Baltimore Gas & Electric Co. v. Public Service Commission

540 A.2d 820, 75 Md. App. 87, 1988 Md. App. LEXIS 93
CourtCourt of Special Appeals of Maryland
DecidedMay 5, 1988
Docket1092, September Term, 1987
StatusPublished
Cited by11 cases

This text of 540 A.2d 820 (Baltimore Gas & Electric Co. v. Public Service Commission) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baltimore Gas & Electric Co. v. Public Service Commission, 540 A.2d 820, 75 Md. App. 87, 1988 Md. App. LEXIS 93 (Md. Ct. App. 1988).

Opinion

ALPERT, Judge.

This appeal by the Baltimore Gas & Electric Company (“BG & E” or “Company”) challenges Order No. 67557, dated December 2, 1986 of the Public Service Commission of Maryland (“PSC” or “Commission”) which, pursuant to the Annotated Code of Maryland, art. 78 § 54F, denied recovery to BG & E of 50% of a fuel adjustment request. The Circuit Court for Calvert County, the Hon. Perry G. Bowen, Jr. presiding, affirmed the decision in an Opinion *89 and Order dated July 15, 1987. BG & E then noted this appeal.

The essential facts are not in dispute. On October 1, 1985, BG & E filed an application with the Commission to adjust its electric fuel rate. The application was docketed as Case No. 8520 and by Order No. 67174, dated October 3, 1985, the Commission suspended the fuel rate, subject to refund, to become effective with BG & E’s November 1985 billings. Hearings were held before Chief Hearing Examiner Paul H. Harrington on November 1, December 5, and December 20, 1985. The Commission’s Staff (“Staff”) and the Office of the People’s Counsel (OPC) noted their appearances and participated in the hearings.

People’s Counsel raised an issue regarding an outage at the Calvert Cliffs No. 1 Generating Unit. A planned out of service period for repairs was extended for the two week period of August 14-28, 1985 when local overheating in the generator was noted while the unit was being returned to service. An investigation revealed that the problem was caused by two mechanic’s rags, measuring approximately 16" x 27" and 14" x 22", which were blocking the flow in the generator’s water cooling system, technically called the stator water cooling system. The rags were removed, and after a series of tests disclosed no performance-endangering damage, the unit was returned to service.

People’s Counsel argued that BG & E should be denied recovery of replacement power costs associated with that portion of the Calvert Cliffs outage extension caused by the rags’ blockage of the stator water cooling system. Specifically, OPC alleged that BG & E's failure to institute “item accountability” procedures was part of a pattern of lack of control of items in critical work areas. BG & E contended that it had instituted all reasonable, cost-effective precautionary measures, and that item accountability was inappropriate for the type of work performed on the stator water cooling system. The Commission’s Staff suggested that consideration of BG & E’s actions during the outage should be deferred until BG & E’s next fuel rate proceeding, at *90 which time BG & E would be required to provide more detailed information concerning the cost/benefit analysis the Commission must perform in such cases. .

On January 29, 1986, the Chief Hearing Examiner issued a Proposed Order in which he disposed of other issues not relevant to this appeal and retained jurisdiction over the Calvert Cliffs Unit No. 1 planned outage extension issue. No party appealed the Proposed Order, which became final by operation of law on March 1, 1986.

On March 3, 1986, the Company filed another application for a fuel rate change with the Commission. The Commission docketed that application as Case No. 8520-A. The unresolved planned outage extension issue was consolidated with the other matters to be heard in Case No. 8520-A. A second round of hearings was held on April 10, May 12, and May 27, 1986 before Chief Hearing Examiner Harrington.

Staff, as well as People’s Counsel, now argued that the Company should be denied recovery of the replacement power costs associated with the extension of the planned outage caused by obstruction of the stator water cooling system. They alleged management imprudence in the failure to implement an item accountability procedure at certain times and on certain portions of the stator water cooling system. BG & E reiterated its basic position that the Company was correct in not implementing item accountability on the entire or any part of the stator water cooling system.

On July 10, 1986, the Hearing Examiner issued a Proposed Order in the consolidated proceedings rejecting Staff’s and People’s Counsel’s contentions concerning item accountability and finding that BG & E had maintained the productive capacity of Calvert Cliffs Unit No. 1 at a reasonable level during the period under review in Case No. 8520.

On August 11, 1986, Staff and People’s Counsel noted appeals to the Commission, and on December 2, 1986, the Commission issued Order No. 67557. The Commission reit *91 erated its belief, as stated in former cases, that “it is axiomatic that no business can operate without the occurrence of human error.” Based upon the circumstances of the error in question, however, and more particularly the size and bulkiness of the two rags involved, the Commission did not view this incident as unavoidable human error. Rather, the Commission found “the workers’ carelessness so great as to call into question the Company’s procedures for instilling appropriate awareness, alertness and diligence among employees to prevent the inadvertent inclusion of foreign objects in critical and sensitive generating equipment.” Therefore, the Commission ordered BG & E to bear 50% of the replacement cost incurred as a result of the outage extension. The order of December 2 is the subject of this appeal.

Appellant BG & E raises four arguments for our consideration:

I. The Commission's decision conflicts with its own standard for making Section 54F(f)(4) productive capacity determinations and, therefore, is arbitrary and capricious.
II. The record does not contain substantial evidence to support a finding that the company failed to instill sufficient awareness, alertness and diligence among its employees to prevent the inadvertent inclusion of foreign objects into critical and sensitive generating equipment.
III. The Commission’s decision in Order No. 67557 exceeds its statutory authority.
IV. The opinion of the circuit court does not provide any reasons to affirm the Commission’s decision in Order No. 67557.

For reasons stated infra, we shall remand without affirmance or reversal. Md. Rule 1071.

*92 I. Article 78, § 54F(f)(4) 1

In this first assignment of error, BG & E argues that the Commission instituted a new per se rule for making § 54F determinations. BG & E contends that inasmuch as the Commission found that BG & E’s decision not to implement item accountability did not amount to imprudent management, the Commission’s imposition of 50% of the replacement costs on BG & E was arbitrary and capricious. The Commission and People’s Counsel, of course, argue that the Commission’s decision was consistent with its well-established interpretation of § 54F(f)(4).

The Public Service Commission Law provides, in pertinent part:

§ 54F. Fuel rate adjustments of electric companies.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Matter of Md. Off. of People's Counsel
Court of Special Appeals of Maryland, 2023
Maryland Office of People's Counsel v. Maryland Public Service Commission
130 A.3d 1061 (Court of Special Appeals of Maryland, 2016)
People's Counsel v. Public Serv. Comm'n
Court of Special Appeals of Maryland, 2016
Maryland State Board of Dental Examiners v. Tabb
22 A.3d 921 (Court of Special Appeals of Maryland, 2011)
Anselmo v. Mayor City Council of Rockville
7 A.3d 710 (Court of Special Appeals of Maryland, 2010)
Board of County Commissioners v. Southern Resources Management, Inc.
837 A.2d 1059 (Court of Special Appeals of Maryland, 2003)
Mehrling v. Nationwide Insurance
806 A.2d 662 (Court of Appeals of Maryland, 2002)
Sweeney v. Montgomery County
667 A.2d 922 (Court of Special Appeals of Maryland, 1995)
Potomac Electric Power Co. v. Montgomery County
560 A.2d 50 (Court of Special Appeals of Maryland, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
540 A.2d 820, 75 Md. App. 87, 1988 Md. App. LEXIS 93, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baltimore-gas-electric-co-v-public-service-commission-mdctspecapp-1988.