, a claim under the Gist contract was filed with the State Highway Commission for the purpose of fixing a lien upon the money due the Scott Construction Company. This was more than sixty days after Gist had stopped work, but before work was completed by the Scott Construction Company. Chapter 173 of the Acts of 1911 (Acts 1911, p. 437) was amended by chapter 44 of the Acts of 1925 (Acts 1925, p. 129, § 53-201, Burns’ 1933, § 14084, Baldwin’s 1934), in such a manner as to require subcontractors to file claims within sixty days after their work is completed in order to acquire a lien. The act provides for the filing of the claim “within sixty days after the passage of this act or within sixty days from the last labor performed . . .” The act was passed by the House on February 6th and by the Senate on February 20th, was approved by the Governor on March 2nd, and went into effect as a law on April 25, 1925. It will be seen that the claim was filed within sixty days after the act went into effect, but it was not filed within sixty days after the act was passed by the two branches of the General Assembly and signed by the Governor. There is a contention that it was not filed in time, and that therefore there is no lien. The question is, was the claim filed within sixty days after the passage of the act? Statutes are not effective as law until published, circulated, and proclaimed by the Governor, except in cases where there is an emergency clause, and there is none in the act involved here. If the word “passage,” as used in the act, were to be construed in the narrow sense, as meaning passage by the House and Senate, it would mean that the sixty days within which a claim might *414 be filed would start to run on February 20th, and would have expired before the act was published and became effective. In other words, the act would have the effect of destroying a pre-existing right to a lien before it became effective as a law. This cannot be, and it cannot reasonably be concluded that the Legislature had in mind any such anomalous situation. It must be concluded that the word “passage” was used in the broad sense, and that it was intended that claims might be filed within sixty days after the act became effective as a law. See People ex rel. Blachly v. Coffin et al. (1917), 279 Ill. 401, 117 N. E. 85. The claim was filed in time to entitle the claimant to a lien upon the fund.

The court’s finding No. 6 is as follows: “That said George W. Gist undertook the excavation and grading of that portion of said highway covered by his said contract dated October 6, 1923; that before the making of the assignment hereinbefore referred to, and on or about the 2nd day of October, 1924, said George W. Gist, without cause abandoned the performance of said contract, withdrew from the job, thereafter refused to complete said contract and failed to perform said contract substantially. Said Scott Construction Company thereupon completed the work that Gist had agreed to perform. Said Scott Construction Company is in no way and to no extent indebted to said George W. Gist, William D. Foulke, or Western Wheeled Scraper Company, plaintiff herein, because of work done or materials furnished in the construction of Federal Aid Project No. 60.” The sufficiency of the evidence to sustain this finding is questioned in a motion for a new trial. The solution of the question thus presented involves a construction of the basic substantial question in the case.

*415 It is contended that the appellant sued upon the entire indivisible contract, alleging full performance; that the contract is by its terms entire and indivisible; and that a failure to complete the contract in its entirety according to its terms precludes any recovery under the contract. The trial court must have adopted this' view, since, otherwise, the finding in question is not sustained.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blade Corp. v. American Drywall, Inc.
400 N.E.2d 1183 (Indiana Court of Appeals, 1980)
Taylor v. Altgelt
67 N.E.2d 531 (Indiana Supreme Court, 1946)
Colberg v. Sebastian
46 N.E.2d 716 (Indiana Court of Appeals, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
27 N.E.2d 879, 217 Ind. 408, 1940 Ind. LEXIS 191, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-wheeled-scraper-co-v-scott-construction-co-ind-1940.