Accokeek, Mattawoman, Piscataway Creeks v. PSC

Court of Appeals of Maryland·Decided December 16, 2016·No. 26/16·Published

Opinion

ACCOKEEK, MATTAWOMAN, PISCATAWAY CREEKS COMMUNITY COUNCIL v. PUBLIC SERVICE COMMISSION (S.T. 2016, No. 26)

PSC granted a Certificate of Public Convenience and Necessity (CPCN) that authorized Dominion Cove Point LNG (Dominion) to build an electric generating station to support an expansion of its liquefied natural gas facility at Cove Point, in Calvert County. In deciding whether to grant the CPCN, PSC was required to consider the economic and environmental impact of the generating station on the State and county. The CPCN was subject to nearly 200 Conditions imposed by PSC designed to ameliorate adverse economic and environmental effects that may result from the construction and operation of the generating station. In a judicial review action, Accokeek claimed that (1) two of the Conditions, which required Dominion to make contributions to State programs designed to reduce greenhouse gas emissions and to assist low-income families in meeting utility bills, constituted an unauthorized tax, (2) the failure of PSC to specify the precise dollar value of the positive economic benefit to the State and county of the generating station deprived Accokeek of due process, and (3) there was insufficient evidence to support PSC’s findings regarding the positive economic benefit of the generating station. Affirming judgments of the Circuit Court for Baltimore City and the Court of Special Appeals, the Court of Appeals rejected Accokeek’s complaints and held that (1) the two conditions complained of were not in the nature of a tax but were regulatory measures within the authority of PSC to impose, (2) PSC make appropriate findings regarding economic benefit based on the record, and (3) the evidence was sufficient to support those findings.

Circuit Court for Baltimore City Case No. 24-C-14-003896/AA Argued 11/7/16

IN THE COURT OF APPEALS

OF MARYLAND

No. 26

September Term, 2016

ACCOKEEK, MATTAWOMAN,

PISCATAWAY CREEKS COMMUNITY COUNCIL, INC.

vs.

PUBLIC SERVICE COMMISSION OF MARYLAND, et al.

Barbera, C.J.

Greene

Adkins

McDonald

Watts

Getty, JJ.

Wilner, Alan M.,

(Senior Judge, Specially Assigned)

Opinion by Wilner, J.

Filed: December 16, 2016

Dominion Cove Point LNG, LP (Dominion) owns and operates a liquefied natural gas (LNG) terminal near Cove Point in Calvert County. As initially constructed, the terminal received LNG from tanker ships, stored it, and, upon a customer’s need, vaporized it and shipped it in gas form through a pipeline that connects the terminal to a local distribution company. That operation is ongoing. The terminal and its operation are subject to approval and regulation by the Federal Energy Regulatory Commission (FERC). See 15 U.S.C. §717b.

In April 2013, Dominion applied to FERC and the Maryland Public Service Commission (PSC) for authorization to expand the terminal into a “bi-directional” facility, so that it could both import and export LNG. Exporting would be a reverse process – Dominion would obtain the domestic product in gas form, liquefy it, and ship it abroad in its liquid form. PSC approval, through the grant of a Certificate of Public Convenience and Necessity (CPCN), was needed because, as part of the expansion Project, Dominion proposed to construct a 130-megawatt electric generating station to provide the electricity necessary for the expanded operation, and, under Md. Code, Public Utility Article (PUA), §§7-207 and 7-208, a CPCN from PSC was required for the construction of that station. Petitioner, Accokeek, Mattawoman, Piscataway Creeks Community Council, Inc. (hereafter AMP), a consortium dedicated to protecting local waterways, was allowed to intervene in the administrative proceeding in opposition to Dominion’s application.

After three days of hearings and consideration of several thousands of pages of testimony and documents, PSC entered an 83-page Order granting the CPCN, subject to approximately 200 Conditions included in a 64-page Appendix. Dissatisfied, AMP sought judicial review in the Circuit Court for Baltimore City, which affirmed the PSC Order. On AMP’s appeal, the Court of Special Appeals affirmed the Circuit Court judgment. Accokeek, Mattawoman & Piscataway v. PSC, 227 Md. App. 265, 133 A.3d 1228 (2016).

We granted certiorari to consider three issues raised by AMP:

(1) whether two of the Conditions imposed by PSC in its grant of the CPCN (Conditions J-3 and J-4) constitute taxes or mandatory payments that PSC had no authority to impose;

(2) whether PSC’s (alleged) failure to identify the value it assigned to positive economic value in favor of the CPCN prevented AMP from effectively challenging the PSC decision; and (3) whether PSC’s valuation of the economic benefit created by the generating station is not supported by substantial evidence in the record.

As did the two lower courts, we find no merit in these complaints and therefore shall affirm the judgment of the Court of Special Appeals.

BACKGROUND

The procedure to be followed by PSC in evaluating a CPCN application for construction of an electric generating station is set forth in PUA §§7-207(c) and (d). Those sections provide for notice to interested persons and a public hearing, and no one contends that those procedures were not followed in this case. Section 7-207(e) lists the factors that PSC must consider in determining whether to grant a CPCN. In relevant part, they are:

(1) the recommendation of the governing body of the county in which the station is to be located; and

(2) the effect of the station on:

(A) the stability and reliability of the electric system;

(B) economics;

(C) esthetics;

(D) historic sites;

(E) aviation safety;

(F) air and water pollution; and (G) availability of means for the timely disposal of waste produced by the generating station.

Evidence was presented on all of those factors, by Dominion, by the Maryland Power Plant Research Program (PPRP), a unit and coordinating body within the Department of Natural Resources, by the PSC Staff, by the Sierra Club, by AMP, and by others. AMP essentially argued that none of the considerations in §7-207 favored the granting of a CPCN, including the assertion that the unanimous recommendation of the Calvert County Board of County Commissioners that the CPCN be granted was invalid

and that, because the generating station would serve only the LNG operation at the terminal and not connect to the electric power grid1, it would have no public benefit that could offset the pollution that would occur from its fossil-fuel based generation.

PPRP included in its Report and testimony a substantial list of Conditions necessary, in its view, for the Project to comply with environmental requirements or to ameliorate negative economic impacts of the Project. It concluded that, with those Conditions, the generating station would comply with all applicable environmental requirements. The PSC Staff submitted a report dealing with the impact of the generating station on the electric power grid. Subject to its list of Conditions, the Staff concluded that the station would not adversely affect the grid. Dominion accepted the Conditions proposed by PPRP and the PSC Staff.

One of the major problems with which the parties and PSC had to contend, particularly in attempting to estimate and evaluate the economic and environmental impacts of the Project, was that the generating station was needed, and was intended to be used, solely to support the export operation – to run the compressors necessary to liquefy the domestic gas. No part of the electricity to be generated was to connect with the grid or be sold to customers. Because of that, in some important respects it was difficult to estimate the impact of the generating station as a stand-alone entity, apart from the

1 The electric grid is a complex network for distributing electricity throughout the country through interconnected generators of electricity, high-power transmission lines, and lower power distribution lines.

Free access — add to your briefcase to read the full text and ask questions with AI

Accokeek, Mattawoman, Piscataway Creeks v. PSC, (Md. 2016).

Accokeek, Mattawoman, Piscataway Creeks v. PSC (Accokeek, Mattawoman, Piscataway Creeks v. PSC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Sugarloaf Citizens' Ass'n v. Department of Environment
686 A.2d 605 (Court of Appeals of Maryland, 1996)
Blue Bird Cab Co. v. Maryland Department of Employment Security
248 A.2d 331 (Court of Appeals of Maryland, 1968)
Mid-Atlantic Power Supply Ass'n v. Public Service Commission
760 A.2d 1087 (Court of Appeals of Maryland, 2000)
Eastern Diversified Properties, Inc. v. Montgomery County
570 A.2d 850 (Court of Appeals of Maryland, 1990)
Office of People's Counsel v. Maryland Public Service Commission
733 A.2d 996 (Court of Appeals of Maryland, 1999)
Maryland Overpak Corporation v. Mayor of Baltimore
909 A.2d 235 (Court of Appeals of Maryland, 2006)
Baltimore Gas & Electric Co. v. Public Service Commission
501 A.2d 1307 (Court of Appeals of Maryland, 1986)
Communications Workers of America v. Public Service Commission
36 A.3d 449 (Court of Appeals of Maryland, 2012)
Town of Easton v. Public Service Commission
838 A.2d 1225 (Court of Appeals of Maryland, 2003)
Stoddard v. State Merchant v. State
136 A.3d 843 (Court of Appeals of Maryland, 2016)
Cashcall, Inc. v. Maryland Commissioner of Financial Regulation
139 A.3d 990 (Court of Appeals of Maryland, 2016)
Hollingsworth v. Severstal Sparrows Point, LLC
141 A.3d 90 (Court of Appeals of Maryland, 2016)