Accokeek, Mattawoman, Piscataway Creeks Communities Council, Inc. v. Maryland Public Service Commission

133 A.3d 1228, 227 Md. App. 265, 2016 Md. App. LEXIS 32
CourtCourt of Special Appeals of Maryland
DecidedMarch 30, 2016
Docket2437/14
StatusPublished
Cited by14 cases

This text of 133 A.3d 1228 (Accokeek, Mattawoman, Piscataway Creeks Communities Council, Inc. v. Maryland Public Service Commission) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Accokeek, Mattawoman, Piscataway Creeks Communities Council, Inc. v. Maryland Public Service Commission, 133 A.3d 1228, 227 Md. App. 265, 2016 Md. App. LEXIS 32 (Md. Ct. App. 2016).

Opinion

ARTHUR, J.

Pursuant to Md.Code (1998, 2010 RepLVol., 2014 Supp.), §§ 7-207 and 7-208 of the Public Utilities Article (“PUA”), the Maryland Public Service Commission authorized Dominion Cove Point LNG, LP (“Dominion”), to construct an electric generating station to power a natural gas liquefaction facility. The Circuit Court for Baltimore City affirmed the decision after Accokeek, Mattawoman, Piscataway Creeks Communities Council, Inc., a nonprofit environmental advocacy organization, petitioned for judicial review. On appeal, we affirm.

Factual and Procedural Background

A. The Dominion Cove Point Liquefíed Natural Gas Terminal

Dominion owns and operates a natural gas import terminal on the western shore of the Chesapeake Bay near Cove Point in Calvert County. 1 The Cove Point terminal receives imported liquefied natural gas (LNG) from ocean-going tankers, vaporizes the LNG, and transports the gas by pipeline to an interstate transmission grid for consumption.

*272 In 2011, Dominion announced plans to convert the Cove Point site from an import-only terminal to a bi-directional terminal. Proposed liquefaction facilities, covering approximately 49 acres, would liquefy natural gas from domestic sources, so that it could be stored in canisters, loaded onto vessels, and exported abroad. Dominion sought approval from the Federal Energy Regulatory Commission to construct the liquefaction facilities and approval from the federal Department of Energy to export LNG to foreign countries.

As a major component of the project, Dominion planned to install combustion turbines to mechanically drive the refrigerant compressors used in the liquefaction process. 2 Dominion proposed a design that would repurpose waste heat from those turbines to generate much of the electricity required for the liquefaction process. This design called for the construction of an electricity generation station, closely integrated into the larger liquefaction facilities. The generating station, with a “name-plate capacity” of 130 megawatts, 3 would not be linked to the larger power grid, as the generated electricity would be consumed exclusively on site.

B. Application for Certifícate of Public Convenience and Necessity

At the same time that Dominion was pursuing federal approval for the liquefaction project, Dominion applied to state *273 authorities for permission to construct the generating station. Under Maryland law, a party may not begin construction on a generating station unless that party obtains a certifícate of public convenience and necessity from the Public Service Commission. PUA § 7-207(b)(l)(i). “The certificate may be granted only after other state agencies evaluate and comment upon the proposal, the [Commission] holds a public hearing which local governing bodies may attend,” and the Commission considers the recommendation of the local governing body and various societal effects of the generating station. See Potomac Elec. Power Co. v. Montgomery Cnty., 80 Md.App. 107, 114, 560 A.2d 50 (1989), aff'd sub nom. Howard Cnty. v. Potomac Elec. Power Co., 319 Md. 511, 573 A.2d 821 (1990). For certain generating stations, the party must apply for the certificate at least two years before beginning construction. PUA § 7-208(c)(1).

On April 1, 2013, Dominion submitted an Application for Certificate of Public Convenience and Necessity. Dominion requested expedited treatment so that it could begin construction before February 2014.

The Commission initially delegated the matter to a public utility law judge, who set a procedural schedule. Multiple parties intervened, including two environmental organizations: the Sierra Club and Chesapeake Climate Action Network (CCAN). The Commission later rescinded its delegation of the proceedings and set the matter for hearing by an en banc panel of commissioners.

In December 2013, Accokeek, Mattawoman, Piscataway Creeks Communities Council, Inc. (AMP), moved to intervene out-of-time. AMP, whose primary mission is to protect local waterways, asserted that the Sierra Club and CCAN, as national and regional environmental groups, would not adequately represent its interests in the proceedings. Over Dominion’s objection, the Commission granted AMP’s intervention request.

Through the Power Plant Siting and Research Act of 1971 and its subsequent revisions, the General Assembly has estab *274 lished a comprehensive process for evaluating the effects of proposed power generation facilities on surrounding communities. In accordance with the siting law, the Commission solicited a review from Maryland’s Power Plant Research Program (PPRP). PPRP, a division of the Department of Natural Resources, is a “continuing research program for electric power plant site evaluation and related environmental and land use considerations.” Md.Code (1974, 2012 Repl.Vol.), § 3-301(d) of the Natural Resources Article (“NR”). In coordination with other government agencies, PPRP studies the environmental and socioeconomic effects of electric power generation facilities in Maryland. NR § 3-303.

PPRP submitted an environmental review report on behalf of seven Maryland agencies. 4 PPRP concluded “that the power plant site [wa]s suitable and that the generating facility c[ould] be constructed and operated in accordance with all applicable environmental regulations,” provided that the Commission adopted an extensive list of conditions. First and foremost, PPRP recommended that the Commission require Dominion to obtain necessary federal approvals for the larger LNG facility before constructing the generating station. The majority of the proposed limitations related to air quality. The remaining requirements concerned terrestrial and aquatic ecology, stormwater management or erosion and sediment control, water supply, cultural resources, visual quality, emergency preparedness and security, traffic, and noise.

C. Evidentiary Hearing Before the Commission

The Commission received testimony and heard arguments at an evidentiary hearing on February 20, 21, and 24, 2014.

In support of its application, Dominion offered testimony from consultants and from company executives. Dominion asserted that the project would result in “significant economic *275 benefits in Maryland,” in the form of temporary jobs for construction of the facilities, permanent jobs for the operation of the facilities, and increased tax revenue for Calvert County. Dominion admitted that the export of LNG would put upward pressure on energy prices, but Dominion argued that benefits to the local economy would outweigh the potential adverse effects on consumers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
133 A.3d 1228, 227 Md. App. 265, 2016 Md. App. LEXIS 32, Counsel Stack Legal Research, https://law.counselstack.com/opinion/accokeek-mattawoman-piscataway-creeks-communities-council-inc-v-mdctspecapp-2016.