Abbey/Land, LLC v. Glacier Constr. Partners, LLC

2019 MT 19, 433 P.3d 1230, 394 Mont. 135
CourtMontana Supreme Court
DecidedJanuary 29, 2019
DocketDA 17-0705
StatusPublished
Cited by10 cases

This text of 2019 MT 19 (Abbey/Land, LLC v. Glacier Constr. Partners, LLC) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Abbey/Land, LLC v. Glacier Constr. Partners, LLC, 2019 MT 19, 433 P.3d 1230, 394 Mont. 135 (Mo. 2019).

Opinion

Justice Beth Baker delivered the Opinion of the Court.

*1234***139¶1 In Abbey/Land LLC v. Interstate Mechanical, Inc. , 2015 MT 77, 378 Mont. 372, 345 P.3d 1032 [hereinafter Abbey/Land I ], we reversed and remanded the District Court's $12 million stipulated judgment against Glacier Construction Partners, LLC ("Glacier") in favor of Abbey/Land LLC ("Abbey/Land"). We remanded with instructions for the District Court to grant James River Insurance Company's ("James River") request to intervene to challenge the reasonableness of the confessed judgment and whether it was the product of collusion.

¶2 After discovery and a hearing on remand, the court determined that the confessed judgment was the product of collusion and was unreasonable. The court reduced the judgment to approximately $2.4 million and ordered Abbey/Land and Glacier to pay James River's attorney fees and costs associated with the proceedings. James River ***140appeals, and Abbey/Land and Glacier each cross-appeal. We address whether the District Court erred when it:

1. Found the $12 million confessed judgment unreasonable; and
2. Held that the settlement was the product of collusion.

Based on our analysis of these issues, we further address whether the District Court:

3. Fashioned a proper remedy by opting to reduce the settlement amount, rather than dismissing the action; and
4. Properly awarded attorney fees and costs to James River.

¶3 We affirm the District Court's findings that the confessed judgment was unreasonable and the product of collusion. On the basis of those findings, we reverse and remand the District Court's amended judgment with instructions to dismiss Abbey/Land's claim with prejudice. We affirm the District Court's decision to grant attorney fees, although on different grounds. We reverse and remand the attorney fee award for the District Court to reduce the award. Finally, we affirm the District Court's decision to award costs, but reverse and remand for the District Court to recalculate the award to include only costs allowable under § 25-10-201, MCA.

PROCEDURAL AND FACTUAL BACKGROUND

¶4 This case, on appeal to the Court for a second time, is one of several actions in at least two counties and two United States district courts, as well as an arbitration proceeding, arising from the construction of a massive luxury home on Shelter Island, a small island in Flathead Lake, Montana. The instant action was originally filed in September 2009 over construction defects and associated problems.

¶5 Real estate developer Donald G. Abbey formed Abbey/Land in 2000 to purchase Shelter Island and related shoreline properties. Abbey/Land began to build a large residence on Shelter Island in 2001. After problems with the original contractor, Abbey formed Glacier to act as a new general contractor for the project. The construction on Shelter Island was Glacier's only project. Abbey is the sole owner, manager, and member of both Abbey/Land and Glacier.

¶6 On May 1, 2006, Abbey/Land and Glacier entered into a general contract for the construction of the Shelter Island residence. Abbey signed on behalf of both parties. The contract included an arbitration provision, limited the prevailing party's damages to actual damages, and specifically precluded any recovery of consequential damages. Under the contract, Glacier was reimbursed for the cost of all work it performed, including the cost of correcting defective work, but did not earn any profit. The District Court found that Glacier served more as ***141a construction agent for Abbey/Land than as an independent, at-risk general contractor.

¶7 Glacier subcontracted with Interstate Mechanical, Inc. ("Interstate") for the design and installation of the plumbing and heating-cooling systems for the house. Subsequent change orders increased the value of Interstate's original $1.4 million contract by approximately $1 million. Neither Abbey, Abbey/Land, nor Glacier employed an architect to oversee the changes to the project. Interstate initiated arbitration proceedings in 2009, alleging $806,917.95 in damages arising from Glacier's breach of contract, violations of the Montana Prompt Payment Act, unjust enrichment, constructive fraud, and negligence.

*1235Glacier counterclaimed against Interstate for $1,608,644.26 in damages due to Interstate's alleged faulty work that Glacier alleged caused damage to the Shelter Island residence and property. Glacier eventually terminated Interstate from the project.

¶8 Abbey/Land and Glacier filed the instant action in Flathead County on September 23, 2009-the day before the scheduled preliminary hearing in the arbitration action. Abbey/Land and Glacier brought claims against Interstate and other subcontractors, seeking compensatory and punitive damages caused by a pipe rupture in October 2008 that flooded the basement with an uncontrolled loss of water. The flooding water over-saturated the septic system drain field, which in turn contaminated the water well with E-coli bacteria. In addition, Abbey/Land claimed Interstate's deficient work caused various other damages, including leaks caused by frozen pipes, heat pumps that did not operate within the permit limits set by the Department of Environmental Quality, and a water treatment system that caused tons of salt and other contaminants to be deposited into the drain field. Abbey/Land and Glacier requested that the arbitration be stayed so they could recover consequential and punitive damages against Interstate in the state court action.

¶9 In response, Interstate sued in the United States District Court for the District of Montana to compel arbitration. The federal court ordered Glacier to arbitrate its dispute with Interstate and stayed the action in state court. On October 11, 2010, after the federal court compelled arbitration, Glacier made the first tender to its comprehensive general liability insurer James River to provide a defense. At that time Glacier was aligned as a plaintiff in this suit. Glacier represented to James River that damages were likely to be in the $1-2 million range. James River denied coverage.

¶10 In January 2011, the arbitrator awarded Glacier $414,021.11 in damages from Interstate. The arbitrator determined that some of ***142Glacier's claims were not for damages but for betterments, and he refused to make an award for those claims.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. B. Kelsey
2025 MT 173N (Montana Supreme Court, 2025)
MEIC v. Governor
2025 MT 112 (Montana Supreme Court, 2025)
JRN Holdings v. Dearborn Meadows
2021 MT 204 (Montana Supreme Court, 2021)
Sarens USA v. Lowery
D. Montana, 2021
JCCS v. Alborn
2020 MT 179 (Montana Supreme Court, 2020)
Gendron v. Montana University System
2020 MT 82 (Montana Supreme Court, 2020)
King v. State Farm Mut. Auto. Ins. Co.
2019 MT 208 (Montana Supreme Court, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
2019 MT 19, 433 P.3d 1230, 394 Mont. 135, Counsel Stack Legal Research, https://law.counselstack.com/opinion/abbeyland-llc-v-glacier-constr-partners-llc-mont-2019.