A. G. Schoonmaker Co. v. Resor

319 F. Supp. 933, 1970 U.S. Dist. LEXIS 10120
CourtDistrict Court, District of Columbia
DecidedSeptember 24, 1970
DocketCiv. A. No. 1760-70
StatusPublished
Cited by8 cases

This text of 319 F. Supp. 933 (A. G. Schoonmaker Co. v. Resor) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A. G. Schoonmaker Co. v. Resor, 319 F. Supp. 933, 1970 U.S. Dist. LEXIS 10120 (D.D.C. 1970).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

WADDY, District Judge.

On June 11, 1970, A. G. Schoonmaker Co., Inc. (“Plaintiff” hereinafter) instituted this action on a claim that Defendant public officials had acted arbitrarily, capriciously and unlawfully in respect to the purported cancellation of Invitation for Bids DAAK 02-70-B-1225 (“Army Invitation” hereinafter), and issuing and purporting to act on Invitation for Bids DAAK 02-70-B-3125 (“New Army Invitation” hereinafter), seeking declaratory and injunctive relief in essence prohibiting the award of any contract to anyone other than Plaintiff and requiring that a contract be issued under the Army Invitation to Plaintiff.

On June 12, 1970, this Court issued a Temporary Restraining Order enjoining the opening of bids on June 15; and on June 26, 1970, upon Findings of Fact and Conclusions of Law entered on that date, issued an Order and Preliminary Injunction restraining the opening of bids and the award of a contract under the New Army Invitation pending the determination of this cause.

On July 2, 1970, Bogue Electric Manufacturing Company (“Intervenor” hereinafter) filed a Motion for Leave to Intervene as a plaintiff and, by order of August 5, 1970, was permitted to intervene and to file a Complaint in this action. This Complaint seeks substantially the same relief sought by Plaintiff but claims that Intervenor, rather than Plaintiff, is entitled to be awarded a contract under the Army Invitation.

The trial of this cause commenced on August 20, 1970, pursuant to this Court’s Order of June 26, 1970, expediting these proceedings, and concluded on August 21. All parties adduced testimony through witnesses and the authenticity and admissibility of a substantial portion of the documentary evidence introduced at the trial was stipulated. The parties also stipulated as to the authenticity of other documents at the outset of trial which were subsequently admitted into evidence by the Court.

Upon consideration of all of the evidence, the stipulations of the parties and the arguments and memoranda of coun[935]*935sel for the parties, the Court makes the following:

FINDINGS OF FACT

1. Plaintiff is a corporation with its principal place of business in the State of California.

2. Defendant Stanley R. Resor is Secretary of the Army and is authorized to conduct all of the affairs of the Department of the Army, including' those of the United States Army Mobility Equipment Research and Development Center, Fort Belvoir, Virginia (“Army” hereinafter). Defendant Melvin R. Laird is Secretary of Defense and exercises direction, authority and control over the Department of Defense. Defendant Staats is Comptroller General of the United States and is charged with the control and direction of the General Accounting Office.

3. Intervenor is a corporation with its principal place of business in the State of New Jersey. Approximately ninety percent of its business is with the Government. Mr. William Guttenberg is its President and has been employed by Intervenor for twenty-six years.

4. In 1968, the Department of Defense developed a program for the standardization of 15 KW through 200 KW engine-driven generator sets for the Armed Services. The Department of Defense assigned responsibility for the procurement of 15 KW and 30 KW generator sets (the “Generator Sets” hereinafter) to the Army and responsibility for the procurement of 100 KW and 200 KW sets to the Department of the Air Force (“Air Force” hereinafter).

5. This program was and is administered by the Department of Defense Project Manager — Mobile Electric Power. The Project Manager for the program is Col. J. J. Rochefort, Jr. Mr. Bart Bingham is, and at all times pertinent hereto was, the chief of the procurement branch of the Project Manager’s Office. Mr. Bingham has, and at all times pertinent hereto had, responsibility for planning the procurement of the standardized generator sets with jurisdiction over both the Army and Air Force Invitations.

6. On February 18, 1969, the.Army issued Solicitation No. DAAK 02-69-R-2200, constituting the first step of a two-step, formally advertised, multi-year procurement of the Generator Sets, to Plaintiff, Intervenor and numerous other companies. Plaintiff and Intervenor devoted substantial time and effort and incurred substantial expense in developing technical proposals for the production of the Generator Sets in response to the Solicitation, and, after their respective technical proposals had been accepted by • the Army, devoted substantial time and effort and incurred substantial expense in developing their respective bids in response to the Army Invitation.

7. In response to the said Solicitation, the Army received technical proposals from Intervenor, Libby Welding Company, Inc. (“Libby” hereinafter)' and two other companies, as well as Plaintiff. The technical proposals of Plaintiff, Intervenor and Libby, but not those of the two other companies, were found acceptable.

8. On or about December 19, 1969, the Army issued the Army Invitation (DAAK-: 02-70-B-1225) to Plaintiff, Intervenor and Libby, as the second step of the aforesaid two-step procurement. The Army Invitation called for the production and delivery of both Pre-Production Models (for testing) and Production Models of the Generator Sets. The first unit of each of the four Pre-Production Models was required to be delivered 300 days after award of a contract and the remaining Pre-Production Models 420 days after award. The first 92 Production Models were required to be delivered 712 days after award and the balance of the Production Models over a period of approximately three to five years. The Invitation also required certain materials and components ancillary to the Pre-Production Models, data items and, in addition, possible additional Production Models to be purchased at the option of the Army. The Army In[936]*936vitation provided that bids would be opened on February 27, 1970. After their respective technical proposals had been accepted by the Army, both Plaintiff and Intervenor devoted substantial time and effort and incurred substantial expense in developing their respective bids in response to the Army Invitation.

9. The Army Invitation provided separate and distinct pricing spaces for the Pre-Production and the Production Models of like Generator Sets. It also contained an express “NOTE”, instructing bidders to include certain items of cost in the price of the Pre-Production Models only and not in the price of the Production Models. Although the PreProduction and Production Models bear the same “MEP” and “FSN” numbers, the Army Invitation contains different descriptions for the Pre-Production Models than the Production Models; provides that only the Pre-Production Models are to be equipped with certain testing equipment, including regulator-exciter systems, slip rings and brush assemblies; and different rules governing how they are to be built. Mr. Edward Prada, Chief of the Testing and Evaluation Division of the Army and Program Manager for the Army’s generator set program, acknowledged that the PreProduction Models are different in some ways from Production Models of the Generator Sets.

10. On January 6, 1970, the Army held a conference of bidders “for the purpose of clarification of any and all questions regarding any contractual aspect” of the Army Invitation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Emery Worldwide Airlines, Inc. v. United States
49 Fed. Cl. 211 (Federal Claims, 2001)
Trojan, Inc. v. Shat-R-Shield, Inc.
885 F.2d 854 (Federal Circuit, 1989)
Essex Electro Engineers, Inc. v. United States
31 Cont. Cas. Fed. 71,391 (Court of Claims, 1983)
Merriam v. Kunzig
347 F. Supp. 713 (E.D. Pennsylvania, 1972)
A. G. Schoonmaker Co. v. Resor
445 F.2d 726 (D.C. Circuit, 1971)
Lombard Corporation v. Resor
321 F. Supp. 687 (District of Columbia, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
319 F. Supp. 933, 1970 U.S. Dist. LEXIS 10120, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-g-schoonmaker-co-v-resor-dcd-1970.