A. F. Conner & Sons, Inc. v. Tri-County Water Supply Corp.

561 S.W.2d 466, 21 Tex. Sup. Ct. J. 160, 1978 Tex. LEXIS 298
CourtTexas Supreme Court
DecidedJanuary 18, 1978
DocketB-6343
StatusPublished
Cited by7 cases

This text of 561 S.W.2d 466 (A. F. Conner & Sons, Inc. v. Tri-County Water Supply Corp.) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A. F. Conner & Sons, Inc. v. Tri-County Water Supply Corp., 561 S.W.2d 466, 21 Tex. Sup. Ct. J. 160, 1978 Tex. LEXIS 298 (Tex. 1978).

Opinions

ON MOTION FOR REHEARING

STEAKLEY, Justice.

Our prior opinion delivered under date of September 27, 1977, is withdrawn and the following opinion is substituted therefor.

Tri-County Water Supply Corporation sued A. F. Conner and Sons, Inc., and Fidelity & Deposit Company of Maryland, the surety on Conner’s performance bond, for damages resulting from Conner’s alleged breach of a contract to construct a water [467]*467distribution system. After a jury trial, and upon the basis of findings later noted, the trial court rendered judgment in favor of Tri-County for $389,815.85 plus prejudgment interest at the rate of six per cent per annum from December 13, 1970 in the sum of $75,282.25, and that Fidelity & Deposit recover over and against Conner. The Court of Civil Appeals ordered a remittitur of $119,542.33 and otherwise affirmed the trial court’s judgment. 541 S.W.2d 856. We reverse these judgments and remand the cause for a new trial.

Tri-County Water Supply Corporation is a non-profit corporation authorized to own and operate a water supply system in the rural area of eastern Falls County, Texas. In February of 1968, Tri-County contracted with Duff Engineers to make an engineering study of the feasibility of constructing a water supply system. Upon a favorable recommendation, Tri-County authorized Duff Engineers to solicit bids for the construction of the system. In October of 1968, Tri-County accepted the bid of A. F. Conner & Sons, Inc., and entered into a contract under which Conner was to construct the water supply system consisting of five pump stations and approximately 178 miles of plastic pipeline. The contract provided that all workmanship and materials would be of good quality and that upon completion of the work Tri-County would pay Conner the sum of $522,480.13, of which $389,815.53 was in payment for the pipeline. The contract also obligated Conner to replace or repair any defective material or equipment discovered within one year of completion. Duff Engineers was designated as the inspecting engineering firm. The certificate of completion was executed June 4, 1970, and thereafter numerous leaks and other defects were discovered. It appears that Conner ceased repairing the leaks and other defects on December 13, 1970.

Tri-County sued Conner in April of 1971, and alleged that the defects in the system rendered it “not reasonably fit for the purpose of the water distribution system” and that Conner had failed to discharge the contractual duty to repair the system and remedy the defects. Tri-County sought damages of $389,815.85, the value of the pipeline. There have been two trials. Upon the first trial in December, 1972, the jury found that the materials and workmanship used by Conner were not of good quality; but that Conner had substantially performed the contract, and that the reasonable cost of repairing and replacing the defective pipe and adapters was $4,853.77. The trial court rendered judgment on the verdict for Tri-County in the amount of $4,853.77; but upon the subsequent motion of Tri-County the trial court set aside this judgment and ordered a new trial on grounds not herein material.

One of the witnesses at the first trial was Mr. William Garner who had been an employee of Duff Engineers for some time and was an experienced inspector. He was directly responsible for supervising and inspecting the construction of the system. At the first trial, Garner testified that he had visited the job site on at least thirty-seven separate occasions and had personally inspected the construction. He testified that numerous leaks were discovered throughout the system after the June 4, 1970 completion date. He further testified that he believed the leaks would not stop and that, in his opinion, the workmanship and materials used by Conner were bad. Garner also said he believed that the only way to put the pipeline in “A-l” shape would be to lay a replacement line and completely abandon the Conner pipeline. Garner also stated that, in his opinion, the line as constructed had no value.

After the first trial concluded, Tri-County expanded the water supply system. This new addition began from the same well as the old system and was some 110 to 120 miles long. It ran in a different direction from the old system and shared only the well in common with the old system. The new system was also designed by Duff Engineers and was supervised and inspected by Duff’s employee, Gamer. Construction was by Brazos Construction Company. The new system differed from the old in that an aerator was designed and installed to cool the water before it went into the plastic [468]*468pipeline. It was also shown that the temperature of the water affects the strength of the pipe, the amount it contracts and expands, and the pressure at which the system is operated.

The second trial was set for Monday, January 28,1974. On the preceding Friday, January 25, counsel for Tri-County advised Conner and Fidelity that Garner was in a Waco hospital and would be unable to testify; and that arrangements had been made to have his testimony at the first trial transcribed for introduction at the forthcoming trial. On the same date Tri-County, by written motion, requested the trial court to direct the court reporter to transcribe Garner’s testimony at the first trial. In its motion Tri-County alleged that Garner “would be unable to appear as a witness in this cause scheduled for trial for the week of January 28,1974, and that he was physically unable to have his deposition taken and that his testimony is essential to plaintiff’s case and that his testimony was developed in the prior trial which commenced in December, 1973, [sic] and that defendant’s counsel had full right to cross examination and therefore his testimony at the former trial is admissible during the trial commencing January 28th.” The trial judge granted the motion and issued the order.

When the cause was called for trial on January 28, counsel for Fidelity made an objection to the proposed introduction of Garner’s prior testimony and moved for a continuance until such time as Garner’s deposition could be taken, or he could appear at trial. Counsel for Fidelity represented to the court that Garner was no longer in the employ of Duff Engineers and contended that the affidavit and testimony of counsel for Conner would further support his motions. The trial court then heard evidence of the following facts and circumstances:

1)On Sunday, January 20, counsel for Tri-County visited Garner at his home and reviewed his testimony. At that time Garner seemed well and fully able to testify. Counsel reviewed the entire testimony with Garner and specifically stressed the question of the system’s value. Garner’s answers were the same as those he had given at the first trial;
2) On Thursday, January 24, counsel for Tri-County learned that Garner was in the hospital and went immediately to see him. Garner informed counsel that he was scheduled to have a mye-logram on Monday the 28th and surgery on the 29th to correct a low back condition. Garner further said that he was unable to be deposed because he was sedated, “full of shots,” and suffering from diabetes;
3) On Friday, January 25, counsel for Tri-County verified Garner’s continued hospitalization with his wife and then called counsel for Conner and Fidelity separately and informed them of Garner’s unavailability and the motion to transcribe his prior testimony;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moore v. State
82 S.W.3d 399 (Court of Appeals of Texas, 2002)
James Gibson Moore, III v. State
Court of Appeals of Texas, 2002
Briones v. Solomon
769 S.W.2d 312 (Court of Appeals of Texas, 1989)
Golleher v. Herrera
651 S.W.2d 329 (Court of Appeals of Texas, 1983)
A. F. Conner & Sons, Inc. v. Tri-County Water Supply Corp.
561 S.W.2d 466 (Texas Supreme Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
561 S.W.2d 466, 21 Tex. Sup. Ct. J. 160, 1978 Tex. LEXIS 298, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-f-conner-sons-inc-v-tri-county-water-supply-corp-tex-1978.